Misplaced Pages

Kaiwera Downs Wind Farm: Difference between revisions

Article snapshot taken from Wikipedia with creative commons attribution-sharealike license. Give it a read and then ask your questions in the chat. We can research this topic together.
Browse history interactively← Previous editNext edit →Content deleted Content addedVisualWikitext
Revision as of 20:33, 21 February 2023 editGibbonsj (talk | contribs)16 editsm added transmission sectionTag: Visual edit← Previous edit Revision as of 08:37, 23 February 2023 edit undoGibbonsj (talk | contribs)16 editsm Updated expected completion dateTag: Visual editNext edit →
Line 33: Line 33:
The project received resource consent in June 2008.<ref>{{cite web | title = Appeals lodged against wind farm | publisher = Otago Daily Times | author = Glenn Conway | date = 2008-07-05 | url = http://www.odt.co.nz/the-regions/southland/12217/appeals-lodged-against-wind-farm | accessdate = 2008-09-24}}</ref> In September 2018 Tilt said that the development was waiting for favourable market conditions.<ref>{{cite web |url=https://www.stuff.co.nz/southland-times/news/107242302/kaiwera-downs-wind-farm-still-on-the-horizon |title=Kaiwera Downs wind farm still on the horizon |author=Rachael Kelly |publisher=Stuff |date=26 September 2018 |access-date=17 June 2021}}</ref> In June 2021 Tilt announced the project was being acquired by ].<ref>{{cite web |url=https://www.stuff.co.nz/business/125412854/kaiwera-downs-windfarm-project-still-viable-in-southland |title=Kaiwera Downs windfarm project still viable in Southland |publisher=Stuff |author=Rachael Kelly |date=11 June 2021 |access-date=17 June 2021}}</ref> In June 2022 Mercury began talks with the local community over the wind farm.<ref>{{cite web |url=https://www.stuff.co.nz/southland-times/news/129050930/talks-ramp-up-around-kaiwera-downs-wind-farm-near-gore |author=Logan Savory |title=Talks ramp up around Kaiwera Downs wind farm near Gore |publisher=Stuff |date=22 June 2022 |access-date=27 June 2022}}</ref> The project received resource consent in June 2008.<ref>{{cite web | title = Appeals lodged against wind farm | publisher = Otago Daily Times | author = Glenn Conway | date = 2008-07-05 | url = http://www.odt.co.nz/the-regions/southland/12217/appeals-lodged-against-wind-farm | accessdate = 2008-09-24}}</ref> In September 2018 Tilt said that the development was waiting for favourable market conditions.<ref>{{cite web |url=https://www.stuff.co.nz/southland-times/news/107242302/kaiwera-downs-wind-farm-still-on-the-horizon |title=Kaiwera Downs wind farm still on the horizon |author=Rachael Kelly |publisher=Stuff |date=26 September 2018 |access-date=17 June 2021}}</ref> In June 2021 Tilt announced the project was being acquired by ].<ref>{{cite web |url=https://www.stuff.co.nz/business/125412854/kaiwera-downs-windfarm-project-still-viable-in-southland |title=Kaiwera Downs windfarm project still viable in Southland |publisher=Stuff |author=Rachael Kelly |date=11 June 2021 |access-date=17 June 2021}}</ref> In June 2022 Mercury began talks with the local community over the wind farm.<ref>{{cite web |url=https://www.stuff.co.nz/southland-times/news/129050930/talks-ramp-up-around-kaiwera-downs-wind-farm-near-gore |author=Logan Savory |title=Talks ramp up around Kaiwera Downs wind farm near Gore |publisher=Stuff |date=22 June 2022 |access-date=27 June 2022}}</ref>


Installation of an initial ten turbines totalling 43MW of generation is expected to start in October 2022.<ref>{{cite web |url=https://www.stuff.co.nz/business/129863738/construction-on-new-wind-farm-near-gore-will-begin-in-october |title=Construction on new wind farm near Gore will begin in October |publisher=Stuff |author=Geraden Cann |date=13 September 2022 |access-date=13 September 2022}}</ref><ref>{{cite web |url=https://www.odt.co.nz/regions/southland/wind-farm-something-we-will-have-learn-live |title=Wind farm 'something we will have to learn to live with' |publisher=Otago Daily Times |date=14 September 2022|access-date=14 September 2022}}</ref><ref>{{cite web |url=https://www.nzherald.co.nz/business/mercury-nz-commits-to-115m-wind-farm-near-gore/MWGLFGG5R3L5GDUDAC6EVHDWEI/ |title=Mercury NZ commits to $115m wind farm near Gore |publisher=New Zealand Herald |date= |access-date=14 September 2022}}</ref> Earthworks began in the first week of October 2022.<ref>{{cite web |url=https://www.stuff.co.nz/southland-times/130070968/earthworks-begin-at-mercury-energys-115m-kaiwera-wind-farm |title=Earthworks begin at Mercury Energy's $115m Kaiwera wind farm |publisher=Stuff |author=Rachael Kelly |date=4 October 2022 |access-date=20 October 2022}}</ref> A sod-turning ceremony was held in November 2022, with the first turbines expected to arrive in April 2023. <ref name=Stuff2022a>{{cite web |url=https://www.stuff.co.nz/national/130366382/southland-has-an-exciting-future-in-wind-generation |title=Southland has an exciting future in wind generation |publisher=Stuff |author=Rachael Kelly |date=3 November 2022 |access-date=3 November 2022}}</ref> The wind farm is expected to be operational by early 2024.<ref name=Stuff2022a/> Installation of an initial ten turbines totalling 43MW of generation is expected to start in October 2022.<ref>{{cite web |url=https://www.stuff.co.nz/business/129863738/construction-on-new-wind-farm-near-gore-will-begin-in-october |title=Construction on new wind farm near Gore will begin in October |publisher=Stuff |author=Geraden Cann |date=13 September 2022 |access-date=13 September 2022}}</ref><ref>{{cite web |url=https://www.odt.co.nz/regions/southland/wind-farm-something-we-will-have-learn-live |title=Wind farm 'something we will have to learn to live with' |publisher=Otago Daily Times |date=14 September 2022|access-date=14 September 2022}}</ref><ref>{{cite web |url=https://www.nzherald.co.nz/business/mercury-nz-commits-to-115m-wind-farm-near-gore/MWGLFGG5R3L5GDUDAC6EVHDWEI/ |title=Mercury NZ commits to $115m wind farm near Gore |publisher=New Zealand Herald |date= |access-date=14 September 2022}}</ref> Earthworks began in the first week of October 2022.<ref>{{cite web |url=https://www.stuff.co.nz/southland-times/130070968/earthworks-begin-at-mercury-energys-115m-kaiwera-wind-farm |title=Earthworks begin at Mercury Energy's $115m Kaiwera wind farm |publisher=Stuff |author=Rachael Kelly |date=4 October 2022 |access-date=20 October 2022}}</ref> A sod-turning ceremony was held in November 2022, with the first turbines expected to arrive in April 2023. <ref name=Stuff2022a>{{cite web |url=https://www.stuff.co.nz/national/130366382/southland-has-an-exciting-future-in-wind-generation |title=Southland has an exciting future in wind generation |publisher=Stuff |author=Rachael Kelly |date=3 November 2022 |access-date=3 November 2022}}</ref> As of February 2023, Mercury say they expect all turbines to be operational by October 2023<ref>{{Cite web |title=2023 Interim Report by Mercury - Issuu |url=https://issuu.com/mercurynz/docs/mer00001_mercury_interim_report_2023_digital_pp5_s |access-date=2023-02-23 |website=issuu.com |language=en}}</ref>


== Transmission == == Transmission ==

Revision as of 08:37, 23 February 2023

Kaiwera Downs Wind Farm
CountryNew Zealand
LocationGore
Coordinates46°14′29″S 169°3′21″E / 46.24139°S 169.05583°E / -46.24139; 169.05583
Construction beganOctober 2022
Construction cost115m (stage 1)
OwnerMercury Energy
Wind farm
TypeOnshore
Hub height77m
Rotor diameter136m
Site elevation400m – 460m
Power generation
Make and modelV136-4.2 MW in 4.3 MW operating mode
Units planned197 MW
Units under const.10 x 4.3MW
Nameplate capacity
  • 198 MW
Annual net output148 GWh (Stage 1)
[edit on Wikidata]

The Kaiwera Downs Wind Farm is a wind farm under construction in the Southland region of New Zealand. It is consented to have a maximum capacity of 240MW and use up 83 turbines. Originally proposed by Trustpower, it will now be owned and operated by Mercury Energy. The 10 turbine, 43MW stage 1 of the project is under construction.

The New Zealand Ministry for Culture and Heritage gives a translation of "hot food" for Kaiwera.

Location

The wind farm will be located about 15 kilometres south-east of Gore, within an area of 2,568 hectares (25.68 km).

Construction

The project received resource consent in June 2008. In September 2018 Tilt said that the development was waiting for favourable market conditions. In June 2021 Tilt announced the project was being acquired by Mercury Energy. In June 2022 Mercury began talks with the local community over the wind farm.

Installation of an initial ten turbines totalling 43MW of generation is expected to start in October 2022. Earthworks began in the first week of October 2022. A sod-turning ceremony was held in November 2022, with the first turbines expected to arrive in April 2023. As of February 2023, Mercury say they expect all turbines to be operational by October 2023

Transmission

Transmission line route and turbine locations for the Kaiwera Downs wind farm stage 1

Power is being exported to the New Zealand grid via a new 18km, 33kV, monopole, overhead transmission line to the Gore Substation.

See also

References

  1. Sonia Gerken (4 April 2008). "Wind farm carbon savings 'could be worth 25m'". The Southland Times. Retrieved 24 September 2008.
  2. "1000 Māori place names". New Zealand Ministry for Culture and Heritage. 6 August 2019.
  3. "Kaiwera Downs Wind Farm". Tilt Renewables. Retrieved 24 June 2018.
  4. Glenn Conway (5 July 2008). "Appeals lodged against wind farm". Otago Daily Times. Retrieved 24 September 2008.
  5. Rachael Kelly (26 September 2018). "Kaiwera Downs wind farm still on the horizon". Stuff. Retrieved 17 June 2021.
  6. Rachael Kelly (11 June 2021). "Kaiwera Downs windfarm project still viable in Southland". Stuff. Retrieved 17 June 2021.
  7. Logan Savory (22 June 2022). "Talks ramp up around Kaiwera Downs wind farm near Gore". Stuff. Retrieved 27 June 2022.
  8. Geraden Cann (13 September 2022). "Construction on new wind farm near Gore will begin in October". Stuff. Retrieved 13 September 2022.
  9. "Wind farm 'something we will have to learn to live with'". Otago Daily Times. 14 September 2022. Retrieved 14 September 2022.
  10. "Mercury NZ commits to $115m wind farm near Gore". New Zealand Herald. Retrieved 14 September 2022.
  11. Rachael Kelly (4 October 2022). "Earthworks begin at Mercury Energy's $115m Kaiwera wind farm". Stuff. Retrieved 20 October 2022.
  12. Rachael Kelly (3 November 2022). "Southland has an exciting future in wind generation". Stuff. Retrieved 3 November 2022.
  13. "2023 Interim Report by Mercury - Issuu". issuu.com. Retrieved 23 February 2023.
  14. Kaiwera Downs Wind Farm Newsletter February 2023.

External links


Stub icon

This article about a wind farm is a stub. You can help Misplaced Pages by expanding it.

Stub icon

This Southland Region geography article is a stub. You can help Misplaced Pages by expanding it.

Stub icon

This article about a New Zealand power station is a stub. You can help Misplaced Pages by expanding it.

Categories: