Baltic Pipeline System-II

Article snapshot taken from Wikipedia with creative commons attribution-sharealike license. Give it a read and then ask your questions in the chat. We can research this topic together.
Baltic Pipeline System-II
Location
CountryRussia
ProvinceBryansk Oblast
Smolensk Oblast
Tver Oblast
Novgorod Oblast
Leningrad Oblast
FromUnecha
Passes throughSmolensk
ToUst-Luga
Kirishi
Runs alongsideLuga River
General information
TypeCrude oil
OperatorTransneft
Construction started2009
Commissioned2011
Technical information
Length1,170 km (730 mi)
Maximum discharge50 million tons per year
No. of pumping stations8

The Baltic Pipeline System-2 (BPS-2, Russian: Балтийская трубопроводная система 2, БТС-2) is a second trunk line of the Baltic Pipeline System. The pipeline is constructed and operated by Russian oil pipeline company Transneft. The BPS-2 was completed in 2011 and began to function in late March 2012.

History

The project was proposed after an oil transit dispute between Russia and Belarus at the beginning of January 2007, and was approved by the Russian government on 21 May 2007.

Although in April 2008 Russia's Ministry of Industry and Energy submitted a negative profitability report regarding the pipeline, Russia opted to develop its own infrastructure for exporting hydrocarbons, bypassing former Soviet transit countries. The main goal of the pipeline is to protect Russia and its partners from the transit countries' possible decisions to raise tariffs or siphon off hydrocarbons. On 1 December 2008 Prime Minister Vladimir Putin signed a resolution ordering construction.

The construction started on 10 June 2009. Construction was completed in October 2011. The opening of export terminal at Ust-Luga was postponed until 2012 due to damage by landslips.

Route

The 1,170-kilometre (730 mi) long pipeline system runs from the Unecha junction of the Druzhba pipeline near the Russia–Belarus border to the Ust-Luga terminal on the Gulf of Finland. The length of the pipeline from Unecha to Ust-Luga is 998 kilometres (620 mi) and the length of the branch line to Kirishi oil refinery is 172 kilometres (107 mi). The pipeline passes Bryansk, Smolensk, Tver, Novgorod, and Leningrad regions.

Technical description

Baltic Pipeline System-II
Legend
Gulf of Finland Tanker's cargo
Luga River lines to Europe
Oil-pumping station # 9 Petroleum store
(Ust-Luga)
Ust-Luga Sea port
R-35 road To Kotly Right arrow
Left arrow To Keikino To Petrodvorets Right arrow
Left arrow To Ivangorod To Veimarn Right arrow
Left arrow To Gdov R-42 road
Left arrow To Osmino To Veimarn Right arrow
Left arrow To Partizanskaya To Prujitsy Right arrow
Luga River R-39 road
Oil-pumping station # 8
M-20 highway
Left arrow To Luga To St. Petersburg Right arrow
Luga River R-41 road
Left arrow To Luga To Lubań Right arrow
Oil-pumping station
Nevskaya
Pipe-end oil-pumping
station (Kirishi)
Oil-pumping station
Pes Right arrow
Kinef
Left arrow To Volkhov To Kirishi Right arrow
Volkhov River Pipeline Bridge
N-33 road
Left arrow To St. Petersburg To Pestovo Right arrow
Tigoda River
 Leningrad Oblast
 Novgorod Oblast
Left arrow To Volkhov To Chudovo Right arrow
M-10 ( E105)
Left arrow To St. Petersburg To Moscow Right arrow
Left arrow To St. Petersburg To Veliky Novgorod Right arrow
Kerest River
Left arrow To Dno To St. Petersburg Right arrow
R-47 road
Left arrow To Luga To Veliky Novgorod Right arrow
Left arrow To Luga To Veliky Novgorod Right arrow
Luga River
Oil-pumping station # 7
(Menusha)
R-52 road
Left arrow To Utorgosh To Shimsk Right arrow
Left arrow To Soltsi To Veliky Novgorod Right arrow
Shelon River A-116 highway
Left arrow To Dno To Staraya Russa Right arrow
Polist River
Porusia River
Oil-pumping station # 6
(Lopastino)
Left arrow To Kholm To Staraya Russa Right arrow
Lovat River R-51 road
Pola River
 Novgorod Oblast
 Tver Oblast
Left arrow To Velikiye Luki To Bologoye Right arrow
Oil-pumping station
Oil-pumping station (Borisovo) Right arrow
Left arrow (Velikiye Luki) Oil-pumping station # 5
(Andreapol)
Daugava River
Left arrow To Velikiye Luki To Rzhev Right arrow
M-9 highway
Left arrow To Velikiye Luki To Moscow Right arrow
Mezha River
 Tver Oblast
 Smolensk Oblast
Dubovitsy Oil-pumping station # 4
To Bely Right arrow
Ozerniy R-136 road
Left arrow To Smolensk To Roslavl Right arrow
M-1 highway Right arrow To Vyazma
Left arrow To Smolensk Right arrow To Sukhinichi
Dnieper River
Left arrow To Smolensk To Roslavl Right arrow
230 km
Oil-pumping station # 3
Left arrow To Smolensk To Roslavl Right arrow
Sozh River A-141 highway
Left arrow To Mstsislaw To Pochinok Right arrow
 Belarus R-96 road
Left arrow To Krychaw To Roslavl Right arrow
Iput River
Sosonki Oil-pumping station # 2
 Smolensk Oblast
 Bryansk Oblast
Iput River
Voronitsa River
Oil-pumping station #1
 Belarus (Unecha)
Left arrow To Kastyukovitchy Oil-pumping station
Left arrow To Mikhalki (Desna) Right arrow
(Mazyr) Druzhba pipeline

The initial capacity of the pipeline at the first stage is 10 million tons of oil per year, which will be upgraded to 50 million tons during the second stage. Of this, 12 million tons will be transported to Ust-Luga and 12 million tons to Kirishi refinery. Diameter of the pipeline will vary between 1,020 and 1,067 millimetres (40 and 42 in).

The construction cost is estimated at US$4 billion. The second stage is expected to be completed by December 2013.

The pipeline will have eight pumping stations. During the first stage, two new pumping stations were built, and two pumping stations (in Unecha and Andreapol) were renovated. During the second stage, four new pumping stations will be added, and the pumping station No.7 will be equipped with a tank farm with a capacity of 80,000 cubic metres (2,800,000 cu ft). In addition, the oil terminal in Ust-Luga was built.

References

  1. ^ "Official page of project" (in Russian). Transneft. Archived from the original on 2009-07-26. Retrieved 2009-09-20.
  2. "Transneft Launches Construction of 2nd Stage of Baltic Pipeline". Turkish Weekly. RIA Novosti. 2009-06-10. Archived from the original on 2012-03-20. Retrieved 2009-11-09.
  3. Groszkowski, Jakub (2012-04-18). "Czech concerns over the future of the Druzhba oil pipeline". CE Weekly. Centre for Eastern Studies. Archived from the original on 2012-05-11. Retrieved 2012-04-20.
  4. Geropoulos, Kostis (2007-05-26). "BPS-2 to redirect oil volumes from Druzhba pipeline". New Europe. Archived from the original on 2007-10-16. Retrieved 2007-12-29.
  5. "Russia Pipeline Extends Reach" (PDF). Iran Daily. 2008-05-24. Retrieved 2008-06-08.
  6. ^ "Putin Clears New Baltic Pipeline to Cut Oil Transit". Downstream Today. AFX News Limited. 2008-12-01. Archived from the original on 2012-04-26. Retrieved 2008-12-05.
  7. ^ "Russia builds Baltic oil pipeline to bypass Belarus". EurActiv. 2009-06-11. Archived from the original on 19 June 2009. Retrieved 2009-06-30.
  8. Stolyarov, Gleb; Zhdannikov, Dmitry; Pinchuk, Denis (2011-11-25). "Exclusive - Russia delays damaged Ust-Luga oil port launch". Reuters. Retrieved 2011-11-25.
  9. "Map of pipeline on builder cite" (in Russian). Transneft. Archived from the original on 2011-02-08. Retrieved 2009-09-20.
  10. Astakhova, Olesya (2011-10-20). "Russia cuts Baltic Belarus by-pass oil flow plan". Reuters. Retrieved 2011-11-25.
  11. ^ Konończuk, Wojciech (2009-06-17). "The construction of the BPS-2 oil pipeline starts" (PDF). EastWeek (172). Centre for Eastern Studies. Archived from the original (PDF) on 2009-08-16. Retrieved 2009-06-30.

External links

Pipeline systems of Russia by year of launch
Natural gas pipelines
Petroleum (oil) pipelines
Other pipelines