Revision as of 22:27, 8 April 2006 editVaoverland (talk | contribs)31,318 editsm History← Previous edit Revision as of 22:43, 8 April 2006 edit undoVaoverland (talk | contribs)31,318 editsm Benefits and travel expenses of members reported by a local newspaper appeared wasteful. The need for additional tunnel construction was also questioned by state and local officials, who compared theNext edit →
Line 3: Line 3:
== History == == History ==


By the early 20th century, the Chesapeake Bay was becoming an increasing transportation obstacle for the growing number of motor vehicles. The ] operated some passenger and ] car ] services between the Eastern Shore and ] on the ] and ] in ]. The ] operated bewteen the Eastern Shore and ] and transported vehicles as part of ] and the ]. By the early 20th century, the Chesapeake Bay was becoming an increasing transportation obstacle for the growing number of motor vehicles. The ] operated some passenger and ] car ] services between the Eastern Shore and ] on the ] and ] in ]. The ] operated between the Eastern Shore and ] and transported vehicles as part of ] and the ].


In 1953, the ] announced an end to the service to Old Point Comfort. Worse yet, despite adding more ships, and making as many as 90 one-way crossings a day, the Little Creek Ferry was also proving inadequate. A fixed crossing had long been desired, but was not feasible due to the risk of blocking access to the ]'s extensive facilities in ]. The shortest possible crossing would be approximately 15 miles, far too long for a ] such as the ] across the ] which was completed in 1952. In 1953, the ] announced an end to the service to Old Point Comfort. Worse yet, despite adding more ships, and making as many as 90 one-way crossings a day, the Little Creek Ferry was also proving inadequate. A fixed crossing had long been desired, but was not feasible due to the risk of blocking access to the ]'s extensive facilities in ]. The shortest possible crossing would be approximately 15 miles, far too long for a ] such as the ] across the ] which was completed in 1952.
Line 27: Line 27:
The first executive director of the CBBT was ], who had previously served as the Manager of ], which had become an ] in 1952 and merged with ] in 1958. The first executive director of the CBBT was ], who had previously served as the Manager of ], which had become an ] in 1952 and merged with ] in 1958.


==Adding additional lanes==

At a cost of $197 million, new ] two-lane ]s were built both to alleviate traffic and for safety reasons, opening on ], ]. This increased the capacity of the above-water portion of the facility to four lanes, facilitated needed repairs, and helped insure against a total closure should a trestle be struck by a ship or otherwise damaged (which had occurred twice in the past).

While there has been planning work done to expand tunnel capacities as well, and tolls were increased in anticipation of this, the facility currently continues to utilize only the original two-lane tunnels.
==Controversy==

In the early 21st century, the Commission came under increased public scrutiny. Benefits and travel expenses of members reported by a local newspaper appeared wasteful. The need for additional tunnel construction was also questioned by state and local officials, who compared the CBBT's light traffic count to the heavy burdens and congestion on other water-crossings in the Hampton Roads area. The growing funds from increased CBBT tolls in anticipation of the future tunnel expansion were also considered for possible redirection to other projects. In the 2006 General Assembly, legislation was proposed to limit the power of the agency and/or combine its efforts and resources with other area needs. Regardless of the outcome of these proposals, it is likely that the tunnel expansion project will remain "on hold" and will not proceed for some time to come.


] ]

Revision as of 22:43, 8 April 2006

Chesapeake Bay Bridge and Tunnel District is a political subdivision of the Commonwealth of Virginia. It is overseen by the Chesapeake Bay Bridge and Tunnel Commission, and operates the Chesapeake Bay Bridge-Tunnel between the Hampton Roads and Eastern Shore regions of the state. The District is comprised of six cities, Virginia Beach, Norfolk, Portsmouth, Chesapeake, Hampton, Newport News, and the two Eastern Shore counties of Northampton and Accomack.

History

By the early 20th century, the Chesapeake Bay was becoming an increasing transportation obstacle for the growing number of motor vehicles. The Pennsylvania Railroad operated some passenger and railroad car ferry services between the Eastern Shore and Old Point Comfort on the Virginia Peninsula and Norfolk in South Hampton Roads. The Little Creek Ferry operated between the Eastern Shore and Princess Anne County and transported vehicles as part of U.S. Route 13 and the Ocean Hiway.

In 1953, the Pennsylvania Railroad announced an end to the service to Old Point Comfort. Worse yet, despite adding more ships, and making as many as 90 one-way crossings a day, the Little Creek Ferry was also proving inadequate. A fixed crossing had long been desired, but was not feasible due to the risk of blocking access to the U.S. Navy's extensive facilities in Hampton Roads. The shortest possible crossing would be approximately 15 miles, far too long for a tunnel such as the Downtown Tunnel across the Elizabeth River which was completed in 1952.

Responding to the problem, in 1954, the Virginia General Assembly created the Chesapeake Bay Ferry District and the Chesapeake Bay Ferry Commission to oversee it. The agency set about the matters of improving bay ferry service and exploring the possibilities of building a fixed crossing. Toll revenue bonds were sold and most of the funds used to purchased the Virginia Ferry Corporation, a public service company which was the operator of the Little Creek Ferry Service. A portion of the funds were designated for a study of a fixed crossing.

A bridge across the Bay was unacceptable to the Navy, and a long tunnel was also considered infeasible. The answer, however, lay close at hand. A similar situation had earlier confronted the crossing of Hampton Roads between Old Point Comfort and South Hampton Roads, and a solution found in a combination of bridge and tunnel which came to be known as a bridge-tunnel. In 1957, the Hampton Roads Bridge-Tunnel was completed, using bridges on each end, and a tunnel under the shipping channel. It was necessary to build artificial islands to anchor the ends of the tunnel, and it was costly to construct, but the design met all the various requirements.

In the late 1950s, a engineering feasibility study of using a combination of bridges and tunnels was performed under the direction of civil engineer Leif J. Sverdrup and his company. Ultimately, a 23 mile-long project, with 17.4 miles of bridge and tunnel construction, was planned. The names of the District and Commission were changed to reflect the new primary mission.

$200 million dollars in toll revenue bonds were sold in August 1960, and construction began the following month. The new bridge-tunnel opened in 1964 as a two lane facility.

Lucius J. Kellam Jr.

Eastern Shore native, businessman, and civic leader Lucius J. Kellam Jr. was the original Commission's first chairman. In a commentary at the time of his death in 1995, the Virginian-Pilot newspaper (Norfolk) recalled that Kellam had been involved in bringing the multi-million-dollar bridge-tunnel project from dream to reality.

Before it was built, Kellam handled a political fight over the location, and addressed concerns of the U.S. Navy about prospective hazards to navigation to and from the Norfolk Navy Base at Sewell's Point.

Kellam was also directly involved in the negotiations to finance the ambitious crossing with bonds. According to the newspaper article, "there were not-unfounded fears that (1) storm-driven seas and drifting or off-course vessels could damage, if not destroy, the span and (2) traffic might not be sufficient to service the entire debt in an orderly way. Sure enough, bridge portions of the crossing have occasionally been damaged by vessels, and there was a long period when holders of the riskiest bonds received no interest on their investment."

J. Clyde Morris

The first executive director of the CBBT was J. Clyde Morris, who had previously served as the Manager of Warwick County, which had become an independent city in 1952 and merged with Newport News in 1958.

Adding additional lanes

At a cost of $197 million, new parallel two-lane trestles were built both to alleviate traffic and for safety reasons, opening on April 19, 1999. This increased the capacity of the above-water portion of the facility to four lanes, facilitated needed repairs, and helped insure against a total closure should a trestle be struck by a ship or otherwise damaged (which had occurred twice in the past).

While there has been planning work done to expand tunnel capacities as well, and tolls were increased in anticipation of this, the facility currently continues to utilize only the original two-lane tunnels.

Controversy

In the early 21st century, the Commission came under increased public scrutiny. Benefits and travel expenses of members reported by a local newspaper appeared wasteful. The need for additional tunnel construction was also questioned by state and local officials, who compared the CBBT's light traffic count to the heavy burdens and congestion on other water-crossings in the Hampton Roads area. The growing funds from increased CBBT tolls in anticipation of the future tunnel expansion were also considered for possible redirection to other projects. In the 2006 General Assembly, legislation was proposed to limit the power of the agency and/or combine its efforts and resources with other area needs. Regardless of the outcome of these proposals, it is likely that the tunnel expansion project will remain "on hold" and will not proceed for some time to come.