Revision as of 22:21, 16 May 2024 edit2601:c4:4082:86e0:25a9:fa8a:7c5:b8af (talk)No edit summaryTags: Mobile edit Mobile web edit← Previous edit | Latest revision as of 15:35, 25 December 2024 edit undo88.138.234.73 (talk) Fixed a formatting error (I'm new at this) | ||
(43 intermediate revisions by 16 users not shown) | |||
Line 1: | Line 1: | ||
{{Short description|French subway network}} | {{Short description|French subway network project}} | ||
{{Use dmy dates|date=May 2022}} | {{Use dmy dates|date=May 2022}} | ||
{{Infobox Public transit | {{Infobox Public transit | ||
| box_width = |
| box_width = 280px | ||
| name = Grand Paris Express | | name = Grand Paris Express | ||
| image = Grand paris express.svg | | image = Grand paris express.svg | ||
| alt = | | alt = | ||
| imagesize = |
| imagesize = 280px | ||
⚫ | | caption = The planned network of the Grand Paris Express | ||
| image2 = | | image2 = | ||
| alt2 = | | alt2 = | ||
Line 14: | Line 15: | ||
| locale = ] | | locale = ] | ||
| transit_type = ] | | transit_type = ] | ||
| |
| began_operation = 24 June 2024 (Line 14 extension) | ||
| operator = ] for ] and ] <br/> ORA (], ], ]) for ]<ref name="Le Parisien">{{cite web |url=https://www.leparisien.fr/info-paris-ile-de-france-oise/transports/grand-paris-express-la-ligne-15-sud-sera-exploitee-par-ratp-dev-a-partir-de-fin-2025-30-06-2023-JBTTQ6F23BHURGXAOBFLTH734M.php |title=Grand Paris Express : la ligne 15 sud sera exploitée par RATP Dev à partir de fin 2025 |publisher=] |access-date=2024-12-25 }}</ref> <br/> | |||
| operator = Will be retained by Ile de France Mobilités after a call for tenders | |||
] for ], ] and ]<ref name="Le Figaro">{{cite web |url=https://www.lefigaro.fr/societes/keolis-remporte-le-droit-d-exploitation-de-la-ligne-18-du-grand-paris-express-20240618 |title=Keolis remporte le droit d’exploitation de la ligne 18 du Grand Paris Express |publisher=] |access-date=2024-12-25 }}</ref> | |||
| owner = ] | | owner = ] | ||
| lines = 6 (4 new lines, 2 extended lines) | | lines = 6 (4 new lines, 2 extended lines) | ||
Line 25: | Line 27: | ||
| track_gauge = {{Track gauge|sg|allk=on}} | | track_gauge = {{Track gauge|sg|allk=on}} | ||
| el = | | el = | ||
| map = ] | |||
⚫ | | |
||
| map_state = collapsed | |||
}} | }} | ||
'''Grand Paris Express''' is a |
The '''Grand Paris Express''' is a project consisting of new rapid transit lines and the extension of existing lines being built in the ] region of France. The project comprises four new lines for the ], plus extensions of the existing Lines ] and ]. A total of {{convert|200|km|mi}} of new tracks and 68 new stations are to be added, serving a projected 2 million passengers a day.<ref name="sgp_en">{{Cite web|title = Grand Paris Express, the largest transport project in Europe|url = https://www.societedugrandparis.fr/info/grand-paris-express-largest-transport-project-europe-1061|access-date = 11 January 2020|website = Société du Grand Paris|archive-date = 11 April 2022|archive-url = https://web.archive.org/web/20220411214218/https://www.societedugrandparis.fr/info/grand-paris-express-largest-transport-project-europe-1061|url-status = dead}}</ref> | ||
⚫ | {{citation needed span|date=July 2024|text=The new lines were originally indexed by colour (Red Line, Pink Line, Green Line, Blue Line), but this was changed in 2013 to continue the numbering convention that the ] uses. They are therefore now known as ], ], ] and ].}} The constructed lines are planned to open in stages, starting with the Line 14 extension in June 2024, until 2030.<ref name="stif.org">{{cite web|url=http://www.stif.org/developpements-avenir/nouveau-grand-paris/metro/projets/lignes-16-17-18-du-nouveau-grand-paris-4899.html |title=Création des nouvelles lignes reliant le Nouveau Grand Paris |work=] |language=fr |url-status=dead |archive-url=https://web.archive.org/web/20141119113117/http://www.stif.org/developpements-avenir/nouveau-grand-paris/metro/projets/lignes-16-17-18-du-nouveau-grand-paris-4899.html |archive-date=19 November 2014 }}</ref> | ||
⚫ | Since August 2013, the New Grand Paris steering committee has met quarterly.<ref>{{Cite web|title = Installation du comité de pilotage du Nouveau Grand Paris|url = http://www.developpement-durable.gouv.fr/Installation-du-comite-de-pilotage.html|website = developpement-durable.gouv.fr|access-date = 21 June 2015|last = Ministère de l'écologie, du développement durable et de l'énergie|date = 28 August 2013|archive-date = 22 June 2015|archive-url = https://web.archive.org/web/20150622024544/http://www.developpement-durable.gouv.fr/Installation-du-comite-de-pilotage.html|url-status = dead}}</ref> The first public inquiry, focused on the southern section of Line 15 from {{stl|Paris Métro|Pont de Sèvres}} to ], was held from October to mid-November 2013.<ref>{{Cite web|title=Métro ligne 15 – STIF |url=http://www.stif.org/developpements-et-avenir/nouveau-grand-paris/metro/projets/article/metro-ligne-quinze.html |website=stif.org |access-date=21 June 2015 |url-status=dead |archive-url=https://web.archive.org/web/20150608014202/http://www.stif.org/developpements-et-avenir/nouveau-grand-paris/metro/projets/article/metro-ligne-quinze.html |archive-date=8 June 2015 }}</ref> Work on Line 15 began in 2015. Its first section between {{stl|Paris Métro|Pont de Sèvres}} Métro station and Noisy–Champs ] station was scheduled at that time to open around 2020, but this has now been pushed back to 2025. This line was first proposed in the ''Orbival'' project, then integrated into the ]. | ||
⚫ | The new lines were originally indexed by colour (Red Line, Pink Line, Green Line), but this changed in 2013 to continue the numbering convention that the ] uses. |
||
⚫ | Since August 2013, the New Grand Paris steering committee has met quarterly.<ref>{{Cite web|title = Installation du comité de pilotage du Nouveau Grand Paris|url = http://www.developpement-durable.gouv.fr/Installation-du-comite-de-pilotage.html|website = developpement-durable.gouv.fr|access-date = 21 June 2015|last = Ministère de l'écologie, du développement durable et de l'énergie|date = 28 August 2013}}</ref> The first public inquiry, focused on the southern section of Line 15 from {{stl|Paris Métro|Pont de Sèvres}} to ], was held from October to mid-November 2013.<ref>{{Cite web|title=Métro ligne 15 – STIF |url=http://www.stif.org/developpements-et-avenir/nouveau-grand-paris/metro/projets/article/metro-ligne-quinze.html |website=stif.org |access-date=21 June 2015 |url-status=dead |archive-url=https://web.archive.org/web/20150608014202/http://www.stif.org/developpements-et-avenir/nouveau-grand-paris/metro/projets/article/metro-ligne-quinze.html |archive-date=8 June 2015 }}</ref> Work on |
||
<!--== Nertwork == | <!--== Nertwork == | ||
]--> | ]--> | ||
Line 41: | Line 42: | ||
{{Main|Paris Métro Line 11}} | {{Main|Paris Métro Line 11}} | ||
{{Paris Métro Line 11}} | {{Paris Métro Line 11}} | ||
To ensure better commuter service to the inner |
To ensure better commuter service to the inner northeastern suburbs, a six-station, {{convert|5.4|km|adj=on}} eastern extension of Line 11, not considered part of the Grand Paris Express project, opened from Mairie des Lilas to ]. The scheme was initially lobbied for by the local authorities of these suburbs, and was adopted during the 2007 review of the Île-de-France Transportation Plan. Work on the extension to ''Rosny – Bois-Perrier'' started in 2015<ref name=francetvinfo.2023-1725603>{{Cite web|title=Prolongement de la ligne 11: le tunnelier inauguré, six nouvelles stations de métro en 2023|url=https://france3-regions.francetvinfo.fr/paris-ile-de-france/seine-saint-denis/prolongement-ligne-11-tunnelier-inaugure-six-nouvelles-stations-metro-2023-1725603.html|access-date=6 June 2020|website=France 3 Paris Ile-de-France|language=fr|archive-date=30 October 2020|archive-url=https://web.archive.org/web/20201030204525/https://france3-regions.francetvinfo.fr/paris-ile-de-france/seine-saint-denis/prolongement-ligne-11-tunnelier-inaugure-six-nouvelles-stations-metro-2023-1725603.html|url-status=live}}</ref> and opened on 13 June 2024.<ref name="line11ext1open">{{cite press release |date=13 June 2024 |title=Focus on the extension of line 11 |url=https://www.ratp.fr/en/extension-metro-line-11 |agency=] |access-date=2024-06-13}}</ref> It provides connections with the ] and an eventual extension of ], which better links central Paris with the commuter hub of ]. | ||
{| class="wikitable" style="margin-left:auto; margin-right:auto;" | {| class="wikitable" style="margin-left:auto; margin-right:auto;" | ||
|+ List of new stations and connections (with |
|+ List of new stations and connections (with opening dates) | ||
|- | |- | ||
! New stations | ! New stations | ||
! Towns served | ! Towns served | ||
! Connection | ! Connection | ||
! |
! Opening<br/>date<ref name=francetvinfo.2023-1725603/><ref name="line11ext1open"/> | ||
|- | |- | ||
| Serge Gainsbourg | | Serge Gainsbourg | ||
| Les Lilas | | Les Lilas | ||
| | | | ||
| rowspan="6" | 2024 | | rowspan="6" | 13 June 2024 | ||
|- | |- | ||
| Place Carnot | | Place Carnot | ||
Line 78: | Line 79: | ||
=== Revisions in the Grand Paris Express Plan and possible automation === | === Revisions in the Grand Paris Express Plan and possible automation === | ||
⚫ | A revised plan for the proposed Grand Paris Express subway system was unveiled on 6 March 2013, and calls for a second extension of Line 11 to be built towards {{station|Noisy–Champs}}, this second extension being considered part of the Grand Paris Express project. The target opening date is 2030, but might be pushed back. Should the second extension be built, Line 11 will eventually be fully automated.<ref>{{cite news |url=http://www.lesechos.fr/06/03/2013/lesechos.fr/0202626990936_-nouveau-grand-paris----l-etat-engage-27-milliards-pour-le-metro-parisien.htm |title=Nouveau Grand Paris» : l'État engage 27 milliards pour le métro parisien |date=6 March 2013 |language=fr |access-date=25 June 2016 |archive-date=3 March 2016 |archive-url=https://web.archive.org/web/20160303222856/http://www.lesechos.fr/06/03/2013/lesechos.fr/0202626990936_-nouveau-grand-paris----l-etat-engage-27-milliards-pour-le-metro-parisien.htm |url-status=live }}</ref> Automatic train operation was not implemented with the Rosny extension, although the RATP and STIF had considered the possibility of adding it later on. | ||
⚫ | ===Rolling stock=== | ||
⚫ | A revised plan for the proposed Grand Paris Express subway system was unveiled on 6 March 2013, and calls for a second extension of Line 11 to be built towards {{station|Noisy–Champs}}. The target opening date is 2030, but might be pushed back. Should the second extension be built, Line 11 will eventually be fully automated.<ref>{{cite news|url=http://www.lesechos.fr/06/03/2013/lesechos.fr/0202626990936_-nouveau-grand-paris----l-etat-engage-27-milliards-pour-le-metro-parisien.htm |title=Nouveau Grand Paris» : l'État engage 27 milliards pour le métro parisien |date=6 March 2013 |language=fr}}</ref> Automatic train operation |
||
]-trainset, this model was fully retired from the line on 23 May 2024.]] | |||
]-trainset, which entered on service on June 1, 2023.]] | |||
Line 11 was the first metro line converted to rubber-tyred pneumatic operation, and its first set of rubber-tyred rolling stock was the ], which operated from October 1956 through January 1999. They were then replaced by refurbished ] stock from Line 4. The MP 55 stock consisted of 4 carriages, as did the replacement MP 59 stock. One ] of ] was in service on the 11 as well. | |||
⚫ | === |
||
As of March 2013, it was expected that additional ] stock will be used for line 11. Unlike lines 14 and 4, these MP 14's will be manually driven and will replace the ]. As of October 2022, the trains are currently in test at the Rosny extension. Passenger service started in June 2023. | |||
] planned to replace the aging fleet of Line 11 with {{nobr|]}} series trains around the time of the opening of the extension to ]. The new trains are driver-operated as the MP 59 fleet was, but they are 5 cars long and have open gangways.<ref name="stif_enquete_publique">Press release: , STIF, 13 February 2013</ref><ref>{{cite web|url=http://beta.leparisien.fr/info-paris-ile-de-france-oise/transports/le-metro-change-de-couleur-11-12-2018-7965513.php|title=Le métro parisien passe au bleu|website=Le Parisien|date=11 December 2018|first=Jila|last=Varoquier|access-date=12 December 2018|language=fr}}</ref> | |||
An initial 20 trains were ordered in February 2018, with an additional 19 trains ordered in July 2021.<ref name=":0" /> Production began in late 2020, and testing in summer 2021.<ref name=":0" /> | |||
The first new ] CC (manual transit) were deployed in June 2023, with four new trains entering service each Tuesday to replace four ] transferred to the Rosny-sous-Bois workshop on Monday nights to be retired. Twenty new ]-manual transit were deployed by summer 2023, with an additional nineteen new trains deployed in spring 2024 to serve the extension to {{stn|Rosny–Bois-Perrier}}.<ref>{{Cite web|url=https://www.leparisien.fr/info-paris-ile-de-france-oise/transports/grand-paris-la-ligne-11-du-metro-fait-sa-revolution-en-sequipant-enfin-de-rames-neuves-09-06-2023-ZLPHHVSMONHNLE4HV4X7NJGE34.php|title=Grand Paris : la ligne 11 du métro fait sa révolution en s'équipant (enfin) de rames neuves|trans-title=Grand Paris: line 11 of the metro is undergoing a revolution by (finally) equipping itself with new trains|language=French|last=Hasse|first=Benoît|date=2023-07-09}} Retrieved 2023-07-09</ref> The ceremonial final runs of the MP 59 took place on 23 May 2024, with #'s 6069, 6073 and 6087 being the final three to be withdrawn. | |||
{{Clear}} | {{Clear}} | ||
Line 90: | Line 98: | ||
{{Main|Paris Métro Line 14}} | {{Main|Paris Métro Line 14}} | ||
=== Northern extension of |
=== Northern extension of Line 14 === | ||
The automated '''Line 14''' was extended north from {{stl|Paris Métro|Saint-Lazare}} to ], with the primary aim of reducing overcrowding on ].<ref name=extension>{{cite web|title=Prolongement de la ligne 14 de Saint-Lazare à Mairie de Saint-Ouen|url=http://www.ratp.fr/fr/ratp/c_11634/carte-d-identite/|publisher=RATP|language=fr|access-date=17 November 2011}}</ref> The adopted solution connects both branches of |
The automated '''Line 14''' was extended north from {{stl|Paris Métro|Saint-Lazare}} to ], with the primary aim of reducing overcrowding on ].<ref name=extension>{{cite web|title=Prolongement de la ligne 14 de Saint-Lazare à Mairie de Saint-Ouen|url=http://www.ratp.fr/fr/ratp/c_11634/carte-d-identite/|publisher=RATP|language=fr|access-date=17 November 2011|archive-date=10 September 2013|archive-url=https://web.archive.org/web/20130910220025/http://www.ratp.fr/fr/ratp/c_11634/carte-d-identite/|url-status=dead}}</ref> The adopted solution connects both branches of Line 13 to Line 14, with stations at {{stl|Paris Métro|Porte de Clichy}} on the Asnières – Gennevilliers branch and {{stl|Paris Métro|Mairie de Saint-Ouen}} on the Saint-Denis branch. An additional station connects with the {{stl|Réseau Express Régional|Saint-Ouen}} ] station, and another with the ] lines at {{stn|Pont Cardinet}}, and the final one with the ] at {{stn|Saint-Denis–Pleyel}}. Construction on the extension began in 2014, with an aim of completion by 2019.<ref>{{Cite web|url=https://www.leparisien.fr/archives/grand-paris-le-prolongement-de-la-ligne-14-du-metro-retarde-a-mi-2019-23-10-2014-4236029.php|title=Grand Paris : le prolongement des lignes 12 et 14 du métro retardé de deux ans|first=Par Julien Duffé Le 23 octobre 2014|last=à 13h09|date=23 October 2014|website=Le Parisien|access-date=18 May 2022|archive-date=18 May 2022|archive-url=https://web.archive.org/web/20220518234000/https://www.leparisien.fr/archives/grand-paris-le-prolongement-de-la-ligne-14-du-metro-retarde-a-mi-2019-23-10-2014-4236029.php|url-status=live}}</ref> Completion was later pushed back to 2020 after flooding from the water table stopped the tunnel works for a year. The COVID-19 pandemic then further delayed the opening to December 2020.<ref name=lemonde_20210305_a>{{Cite web|url=https://www.lemonde.fr/economie/article/2021/03/05/a-paris-la-ligne-14-du-metro-en-plein-essor-la-13-toujours-aussi-chargee_6072116_3234.html|title=A Paris, la ligne 14 du métro en plein essor, la 13 toujours aussi chargée|date=5 March 2021|work=Le Monde|access-date=5 March 2021|archive-date=5 March 2021|archive-url=https://web.archive.org/web/20210305222740/https://www.lemonde.fr/economie/article/2021/03/05/a-paris-la-ligne-14-du-metro-en-plein-essor-la-13-toujours-aussi-chargee_6072116_3234.html|url-status=live}}</ref> The extension opened on 24 June 2024, just a month before the ].<ref name="24 June 2024">{{Cite web |last1=Compagnon |first1=Sébastian |last2=Gairaud |first2=Marie-Anne |date=2024-06-24 |title=Ligne 14 de Saint-Denis - Pleyel à l'aéroport d'Orly : "Ces nouvelles stations, c'est vraiment waouh !" |url=https://www.leparisien.fr/info-paris-ile-de-france-oise/transports/ligne-14-de-saint-denis-pleyel-a-laeroport-dorly-ces-nouvelles-stations-cest-vraiment-waouh-24-06-2024-XCDH4PAG2RFYTLS4Z4VIVJT66Y.php |access-date=2024-06-24 |website=leparisien.fr |language=fr-FR}}</ref> | ||
=== Southern extension of |
=== Southern extension of Line 14 === | ||
Line 14 |
Line 14 was also extended south from {{stn|Olympiades}} towards ]. The extension travels southeastward from Olympiades to {{stl|Paris Métro|Maison Blanche}}, interchanging with ]'s ] branch, and opened on 24 June 2024 (again, just a month before the 2024 Summer Olympics).<ref name="24 June 2024" /> | ||
With both extensions complete, it is expected that Line 14 will eventually be merged into the proposed Grand Paris Express system.<ref>{{in lang|fr}} http://www.symbioz.net/index.php?id=99 {{Webarchive|url=https://web.archive.org/web/20210116171330/https://www.symbioz.net/index.php?id=99 |date=16 January 2021 }} Grand Paris Express</ref> | |||
=== Rolling stock === | === Rolling stock === | ||
], of the same type as for line 14]] | ], of the same type as for line 14]] | ||
In February 2012 the STIF announced that with the two extensions planned, the brand new ] class of rolling stock |
In February 2012 the STIF announced that with the two extensions planned, the brand new ] class of rolling stock would replace the ] and ] stock on Line 14 starting from 2020. This new stock is in eight-car train formations, longer than previously employed anywhere on the Paris Métro but which the length of all Line 14 stations was planned for. The previous MP 89 CA and MP 05 stock was then reassigned to the newly automated line 4, alongside some 6-car MP 14s. They replaced its manually driven ] rolling stock, which was refurbished before going to line 6 to replace the aging ] rolling stock.<ref name="stif.info">{{cite web |url=http://www.stif.info/IMG/pdf/STIF_-_Modernisation_du_metro.pdf |title=Archived copy |access-date=8 March 2012 |url-status=dead |archive-url=https://web.archive.org/web/20121014065246/http://www.stif.info/IMG/pdf/STIF_-_Modernisation_du_metro.pdf |archive-date=14 October 2012 }} Modernisation du métro (in French). STIF. Retrieved 11 February 2012</ref> | ||
{{Clear}} | {{Clear}} | ||
Line 117: | Line 125: | ||
| locale = | | locale = | ||
| year_opened = 2025–2030 | | year_opened = 2025–2030 | ||
| terminus = {{station|Noisy–Champs}}<br/>] | | terminus = {{station|Noisy–Champs}}<br/>] | ||
| operator_org = Will be retained by Ile de France Mobilités after a call for tenders | | operator_org = Will be retained by Ile de France Mobilités after a call for tenders | ||
| conducting_system = Automated | | conducting_system = Automated | ||
Line 132: | Line 140: | ||
}} | }} | ||
{{Paris Métro Line 15}} | {{Paris Métro Line 15}} | ||
'''Line 15''' will be a high-capacity underground rail line, providing a new ring line around Paris in the departments of ], Val-de-Marne and ]. It will enable direct journeys between the suburbs, bypassing central Paris.<ref>{{Cite web|title = Acte motivé|url = https://www.societedugrandparis.fr/liste-documents-multimedia/documents-de-reference|website = societedugrandparis.fr|access-date = 21 June 2015|date = 26 May 2011|pages = 34, 35, 45|archive-url = https://web.archive.org/web/20150708120938/http://www.societedugrandparis.fr/liste-documents-multimedia/documents-de-reference|archive-date = 8 July 2015|url-status = dead}}</ref><ref>{{Cite web|title = ratp.fr – The Greater Paris Express project|url = http://www.ratp.fr/en/ratp/r_33841/the-greater-paris-express-project/|website = ratp.fr|access-date = 21 June 2015|archive-url = https://web.archive.org/web/20150801074659/http://www.ratp.fr/en/ratp/r_33841/the-greater-paris-express-project/|archive-date = 1 August 2015|url-status = dead}}</ref> The configuration of the line is very similar to that of the ], proposed by the ] in 2006. It was later included in the red line project of the Grand Paris public transportation network, introduced by French President ] in 2009. In March 2013, the "New Grand Paris" project was announced by the Prime Minister at the time, ]. At this time, the line acquired its current line 15 naming.<ref>{{Cite web|title = Le Nouveau Grand Paris : pour une région compétitive et solidaire|url = http://archives.gouvernement.fr/ayrault/premier-ministre/le-nouveau-grand-paris-pour-une-region-competitive-et-solidaire.html|website = archives.gouvernement.fr|access-date = 21 June 2015|date = 6 March 2013}}</ref> | '''Line 15''' will be a high-capacity underground rail line, providing a new ring line around Paris in the departments of ], Val-de-Marne and ]. It will enable direct journeys between the suburbs, bypassing central Paris.<ref>{{Cite web|title = Acte motivé|url = https://www.societedugrandparis.fr/liste-documents-multimedia/documents-de-reference|website = societedugrandparis.fr|access-date = 21 June 2015|date = 26 May 2011|pages = 34, 35, 45|archive-url = https://web.archive.org/web/20150708120938/http://www.societedugrandparis.fr/liste-documents-multimedia/documents-de-reference|archive-date = 8 July 2015|url-status = dead}}</ref><ref>{{Cite web|title = ratp.fr – The Greater Paris Express project|url = http://www.ratp.fr/en/ratp/r_33841/the-greater-paris-express-project/|website = ratp.fr|access-date = 21 June 2015|archive-url = https://web.archive.org/web/20150801074659/http://www.ratp.fr/en/ratp/r_33841/the-greater-paris-express-project/|archive-date = 1 August 2015|url-status = dead}}</ref> The configuration of the line is very similar to that of the ], proposed by the ] in 2006. It was later included in the red line project of the Grand Paris public transportation network, introduced by French President ] in 2009. In March 2013, the "New Grand Paris" project was announced by the Prime Minister at the time, ]. At this time, the line acquired its current line 15 naming.<ref>{{Cite web|title = Le Nouveau Grand Paris : pour une région compétitive et solidaire|url = http://archives.gouvernement.fr/ayrault/premier-ministre/le-nouveau-grand-paris-pour-une-region-competitive-et-solidaire.html|website = archives.gouvernement.fr|access-date = 21 June 2015|date = 6 March 2013|archive-date = 22 June 2015|archive-url = https://web.archive.org/web/20150622024714/http://archives.gouvernement.fr/ayrault/premier-ministre/le-nouveau-grand-paris-pour-une-region-competitive-et-solidaire.html|url-status = dead}}</ref> | ||
Line 15 is planned to open in phases from 2025 through 2030.<ref>{{cite web|url=https://www.societedugrandparis.fr/wp-content/uploads/2015/03/150305_sgp-tp_brochure-issylesmoulineaux-a5-pdf.pdf|title=Grand Paris Express|access-date=29 December 2017|archive-url=https://web.archive.org/web/20170811183927/https://www.societedugrandparis.fr/wp-content/uploads/2015/03/150305_sgp-tp_brochure-issylesmoulineaux-a5-pdf.pdf|archive-date=11 August 2017|url-status=dead}}</ref> It will create a loop connecting Noisy–Champs to Champigny, passing through ], ], ], ], ] and ]. | Line 15 is planned to open in phases from 2025 through 2030.<ref>{{cite web|url=https://www.societedugrandparis.fr/wp-content/uploads/2015/03/150305_sgp-tp_brochure-issylesmoulineaux-a5-pdf.pdf|title=Grand Paris Express|access-date=29 December 2017|archive-url=https://web.archive.org/web/20170811183927/https://www.societedugrandparis.fr/wp-content/uploads/2015/03/150305_sgp-tp_brochure-issylesmoulineaux-a5-pdf.pdf|archive-date=11 August 2017|url-status=dead}}</ref> It will create a loop connecting Noisy–Champs to Champigny, passing through ], ], ], ], ] and ]. | ||
=== Proposed timeline === | === Proposed timeline === | ||
On 22 February 2018, a new timeline is announced by Prime minister ]:<ref>{{Cite web|url = https://www.societedugrandparis.fr/gpe/actualite/la-nouvelle-feuille-de-route-du-grand-paris-express-1683 |title = La nouvelle feuille de route du Grand Paris Express |date = 22 February 2018|website = societedugrandparis.fr}}.</ref> | On 22 February 2018, a new timeline is announced by Prime minister ]:<ref>{{Cite web |url = https://www.societedugrandparis.fr/gpe/actualite/la-nouvelle-feuille-de-route-du-grand-paris-express-1683 |title = La nouvelle feuille de route du Grand Paris Express |date = 22 February 2018 |website = societedugrandparis.fr |access-date = 16 May 2021 |archive-date = 30 September 2020 |archive-url = https://web.archive.org/web/20200930221345/https://www.societedugrandparis.fr/gpe/actualite/la-nouvelle-feuille-de-route-du-grand-paris-express-1683 |url-status = live }}.</ref> | ||
* During 2014: Public inquiry on the eastern section from Saint-Denis–Pleyel to Champigny Centre. | * During 2014: Public inquiry on the eastern section from Saint-Denis–Pleyel to Champigny Centre. | ||
Line 145: | Line 153: | ||
=== Previous timeline === | === Previous timeline === | ||
In 2013, the government led by Ayrault proposed this timeline for the line 15 project:<ref>{{Cite web|url = http://archives.gouvernement.fr/ayrault/sites/default/files/fichiers_joints/nouveau-grand-paris_0.pdf|title = Le Nouveau Grand Paris|date = 6 March 2013|access-date = 21 June 2015|website = archives.gouvernement.fr/|last = Service de presse de Matignon}}</ref><ref>{{Cite web|title = Nouveau Grand Paris : le comité de pilotage installé|url = http://www.actu-environnement.com/ae/news/comite-pilotage-nouveau-grand-paris-19303.php4|access-date = 21 June 2015|last = Boughriet|first = Rachida|date = 28 August 2013|website = Actu Environnement}}</ref> | In 2013, the government led by Ayrault proposed this timeline for the line 15 project:<ref>{{Cite web|url = http://archives.gouvernement.fr/ayrault/sites/default/files/fichiers_joints/nouveau-grand-paris_0.pdf|title = Le Nouveau Grand Paris|date = 6 March 2013|access-date = 21 June 2015|website = archives.gouvernement.fr/|last = Service de presse de Matignon|archive-date = 22 June 2015|archive-url = https://web.archive.org/web/20150622025147/http://archives.gouvernement.fr/ayrault/sites/default/files/fichiers_joints/nouveau-grand-paris_0.pdf|url-status = dead}}</ref><ref>{{Cite web|title = Nouveau Grand Paris : le comité de pilotage installé|url = http://www.actu-environnement.com/ae/news/comite-pilotage-nouveau-grand-paris-19303.php4|access-date = 21 June 2015|last = Boughriet|first = Rachida|date = 28 August 2013|website = Actu Environnement|archive-date = 23 February 2014|archive-url = https://web.archive.org/web/20140223113904/http://www.actu-environnement.com/ae/news/comite-pilotage-nouveau-grand-paris-19303.php4|url-status = live}}</ref> | ||
* 2014: Public inquiry on the eastern section from Saint-Denis–Pleyel to Champigny Centre. | * 2014: Public inquiry on the eastern section from Saint-Denis–Pleyel to Champigny Centre. | ||
* Early-2015: Groundbreaking for the southern section between Pont-de-Sèvres and Noisy–Champs. | * Early-2015: Groundbreaking for the southern section between Pont-de-Sèvres and Noisy–Champs. | ||
Line 157: | Line 165: | ||
=== Rolling stock === | === Rolling stock === | ||
The proposed rolling stock for line 15 is a new automated design, using conventional steel wheel on steel rail technology and overhead electrification, with a width of {{convert|2.80|m}}. Alstom has been chosen to build these trains. The names of the trains are the Alstom Metropolis ] ( |
The proposed rolling stock for line 15 is a new automated design, using conventional steel wheel on steel rail technology and overhead electrification, with a width of {{convert|2.80|m}}. Alstom has been chosen to build these trains. The names of the trains are the Alstom Metropolis ] (MR6V (6-car variant for line 15) and MR3V (3-car variant for lines 16 and 17)).<ref>{{cite web |title=Le Grand Paris Express Un projet pour le XXIe siècle |url=https://www.iledefrance-mobilites.fr/medias/portail-idfm/d2b73925-aa17-452d-b662-c466dbbe3e04_Journe%CC%81e-dinformation-aux-ope%CC%81rateurs-_Socie%CC%81te%CC%81-du-Grand-Paris-_-13062019.pdf |website=Île-de-France Mobilités |publisher=Société du Grand Paris |access-date=13 July 2023 |language=fr |date=13 June 2019 |archive-date=18 January 2024 |archive-url=https://web.archive.org/web/20240118035758/https://www.iledefrance-mobilites.fr/medias/portail-idfm/d2b73925-aa17-452d-b662-c466dbbe3e04_Journe%CC%81e-dinformation-aux-ope%CC%81rateurs-_Socie%CC%81te%CC%81-du-Grand-Paris-_-13062019.pdf |url-status=live }}</ref> | ||
The specifications of the trains travelling line 15 and their operation are as follows:<ref>{{Cite web|title = Dossier d'enquête préalable à la déclaration d'utilité publique – Tronçon Pont-de-Sèvres < > Noisy–Champs (Ligne rouge – 15 Sud) – Pièce C – Présentation du programme|url = http://www.enquetepubliquelignerouge15sud.fr/assets/files/DEP03.pdf|website = enquetepubliquelignerouge15sud.fr|access-date = 21 June 2015|last = Préfecture d'Île-de-France|language=fr}}</ref><ref>{{Cite web|title = Transports: Le Grand Paris rebaptisé et précisé|url = http://www.20minutes.fr/paris/1113363-20130306-transports-nouveau-grand-paris-voit-jour|access-date = 21 June 2015|last = Gabriel|first = Oihana|date = 6 March 2013|website = 20 minutes|language=fr}}</ref> | The specifications of the trains travelling line 15 and their operation are as follows:<ref>{{Cite web|title = Dossier d'enquête préalable à la déclaration d'utilité publique – Tronçon Pont-de-Sèvres < > Noisy–Champs (Ligne rouge – 15 Sud) – Pièce C – Présentation du programme|url = http://www.enquetepubliquelignerouge15sud.fr/assets/files/DEP03.pdf|website = enquetepubliquelignerouge15sud.fr|access-date = 21 June 2015|last = Préfecture d'Île-de-France|language=fr}}</ref><ref>{{Cite web|title = Transports: Le Grand Paris rebaptisé et précisé|url = http://www.20minutes.fr/paris/1113363-20130306-transports-nouveau-grand-paris-voit-jour|access-date = 21 June 2015|last = Gabriel|first = Oihana|date = 6 March 2013|website = 20 minutes|language = fr|archive-date = 18 June 2015|archive-url = https://web.archive.org/web/20150618031542/http://www.20minutes.fr/paris/1113363-20130306-transports-nouveau-grand-paris-voit-jour|url-status = live}}</ref> | ||
* Train width: {{convert|2.80|m}} minimum | * Train width: {{convert|2.80|m}} minimum | ||
* Train length: {{convert|108|m}}, made up of 6 cars with full-open interior gangways | * Train length: {{convert|108|m}}, made up of 6 cars with full-open interior gangways | ||
* Train capacity: 960 passengers (at 4 passengers per m²) | * Train capacity: 960 passengers (at 4 passengers per m²) | ||
* ]: iron | * ]: iron | ||
* ]: 1500 volt direct current via ] and contact wires<ref>{{Cite journal|title = Egis et Setec décrochent un gros lot du Grand Paris|url = http://www.usinenouvelle.com/article/egis-et-setec-decrochent-un-gros-lot-du-grand-paris.N204515|access-date = 21 June 2015|website = Usinenouvelle.com|date = 11 September 2013|last = Ragu|first = Didier|language=fr}}</ref> | * ]: 1500 volt direct current via ] and contact wires<ref>{{Cite journal|title = Egis et Setec décrochent un gros lot du Grand Paris|url = http://www.usinenouvelle.com/article/egis-et-setec-decrochent-un-gros-lot-du-grand-paris.N204515|access-date = 21 June 2015|website = Usinenouvelle.com|date = 11 September 2013|last = Ragu|first = Didier|language = fr|archive-date = 22 June 2015|archive-url = https://web.archive.org/web/20150622031639/http://www.usinenouvelle.com/article/egis-et-setec-decrochent-un-gros-lot-du-grand-paris.N204515|url-status = live}}</ref> | ||
* Operation: Fully automated | * Operation: Fully automated | ||
* Maximum speed: {{convert|120|km/h}}<ref name=":0">{{Cite web|title = Une offre adaptée aux territoires|url = https://www.societedugrandparis.fr/focus/le-systeme-de-transport/offre-adaptee-aux-territoires|access-date = 21 June 2015|website = Société du Grand Paris|date = 1 April 2014|archive-url=https://web.archive.org/web/20170701042441/https://www.societedugrandparis.fr/focus/le-systeme-de-transport/offre-adaptee-aux-territoires|archive-date=1 July 2017|language=fr}}</ref> | * Maximum speed: {{convert|120|km/h}}<ref name=":0">{{Cite web|title = Une offre adaptée aux territoires|url = https://www.societedugrandparis.fr/focus/le-systeme-de-transport/offre-adaptee-aux-territoires|access-date = 21 June 2015|website = Société du Grand Paris|date = 1 April 2014|archive-url=https://web.archive.org/web/20170701042441/https://www.societedugrandparis.fr/focus/le-systeme-de-transport/offre-adaptee-aux-territoires|archive-date=1 July 2017|language=fr}}</ref> | ||
* Average operating speed: {{convert|55|km/h}}<ref name=":0" /> | * Average operating speed: {{convert|55|km/h}}<ref name=":0" /> | ||
* Theoretical morning rush hour throughput: 34 560 passengers per hour<ref>{{Cite web|title = Étude Prévisions de trafic (RATP)|url = http://cpdp.debatpublic.fr/cpdp-grandparis/site/DEBATPUBLIC_GRANDPARIS_ORG/_SCRIPT/NTSP_DOCUMENT_FILE_DOWNLOAD500D.PDF|website = cpdp.debatpublic.fr|access-date = 21 June 2015|date = 18 October 2010|last = Société du Grand Paris|language=fr}}</ref> | * Theoretical morning rush hour throughput: 34 560 passengers per hour<ref>{{Cite web|title = Étude Prévisions de trafic (RATP)|url = http://cpdp.debatpublic.fr/cpdp-grandparis/site/DEBATPUBLIC_GRANDPARIS_ORG/_SCRIPT/NTSP_DOCUMENT_FILE_DOWNLOAD500D.PDF|website = cpdp.debatpublic.fr|access-date = 21 June 2015|date = 18 October 2010|last = Société du Grand Paris|language = fr|archive-date = 20 October 2016|archive-url = https://web.archive.org/web/20161020233548/http://cpdp.debatpublic.fr/cpdp-grandparis/site/DEBATPUBLIC_GRANDPARIS_ORG/_SCRIPT/NTSP_DOCUMENT_FILE_DOWNLOAD500D.PDF|url-status = live}}</ref> | ||
* Average interval: 3 to 4 minutes<ref name=":0" /> | * Average interval: 3 to 4 minutes<ref name=":0" /> | ||
* Minimum interval: 2 minutes<ref name=":0" /> | * Minimum interval: 2 minutes<ref name=":0" /> | ||
Line 230: | Line 238: | ||
}} | }} | ||
|} | |} | ||
{{Paris Métro |
{{Paris Métro lines 16 and 17}} | ||
'''Line 16''' is planned to open in between 2026 and 2028. | '''Line 16''' is planned to open in between 2026 and 2028. | ||
Line 270: | Line 278: | ||
=== Rolling stock === | === Rolling stock === | ||
The proposed rolling stock for line 18 is the ] (Matériel Roulant Voyageurs), a new automated design with a width of {{convert|2.45|m}}, using conventional steel wheel on steel rail technology and third rail electrification. Alstom has been chosen to build these trains. | The proposed rolling stock for line 18 is the ] (Matériel Roulant Voyageurs), a new automated design with a width of {{convert|2.45|m}}, using conventional steel wheel on steel rail technology and third rail electrification. Alstom has been chosen to build these trains. | ||
==Reception== | |||
The Grand Paris Express development has received the ] from ]'s ] in 2023.<ref> | |||
{{cite web |title=Veronica Rudge Green Prize in Urban Design |url=https://www.gsd.harvard.edu/urban-planning-design/fellowships-prizes-and-travel-programs/veronica-rudge-green-prize-in-urban-design/ |archive-url= |archive-date= |access-date=Oct 16, 2024 |website=gsd.harvard.edu}} | |||
</ref> | |||
==References== | ==References== |
Latest revision as of 15:35, 25 December 2024
French subway network project
Grand Paris Express | |
---|---|
The planned network of the Grand Paris Express | |
Overview | |
Owner | RATP |
Locale | Île-de-France |
Transit type | Rapid transit |
Number of lines | 6 (4 new lines, 2 extended lines) |
Number of stations | 68 |
Operation | |
Began operation | 24 June 2024 (Line 14 extension) |
Operator(s) | RATP for Lines 11 and 14 ORA (RATP Dev, Alstom, ComfortDelGro) for Line 15 south Keolis for Lines 16, 17 and 18 |
Technical | |
System length | 200 km (120 mi) |
Track gauge | 1,435 mm (4 ft 8+1⁄2 in) standard gauge |
The Grand Paris Express is a project consisting of new rapid transit lines and the extension of existing lines being built in the Île-de-France region of France. The project comprises four new lines for the Paris Métro, plus extensions of the existing Lines 11 and 14. A total of 200 kilometres (120 mi) of new tracks and 68 new stations are to be added, serving a projected 2 million passengers a day.
The new lines were originally indexed by colour (Red Line, Pink Line, Green Line, Blue Line), but this was changed in 2013 to continue the numbering convention that the RATP uses. They are therefore now known as Line 15, Line 16, Line 17 and Line 18. The constructed lines are planned to open in stages, starting with the Line 14 extension in June 2024, until 2030.
Since August 2013, the New Grand Paris steering committee has met quarterly. The first public inquiry, focused on the southern section of Line 15 from Pont de Sèvres to Noisy–Champs, was held from October to mid-November 2013. Work on Line 15 began in 2015. Its first section between Pont de Sèvres Métro station and Noisy–Champs RER A station was scheduled at that time to open around 2020, but this has now been pushed back to 2025. This line was first proposed in the Orbival project, then integrated into the Arc Express.
Line 11 extension
Main article: Paris Métro Line 11Line 11 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Legend | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(*) Under Construction (**) Planned | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
This diagram: |
To ensure better commuter service to the inner northeastern suburbs, a six-station, 5.4-kilometre (3.4 mi) eastern extension of Line 11, not considered part of the Grand Paris Express project, opened from Mairie des Lilas to Rosny-sous-Bois. The scheme was initially lobbied for by the local authorities of these suburbs, and was adopted during the 2007 review of the Île-de-France Transportation Plan. Work on the extension to Rosny – Bois-Perrier started in 2015 and opened on 13 June 2024. It provides connections with the RER E and an eventual extension of Île-de-France tramway Line 1, which better links central Paris with the commuter hub of Châtelet–Les Halles.
Revisions in the Grand Paris Express Plan and possible automation
A revised plan for the proposed Grand Paris Express subway system was unveiled on 6 March 2013, and calls for a second extension of Line 11 to be built towards Noisy–Champs, this second extension being considered part of the Grand Paris Express project. The target opening date is 2030, but might be pushed back. Should the second extension be built, Line 11 will eventually be fully automated. Automatic train operation was not implemented with the Rosny extension, although the RATP and STIF had considered the possibility of adding it later on.
Rolling stock
Line 11 was the first metro line converted to rubber-tyred pneumatic operation, and its first set of rubber-tyred rolling stock was the MP 55, which operated from October 1956 through January 1999. They were then replaced by refurbished MP 59 stock from Line 4. The MP 55 stock consisted of 4 carriages, as did the replacement MP 59 stock. One MP 73 of line 6 was in service on the 11 as well.
Île-de-France Mobilités planned to replace the aging fleet of Line 11 with MP 14 series trains around the time of the opening of the extension to Rosny-sous-Bois. The new trains are driver-operated as the MP 59 fleet was, but they are 5 cars long and have open gangways. An initial 20 trains were ordered in February 2018, with an additional 19 trains ordered in July 2021. Production began in late 2020, and testing in summer 2021.
The first new MP 14 CC (manual transit) were deployed in June 2023, with four new trains entering service each Tuesday to replace four MP 59 transferred to the Rosny-sous-Bois workshop on Monday nights to be retired. Twenty new MP 14-manual transit were deployed by summer 2023, with an additional nineteen new trains deployed in spring 2024 to serve the extension to Rosny–Bois-Perrier. The ceremonial final runs of the MP 59 took place on 23 May 2024, with #'s 6069, 6073 and 6087 being the final three to be withdrawn.
Line 14 extension
Line 14 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Legend | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(*) Under construction (**) Planned |
Northern extension of Line 14
The automated Line 14 was extended north from Saint-Lazare to Mairie de Saint-Ouen, with the primary aim of reducing overcrowding on Line 13. The adopted solution connects both branches of Line 13 to Line 14, with stations at Porte de Clichy on the Asnières – Gennevilliers branch and Mairie de Saint-Ouen on the Saint-Denis branch. An additional station connects with the Saint-Ouen RER C station, and another with the Transilien Paris-Saint-Lazare lines at Pont Cardinet, and the final one with the RER D at Saint-Denis–Pleyel. Construction on the extension began in 2014, with an aim of completion by 2019. Completion was later pushed back to 2020 after flooding from the water table stopped the tunnel works for a year. The COVID-19 pandemic then further delayed the opening to December 2020. The extension opened on 24 June 2024, just a month before the 2024 Summer Olympics.
Southern extension of Line 14
Line 14 was also extended south from Olympiades towards Orly Airport. The extension travels southeastward from Olympiades to Maison Blanche, interchanging with Line 7's Villejuif branch, and opened on 24 June 2024 (again, just a month before the 2024 Summer Olympics).
With both extensions complete, it is expected that Line 14 will eventually be merged into the proposed Grand Paris Express system.
Rolling stock
In February 2012 the STIF announced that with the two extensions planned, the brand new MP 14 class of rolling stock would replace the MP89 CA and MP 05 stock on Line 14 starting from 2020. This new stock is in eight-car train formations, longer than previously employed anywhere on the Paris Métro but which the length of all Line 14 stations was planned for. The previous MP 89 CA and MP 05 stock was then reassigned to the newly automated line 4, alongside some 6-car MP 14s. They replaced its manually driven MP 89 CC rolling stock, which was refurbished before going to line 6 to replace the aging MP 73 rolling stock.
Line 15
Main article: Paris Métro Line 15 For the previously-planned Line 15, see Merger of Paris Métro lines 3bis and 7bis.Line 15 | |||
---|---|---|---|
Overview | |||
Termini | Noisy–Champs Champigny Centre station | ||
Connecting lines | |||
Stations | 36 | ||
Service | |||
System | Paris Métro | ||
Operator(s) | Will be retained by Ile de France Mobilités after a call for tenders | ||
Rolling stock | Alstom Metropolis MR6V | ||
History | |||
Opened | 2025–2030 | ||
Technical | |||
Line length | 75 km (47 mi) | ||
Track gauge | 1,435 mm (4 ft 8+1⁄2 in) standard gauge | ||
Conduction system | Automated | ||
|
Line 15 will be a high-capacity underground rail line, providing a new ring line around Paris in the departments of Hauts-de-Seine, Val-de-Marne and Seine-Saint-Denis. It will enable direct journeys between the suburbs, bypassing central Paris. The configuration of the line is very similar to that of the Arc Express, proposed by the RATP in 2006. It was later included in the red line project of the Grand Paris public transportation network, introduced by French President Nicolas Sarkozy in 2009. In March 2013, the "New Grand Paris" project was announced by the Prime Minister at the time, Jean-Marc Ayrault. At this time, the line acquired its current line 15 naming.
Line 15 is planned to open in phases from 2025 through 2030. It will create a loop connecting Noisy–Champs to Champigny, passing through Champigny-sur-Marne, Créteil, Villejuif, La Défense, Saint-Denis and Rosny-sous-Bois.
Proposed timeline
On 22 February 2018, a new timeline is announced by Prime minister Édouard Philippe:
- During 2014: Public inquiry on the eastern section from Saint-Denis–Pleyel to Champigny Centre.
- Early 2015: Groundbreaking of the southern section spanning Pont-de-Sèvres to Noisy–Champs.
- 2024, postponed to 2025 in September 2018: Southern section from Pont de Sèvres to Noisy–Champs put into service.
- 2030: western section from Pont de Sèvres to Saint-Denis–Pleyel and eastern section from Saint-Denis–Pleyel to Champigny Centre put into service.
Previous timeline
In 2013, the government led by Ayrault proposed this timeline for the line 15 project:
- 2014: Public inquiry on the eastern section from Saint-Denis–Pleyel to Champigny Centre.
- Early-2015: Groundbreaking for the southern section between Pont-de-Sèvres and Noisy–Champs.
- 2020: Groundbreaking of the section from Pont-de-Sèvres to Nanterre and from Saint-Denis–Pleyel to Rosny-Bois-Perrier on the northern section.
- 2022: Southern section from Pont-de-Sèvres to Noisy–Champs opens.
- Early 2025: Segments from Pont-de-Sèvres to Nanterre and from Saint-Denis–Pleyel to Rosny-Bois-Perrier of the northern section put into service.
- 2025: Groundbreaking of the segment from Nanterre to Saint-Denis–Pleyel via La Défense-Grande-Arche of the northern section.
- Early 2030: Segment from Nanterre to Saint-Denis–Pleyel via La Défense-Grande-Arche of the northern section put into service.
- End of 2030: Northern section from Rosny to Champigny completed.
Rolling stock
The proposed rolling stock for line 15 is a new automated design, using conventional steel wheel on steel rail technology and overhead electrification, with a width of 2.80 metres (9 ft 2 in). Alstom has been chosen to build these trains. The names of the trains are the Alstom Metropolis MR3V/MR6V (MR6V (6-car variant for line 15) and MR3V (3-car variant for lines 16 and 17)).
The specifications of the trains travelling line 15 and their operation are as follows:
- Train width: 2.80 metres (9 ft 2 in) minimum
- Train length: 108 metres (354 ft), made up of 6 cars with full-open interior gangways
- Train capacity: 960 passengers (at 4 passengers per m²)
- Bearings: iron
- Electric traction current: 1500 volt direct current via pantograph and contact wires
- Operation: Fully automated
- Maximum speed: 120 kilometres per hour (75 mph)
- Average operating speed: 55 kilometres per hour (34 mph)
- Theoretical morning rush hour throughput: 34 560 passengers per hour
- Average interval: 3 to 4 minutes
- Minimum interval: 2 minutes
Lines 16 and 17
Main articles: Paris Métro Line 16 and Paris Métro Line 17
|
|
Lines 16 and 17 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Legend | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
This diagram: |
Line 16 is planned to open in between 2026 and 2028.
Line 17 is planned to open in phases between 2026 and 2030.
Rolling stock
The proposed rolling stock for lines 16 and 17 is a new automated design with a width of 2.80 metres (9 ft 2 in), using conventional steel wheel on steel rail technology and overhead electrification. The rolling stocks for the line is the Alstom Metropolis MR3V (3-car variant)
Line 18
Main article: Paris Métro Line 18Line 18 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Overview | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Termini | Versailles-Chantiers Orly airport | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Connecting lines | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Stations | 13 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Service | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
System | Paris Métro | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Operator(s) | Will be retained by Ile de France Mobilités after a call for tenders | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
History | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Opened | 2026–2030 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Technical | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Line length | 50 km (31 mi) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Track gauge | 1,435 mm (4 ft 8+1⁄2 in) standard gauge | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Conduction system | Automated | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Line 18 is planned to open in phases between 2026 and 2030.
Rolling stock
The proposed rolling stock for line 18 is the MRV (Matériel Roulant Voyageurs), a new automated design with a width of 2.45 metres (8 ft 0 in), using conventional steel wheel on steel rail technology and third rail electrification. Alstom has been chosen to build these trains.
Reception
The Grand Paris Express development has received the Veronica Rudge Green Prize in Urban Design from Harvard University's Graduate School of Design in 2023.
References
- "The Metro: a Parisian institution". RATP. Archived from the original on 18 February 2017. Retrieved 29 January 2014. The Montmartre funicular is considered to be part of the metro system, within which is represented by a 303rd fictive station "Funiculaire".
- "Grand Paris Express : la ligne 15 sud sera exploitée par RATP Dev à partir de fin 2025". Le Parisien. Retrieved 25 December 2024.
- "Keolis remporte le droit d'exploitation de la ligne 18 du Grand Paris Express". Le Figaro. Retrieved 25 December 2024.
- "Brief history of the Paris metro". france.fr – The official website of France. Archived from the original on 26 September 2013. Retrieved 21 September 2013.
- "Grand Paris Express, the largest transport project in Europe". Société du Grand Paris. Archived from the original on 11 April 2022. Retrieved 11 January 2020.
- ^ "Création des nouvelles lignes reliant le Nouveau Grand Paris". STIF (in French). Archived from the original on 19 November 2014.
- Ministère de l'écologie, du développement durable et de l'énergie (28 August 2013). "Installation du comité de pilotage du Nouveau Grand Paris". developpement-durable.gouv.fr. Archived from the original on 22 June 2015. Retrieved 21 June 2015.
- "Métro ligne 15 – STIF". stif.org. Archived from the original on 8 June 2015. Retrieved 21 June 2015.
- ^ "Prolongement de la ligne 11: le tunnelier inauguré, six nouvelles stations de métro en 2023". France 3 Paris Ile-de-France (in French). Archived from the original on 30 October 2020. Retrieved 6 June 2020.
- ^ "Focus on the extension of line 11" (Press release). RATP Group. 13 June 2024. Retrieved 13 June 2024.
- "Nouveau Grand Paris» : l'État engage 27 milliards pour le métro parisien" (in French). 6 March 2013. Archived from the original on 3 March 2016. Retrieved 25 June 2016.
- Press release: "Le prolongement de la ligne 11 du métro à Rosny-Bois-Perrier à l’enquête publique en 2013", STIF, 13 February 2013
- Varoquier, Jila (11 December 2018). "Le métro parisien passe au bleu". Le Parisien (in French). Retrieved 12 December 2018.
- ^ "Une offre adaptée aux territoires". Société du Grand Paris (in French). 1 April 2014. Archived from the original on 1 July 2017. Retrieved 21 June 2015.
- Hasse, Benoît (9 July 2023). "Grand Paris : la ligne 11 du métro fait sa révolution en s'équipant (enfin) de rames neuves" [Grand Paris: line 11 of the metro is undergoing a revolution by (finally) equipping itself with new trains] (in French). Retrieved 2023-07-09
- "Prolongement de la ligne 14 de Saint-Lazare à Mairie de Saint-Ouen" (in French). RATP. Archived from the original on 10 September 2013. Retrieved 17 November 2011.
- à 13h09, Par Julien Duffé Le 23 octobre 2014 (23 October 2014). "Grand Paris : le prolongement des lignes 12 et 14 du métro retardé de deux ans". Le Parisien. Archived from the original on 18 May 2022. Retrieved 18 May 2022.
{{cite web}}
: CS1 maint: numeric names: authors list (link) - "A Paris, la ligne 14 du métro en plein essor, la 13 toujours aussi chargée". Le Monde. 5 March 2021. Archived from the original on 5 March 2021. Retrieved 5 March 2021.
- ^ Compagnon, Sébastian; Gairaud, Marie-Anne (24 June 2024). "Ligne 14 de Saint-Denis - Pleyel à l'aéroport d'Orly : "Ces nouvelles stations, c'est vraiment waouh !"". leparisien.fr (in French). Retrieved 24 June 2024.
- (in French) http://www.symbioz.net/index.php?id=99 Archived 16 January 2021 at the Wayback Machine Grand Paris Express
- "Archived copy" (PDF). Archived from the original (PDF) on 14 October 2012. Retrieved 8 March 2012.
{{cite web}}
: CS1 maint: archived copy as title (link) Modernisation du métro (in French). STIF. Retrieved 11 February 2012 - "Acte motivé". societedugrandparis.fr. 26 May 2011. pp. 34, 35, 45. Archived from the original on 8 July 2015. Retrieved 21 June 2015.
- "ratp.fr – The Greater Paris Express project". ratp.fr. Archived from the original on 1 August 2015. Retrieved 21 June 2015.
- "Le Nouveau Grand Paris : pour une région compétitive et solidaire". archives.gouvernement.fr. 6 March 2013. Archived from the original on 22 June 2015. Retrieved 21 June 2015.
- "Grand Paris Express" (PDF). Archived from the original (PDF) on 11 August 2017. Retrieved 29 December 2017.
- "La nouvelle feuille de route du Grand Paris Express". societedugrandparis.fr. 22 February 2018. Archived from the original on 30 September 2020. Retrieved 16 May 2021..
- Service de presse de Matignon (6 March 2013). "Le Nouveau Grand Paris" (PDF). archives.gouvernement.fr/. Archived from the original (PDF) on 22 June 2015. Retrieved 21 June 2015.
- Boughriet, Rachida (28 August 2013). "Nouveau Grand Paris : le comité de pilotage installé". Actu Environnement. Archived from the original on 23 February 2014. Retrieved 21 June 2015.
- "Le Grand Paris Express Un projet pour le XXIe siècle" (PDF). Île-de-France Mobilités (in French). Société du Grand Paris. 13 June 2019. Archived (PDF) from the original on 18 January 2024. Retrieved 13 July 2023.
- Préfecture d'Île-de-France. "Dossier d'enquête préalable à la déclaration d'utilité publique – Tronçon Pont-de-Sèvres < > Noisy–Champs (Ligne rouge – 15 Sud) – Pièce C – Présentation du programme" (PDF). enquetepubliquelignerouge15sud.fr (in French). Retrieved 21 June 2015.
- Gabriel, Oihana (6 March 2013). "Transports: Le Grand Paris rebaptisé et précisé". 20 minutes (in French). Archived from the original on 18 June 2015. Retrieved 21 June 2015.
- Ragu, Didier (11 September 2013). "Egis et Setec décrochent un gros lot du Grand Paris". Usinenouvelle.com (in French). Archived from the original on 22 June 2015. Retrieved 21 June 2015.
- Société du Grand Paris (18 October 2010). "Étude Prévisions de trafic (RATP)" (PDF). cpdp.debatpublic.fr (in French). Archived (PDF) from the original on 20 October 2016. Retrieved 21 June 2015.
- "Veronica Rudge Green Prize in Urban Design". gsd.harvard.edu. Retrieved 16 October 2024.
External links
- (in French) Official website
Paris transport network | |
---|---|
Métro | |
RER | |
Transilien | |
Tramway | |
Bus | |
Others | |
Projects | |
Administration | |
Finance | |
Stations |
|
Line 11 | |
---|---|
Stations |
Line 14 | |
---|---|
Stations |
|
Line 15 | |
---|---|
Stations |
|