Beleghata (also known as Metropolitan), is a station of Line 6 of the Kolkata Metro located in Beleghata at Biswa Bangla Sarani, Dhapa of Kolkata, West Bengal, India, serving Beleghata and Metropolitan areas. The station is elevated beside the Eastern Metropolitan Bypass.
Location
This station is located in Beleghata across the service road and footpath on the eastern side of Biswa Bangla Sarani. The main elevated structure of the station is situated along the service road and footpath adjacent to the New Garia-bound lane of Biswa Bangla Sarani near the end of Maa Flyover. It is geographically located at 22°33′03″N 88°24′15″E / 22.550703°N 88.404094°E / 22.550703; 88.404094. The previous station of the station is Barun Sengupta metro station at a distance of 0.9 km (0.56 mi) and the next station is Gour Kishore Ghosh metro station at a distance of 1.7 km (1.1 mi).
History
This project was sanctioned in the budget of 2010–11 by Mamata Banerjee with a project deadline of six years. The execution of this project has been entrusted to RVNL at a cost of Rs 3951.98 crore. It will help to reduce travel time between the southern fringes of Kolkata to Netaji Subhas Chandra Bose International Airport. In October 2011, RVNL awarded Gammon India Limited, the tender for the construction of the metro corridor from VIP Bazar Metro Station to Nikko Park (Nalban metro station), including stations, as part of Package-II of Line 6. Amongst those metro stations, one near Beleghata was also sanctioned. In January 2012, the construction of the metro station along with the metro line started. The construction of the station was stopped in 2015 due to land dispute at Tagore Park culvert and a pair of its own footover bridges. The construction of the station started again in May 2017. But the metro couldn't be started due to a viaduct gap over Tagore Park culvert.
A week later after inauguration and a day after commercial run started on Kavi Subhash-Hemanta Mukhopadhyay section, in March 2024, RVNL announced the completion of that 76 m viaduct gap after construction of a single-span hanging steel bridge over the disputed Tagore Park culvert. This completed the viaduct upto Beleghata metro station, clearing the way for commercial operations at this station. Trial runs have started in March 2024.
As of November 2024, for the Beleghata station and the stretch from Hemanta Mukhopadhyay till IT Centre metro station to be inaugurated, construction of safety limit of 90 m (300 ft) metro viaduct beyond the station is completed but the footover bridge is yet to be connected from both side of road. On the other hand, filling a 650 m (2,130 ft) gap over Chingrighata crossing has not started and construction of Gour Kishore Ghosh, Nalban and IT Centre metro station is yet to be completed. The station is expected to be operational by mid-2025.
Station
Structure
Beleghata Metro Station is an elevated metro station and has a total of 3 levels. Station entrances and exits begin or end at the first level or ground level. Second-level or L1 or intermediate level houses station fare control, station agents, metro vending machines, crossovers, etc. The third level or L2 or the final level houses the platforms and rail tracks. The station is 200 meters long and 25 meters wide.
The station has four entrances and exits. The station is being built with state-of-the-art technology. In addition to staircases, it will be equipped with lifts and escalators. The station also has drinking water and toilet facilities.
Layout
Beleghata track layout | ||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Legend | ||||||||||||||||||||||||||||||||||||||||||
| ||||||||||||||||||||||||||||||||||||||||||
Station with two tracks and two side platforms |
G | Street Level | Exit/Entrance |
L1 | Mezzanine | Fare control, station agent, Metro Card vending machines, crossover |
L2 | Side platform doors will open on the left | |
Southbound | Towards →Kavi Subhash→ next station is Barun Sengupta→ | |
Northbound | →Towards ←Jai Hind← next station is Gour Kishore Ghosh← | |
Side platform doors will open on the left | ||
L2 |
Power and signal systems
Like other stations and lines of Kolkata Metro, this station has 750 volt DC powered third rail. The electricity system will be used to operate the train.
Train movement at this station will be managed by communication based train control signaling system. With this signal system, trains can be operated at intervals of 90 seconds.
Services
Services have not started from this station. Currently the station is under construction and is set to be opened in 2024.
Connections
This section is empty. You can help by adding to it. (December 2024) |
See also
References
- Chakraborty, Ajanta (20 February 2023). "Rail Vikas Nigam Limited plans 4 km extension from Ruby Metro to Beliaghata by puja". The Times of India. Archived from the original on 22 February 2023. Retrieved 11 March 2023.
- Abbas, Ajmal (30 January 2023). "First phase of Kolkata Metro's Orange Line all set for launch; covers Kavi Subash to Hemanta Mukherjee in 7 minutes". TimesNow. Archived from the original on 30 January 2023. Retrieved 11 March 2023.
- Staff Reporter (30 March 2024). "Kolkata Metro: CCRS Inspects Beleghata-Hemanta Muk. Stretch - Metro Rail News". Retrieved 8 May 2024.
- Basu, Kinsuk. "Metro Railway accuses state government of non-cooperation; government refutes claim". Telegraph India.
- "TRIAL RUN FOR TRAFFIC DIVERSION NEAR BELEGHATA METRO STATION STARTED".
- "Trial run for traffic diversion near Beleghata Metro started".
- "Rail Vikas Nigam Limited plans 4 km extension from Ruby Metro to Beliaghata by puja". The Times of India. 20 February 2023. ISSN 0971-8257. Retrieved 23 August 2023.
- Staff Reporter (23 August 2023). "Kolkata Metro: GM Reviews Orange Line's Kavi Subhas to Airport Stretch". Metro Rail News. Retrieved 23 August 2023.
- ^ "Beleghata-Ruby Section of Kolkata Metro Undergoes Inspection, Here's Why". News18. 30 March 2024. Retrieved 8 May 2024.
- ^ "Metro Railway Kolkata / Indian Railways Portal". mtp.indianrailways.gov.in. Retrieved 8 May 2024.
- Ghosh, Shreya (26 April 2024). "Kolkata Metro: From Stations To Trial Runs, Here's All About The Ruby-Beleghata Stretch". Curly Tales. Retrieved 8 May 2024.
- "Kolkata Metro: বাইপাসের উপর 'প্রায় তৈরি' নয়া মেট্রো স্টেশন, কবে জুড়বে গড়িয়া-এয়ারপোর্ট রুট?". Aaj Tak বাংলা (in Bengali). Retrieved 8 May 2024.
- "Kolkata Metro conducts trial runs on Orange Line from Ruby Crossing to Beleghata | Metro Rail Today". Metro Rail Today: Gateway to Rail & Metro Industry. Retrieved 8 May 2024.
- "Metro block after Bypass trial chaos". The Times of India. 9 February 2024. ISSN 0971-8257. Retrieved 8 May 2024.
- "Rail Vikas Nigam Limited plans 4 km extension from Ruby Metro to Beliaghata by puja". The Times of India. 20 February 2023. ISSN 0971-8257. Retrieved 8 May 2024.
- "Metro Railway Kolkata / Indian Railways Portal". mtp.indianrailways.gov.in. Retrieved 8 May 2024.
- ^ "Metro Railway Kolkata / Indian Railways Portal". mtp.indianrailways.gov.in. Retrieved 8 May 2024.
- Staff Reporter (30 April 2024). "Kolkata Metro Conducts Trial Runs On New Orange Line Stretch - Metro Rail News". Retrieved 8 May 2024.
- "Kolkata Metro Update: Trial runs to commence on extended Orange line from Ruby Crossing to Beleghata". Financialexpress. 25 April 2024. Retrieved 8 May 2024.
- MPost (30 March 2024). "Min & Kolkata Police refute Metro's claim of non-cooperation from state". www.millenniumpost.in. Retrieved 8 May 2024.
- ^ "Rail set to take over East-West". The Telegraph. Calcutta, India. 8 February 2011. Archived from the original on 13 February 2011.
- ""Seven projects meant to change the face of Calcutta are entangled in a web of land politics and pandering. Metro explores the tunnel vision"". Telegraph india.
- "বরুণ সেনগুপ্ত মেট্রো স্টেশনের নির্মাণ কাজ তুঙ্গে, অন্দরমহলটা দেখে নিন". Eisamay (in Bengali). Retrieved 8 May 2024.
- "Kolkata Metro Update: Chief Commissioner of Railway Safety inspects Beleghata-Ruby section". Financialexpress. 30 March 2024. Retrieved 8 May 2024.
- ^ MP, Team (29 March 2024). "Chief Commissioner of Rly Safety inspects Beleghata to Hemanta Mukhopadhyay (Ruby) stretch". www.millenniumpost.in. Retrieved 8 May 2024.
- "Details of tenders/contracts" (PDF). Archived from the original (PDF) on 19 March 2020. Retrieved 30 March 2024.
- ""Road Ahead….. Projects sanctioned"". mtp.indianrailways.gov.in. Retrieved 28 March 2024.
- ""Construction of VIP Bazar station begins after two years"".
- ^ "Airport-New Garia Metro: Site visit next week to bridge VIP Bazar gap". The Times of India. 12 March 2023. ISSN 0971-8257. Retrieved 28 March 2024.
- "Man electrocuted at construction site". The Times of India. 19 February 2024. ISSN 0971-8257. Retrieved 28 March 2024.
- "শেষের মুখে কলকাতা মেট্রোর আরও ১ স্টেশনের কাজ! ভিতরটা কেমন হল? রইল 'ফার্স্ট লুক'". Hindustantimes Bangla (in Bengali). 28 September 2023. Retrieved 29 March 2023.
- "মেট্রোর পথ করতে নোনাডাঙায় সরছে পুরোনো ভিআইপি বাজার". Eisamay (in Bengali). Retrieved 28 March 2024.
- "CRS check till Metropolitan: No Ruby ops on Thurs, Fri". The Times of India. 27 March 2024. ISSN 0971-8257. Retrieved 29 March 2024.
- "Kolkata: Pipe bridge lifted out of Metro alignment". The Times of India. 15 July 2020. ISSN 0971-8257. Retrieved 29 March 2024.
- "Ritwik Ghatak Metro Station: ঋত্বিক ঘটক মেট্রো স্টেশনের কাজ শেষ পর্যায়ে, ফাস্ট লুকেই হাঁকাল ছক্কা! » Najarbandi 24X7". najarbandi.in (in Bengali). 29 September 2023. Retrieved 29 March 2024.
- "Hanging bridge on Bypass solves Metro problem at Tagore Park". The Times of India. 3 November 2023. ISSN 0971-8257. Retrieved 29 March 2024.
- PTI (25 April 2024). "Kolkata Metro to start trial runs along Ruby-Beleghata stretch". ThePrint. Retrieved 8 May 2024.
- "Traffic starts moving along Tagore Park western flank". The Times of India. ISSN 0971-8257. Retrieved 16 March 2024.
- "Kolkata Metro Orange Line Expands for Beleghata: Trials Start - TimesProperty". timesproperty.com. Retrieved 8 May 2024.
- SNS (1 April 2024). "Blame game between Kolkata Metro, city police over Orange Line delays". The Statesman. Retrieved 8 May 2024.
- "Kolkata Metro: Trial Runs Begin For Seamless Commutes From Ruby Crossing To Beleghata". News18. 26 April 2024. Retrieved 8 May 2024.
- "Metro Railway Kolkata / Indian Railways Portal". mtp.indianrailways.gov.in. Retrieved 8 May 2024.
- "Metro Railway rues delay in getting NOC from police for construction work near Beleghata station". The Telegraph Online.
- "Metro Railway Kolkata / Indian Railways Portal". mtp.indianrailways.gov.in. Retrieved 8 May 2024.
- "Metro Railway Kolkata / Indian Railways Portal". mtp.indianrailways.gov.in. Retrieved 8 May 2024.
- ^ "Ritwik Ghatak Metro Station: ঋত্বিক ঘটক মেট্রো স্টেশন চোখ ধাঁধানো, কাজ প্রায় শেষ, কেমন হল? দেখুন". Aaj Tak বাংলা (in Bengali). Retrieved 29 March 2024.
- "Metro Railway Kolkata / Indian Railways Portal". mtp.indianrailways.gov.in. Retrieved 8 May 2024.
- "নিউ গড়িয়া-বিমানবন্দর মেট্রো করিডোরে বড় খবর, নতুন স্টেশনের ছবি দেখুন". Eisamay (in Bengali). Retrieved 29 March 2024.
- "Kolkata Metro update: Authorities conduct trial runs on extended Orange line from Ruby Crossing to Beleghata – Details inside". Financialexpress. 28 April 2024. Retrieved 8 May 2024.
- MP, Team (29 April 2024). "Trial run by Metro from Hemanta Mukhopadhyay (Ruby) to Beleghata". www.millenniumpost.in. Retrieved 8 May 2024.
- PTI (29 March 2024). "Beleghata-Ruby section of Kolkata Metro undergoes inspection". ThePrint. Retrieved 8 May 2024.
Kolkata Metro | ||||||||
---|---|---|---|---|---|---|---|---|
Blue line (Line 1) |
| |||||||
Green line (Line 2) |
| |||||||
Purple Line (Line 3) |
| |||||||
Yellow Line (Line 4) |
| |||||||
Pink Line (Line 5) |
| |||||||
Orange Line (Line 6) |
| |||||||
See also | ||||||||