Misplaced Pages

Schuman-Josaphat tunnel: Difference between revisions

Article snapshot taken from Wikipedia with creative commons attribution-sharealike license. Give it a read and then ask your questions in the chat. We can research this topic together.
Browse history interactively← Previous editNext edit →Content deleted Content addedVisualWikitext
Revision as of 09:00, 19 December 2020 editCewbot (talk | contribs)Bots7,262,980 editsm Fix broken anchor: 2017-05-09T02:08:23Z #Quarter→Brussels and the European Union#European Quarter← Previous edit Revision as of 06:20, 11 July 2023 edit undoBobrayner (talk | contribs)Autopatrolled, Extended confirmed users, Pending changes reviewers, Rollbackers53,706 edits Project details: plus a linkNext edit →
Line 17: Line 17:
The tunnel was expected to be officially opened on 12 December 2015,<ref>{{cite web|url=http://www.demorgen.be/binnenland/licht-aan-het-einde-van-de-schuman-josafattunnel-opent-over-100-dagen-a2444147/|title=Licht aan het einde van de Schuman-Josafattunnel: opent over 100 dagen|publisher=De Morgen|date=3 September 2015}}</ref> but the opening was postponed until 9 April 2016 because the mandatory safety test could not be held due to the ].<ref>{{cite web|url=http://www.lesoir.be/1052641/article/actualite/fil-info/fil-info-belgique/2015-11-24/menace-terroriste-report-mise-en-service-du-tunnel-schuman-josap|title=Menace terroriste: report de la mise en service du tunnel Schuman-Josaphat au 9 avril 2016|publisher=Le Soir|date=24 November 2015}}</ref> The opening date was designed to enable the execution of the ], which had to be modified until the tunnel can be put into service. The safety test was eventually held on 25 February 2016, <ref>{{cite web|url=http://deredactie.be/permalink/1.2583251|title=Grote rampoefening in Schuman-Josaphattunnel|date=25 February 2016|publisher=deredactie.be}}</ref> and the tunnel opened on April 4.<ref>{{cite web|last1=Barrow|first1=Keith|title=Brussels Schuman - Josaphat rail tunnel opens|url=http://www.railjournal.com/index.php/europe/brussels-schuman-josaphat-rail-tunnel-opens.html?channel=537|website=International Rail Journal|publisher=Simmons-Boardman|accessdate=4 April 2016}}</ref> The tunnel was expected to be officially opened on 12 December 2015,<ref>{{cite web|url=http://www.demorgen.be/binnenland/licht-aan-het-einde-van-de-schuman-josafattunnel-opent-over-100-dagen-a2444147/|title=Licht aan het einde van de Schuman-Josafattunnel: opent over 100 dagen|publisher=De Morgen|date=3 September 2015}}</ref> but the opening was postponed until 9 April 2016 because the mandatory safety test could not be held due to the ].<ref>{{cite web|url=http://www.lesoir.be/1052641/article/actualite/fil-info/fil-info-belgique/2015-11-24/menace-terroriste-report-mise-en-service-du-tunnel-schuman-josap|title=Menace terroriste: report de la mise en service du tunnel Schuman-Josaphat au 9 avril 2016|publisher=Le Soir|date=24 November 2015}}</ref> The opening date was designed to enable the execution of the ], which had to be modified until the tunnel can be put into service. The safety test was eventually held on 25 February 2016, <ref>{{cite web|url=http://deredactie.be/permalink/1.2583251|title=Grote rampoefening in Schuman-Josaphattunnel|date=25 February 2016|publisher=deredactie.be}}</ref> and the tunnel opened on April 4.<ref>{{cite web|last1=Barrow|first1=Keith|title=Brussels Schuman - Josaphat rail tunnel opens|url=http://www.railjournal.com/index.php/europe/brussels-schuman-josaphat-rail-tunnel-opens.html?channel=537|website=International Rail Journal|publisher=Simmons-Boardman|accessdate=4 April 2016}}</ref>


The cost of the tunnel is estimated at 210 million euros, funded through Beliris, a joint venture between the Belgian Federal State and the ] Region. The project is also managed by ]. The cost of the tunnel is estimated at 210 million euros, funded through ], a joint venture between the Belgian Federal State and the ] Region. The project is also managed by ].


Unusual construction techniques were used to limit disturbance to local residents and protect the appearance of Brussels. It was decided to carry out the work without opening the tunnel from the surface so the digging is being done without a ], but rather by hand or using small excavators. The Cortenbergh road tunnel was built with extra deep foundations to accommodate a future rail tunnel beneath it. Elsewhere the tunnel passes close beneath the cellars of buildings, and in any case delivering a TBM in central Brussels would have created great disruption. Similar techniques were used during the construction of the underground junction passing under the ]. Unusual construction techniques were used to limit disturbance to local residents and protect the appearance of Brussels. It was decided to carry out the work without opening the tunnel from the surface so the digging is being done without a ], but rather by hand or using small excavators. The Cortenbergh road tunnel was built with extra deep foundations to accommodate a future rail tunnel beneath it. Elsewhere the tunnel passes close beneath the cellars of buildings, and in any case delivering a TBM in central Brussels would have created great disruption. Similar techniques were used during the construction of the underground junction passing under the ].

Revision as of 06:20, 11 July 2023

How the tunnel fits into the Brussels rail network

The Schuman-Josaphat tunnel is a 1,250 metres (4,100 ft) double track rail tunnel in Brussels, which entered into service on 4 April 2016. It links line 161 (Brussels-Namur) just after Meiser station and line 26 (Halle-Vilvoorde) at the Cinquantenaire/Jubelpark tunnel just before Schuman station. The line is numbered L161A. A key component of the Brussels RER project, it passes beneath avenue Plasky/Plaskylaan, place de Jamblinne de Meux/Jamblinne de Meuxplein and the Cortenbergh/Kortenberg road tunnel. The position of the tunnel in the Brussels rail network is shown in the simplified map on the right. Benefits of the project include:

Project details

Rail tunnel structure (in blue) as it fits in/under the road tunnel foundations (in orange)
Schuman station looking North towards the Schuman-Josaphat tunnel
Meiser station looking South towards the Schuman-Josaphat tunnel

The project began in June 2008 and is planned to take 1645 days to complete. Construction is taking place in two phases. First, the shell was dug out, which finished in late 2011. Secondly, equipping the tunnel with track etc. was scheduled to last from late 2010 to late 2013. In fact track laying began in 2014.

The tunnel was expected to be officially opened on 12 December 2015, but the opening was postponed until 9 April 2016 because the mandatory safety test could not be held due to the Brussels lockdown. The opening date was designed to enable the execution of the Brussels RER 2015 plan, which had to be modified until the tunnel can be put into service. The safety test was eventually held on 25 February 2016, and the tunnel opened on April 4.

The cost of the tunnel is estimated at 210 million euros, funded through Beliris, a joint venture between the Belgian Federal State and the Brussels Region. The project is also managed by Infrabel.

Unusual construction techniques were used to limit disturbance to local residents and protect the appearance of Brussels. It was decided to carry out the work without opening the tunnel from the surface so the digging is being done without a tunnel boring machine, but rather by hand or using small excavators. The Cortenbergh road tunnel was built with extra deep foundations to accommodate a future rail tunnel beneath it. Elsewhere the tunnel passes close beneath the cellars of buildings, and in any case delivering a TBM in central Brussels would have created great disruption. Similar techniques were used during the construction of the underground junction passing under the Antwerp Central railway station.

References

  1. "Le tunnel Schuman-Josaphat" (PDF) (in French). Infrabel. Archived from the original (PDF) on 2013-11-14. Retrieved 14 Feb 2012.
  2. "Schuman-Josaphat tunnel". Infrabel. Retrieved 14 Feb 2012.
  3. "Schuman-Josaphat tunnel" (in French). Retrieved 9 Mar 2012.
  4. "The Regional Express Network". Retrieved 19 Mar 2012.
  5. "Le tunnel Schuman-Josaphat sur les Rails" (in French). L'Echo. Retrieved 28 Jan 2014.
  6. "Licht aan het einde van de Schuman-Josafattunnel: opent over 100 dagen". De Morgen. 3 September 2015.
  7. "Menace terroriste: report de la mise en service du tunnel Schuman-Josaphat au 9 avril 2016". Le Soir. 24 November 2015.
  8. "Grote rampoefening in Schuman-Josaphattunnel". deredactie.be. 25 February 2016.
  9. Barrow, Keith. "Brussels Schuman - Josaphat rail tunnel opens". International Rail Journal. Simmons-Boardman. Retrieved 4 April 2016.

External links

50°50′40″N 4°23′30″E / 50.84444°N 4.39167°E / 50.84444; 4.39167

Categories: