Directlink (Terranora) Interconnector | |
---|---|
Location of Directlink (Terranora) Interconnector | |
Location | |
Country | Australia |
State | New South Wales |
General direction | south-north |
From | Mullumbimby |
To | Bungalora |
Ownership information | |
Owner | Energy Infrastructure Investments (EII) |
Operator | APA Group |
Construction information | |
Manufacturer of conductor/cable | ABB |
Manufacturer of substations | ABB |
Contractors | TransÉnergie Australia |
Commissioned | 2000 |
Technical information | |
Type | Land cable (buried) |
Type of current | HVDC VSC |
Total length | 63 km (39 mi) |
Power rating | 180 MW |
AC voltage | 110 kV (Bungalora), 132 kV (Mullumbimby) |
DC voltage | ±80 kV |
No. of circuits | 3 |
Directlink (Terranora) Interconnector is a mixed buried and above ground 59 kilometre (37 mi) High Voltage Direct Current (HVDC) electricity transmission cable route from near Lavertys Gap (28°34′15″S 153°27′8″E / 28.57083°S 153.45222°E / -28.57083; 153.45222 (Directlink - Mullumbimby Static Inverter Plant)), 5 kilometres (3.1 mi) Southwest of Mullumbimby, New South Wales and Bungalora (28°15′20″S 153°28′20″E / 28.25556°S 153.47222°E / -28.25556; 153.47222 (Directlink - Bungalora Static Inverter Plant)) & connected via a 3.5 km (2.2 mi) AC Overhead Transmission Line to the NorthEast to the Terranora Electrical Substation (28°14′28.3″S 153°30′12.7″E / 28.241194°S 153.503528°E / -28.241194; 153.503528 (Essential Energy - Terranora Electrical Substation)) @ Terranora, New South Wales in Eastern Australia. The DC cables alternate between above ground in a galvanised steel trough and below ground with depths up to 1 metre.
It is one of the two interconnections used to trade electricity between New South Wales and Queensland (the other is the 330 kV Dual Circuit Queensland – New South Wales Interconnector (QNI)).
History
The interconnector was developed by a joint venture of NorthPower (later Country Energy), TransÉnergie–a subsidiary of Hydro-Québec, and Fonds de solidarité FTQ. The motivation to build the interconnector was the power shortage in Southern Queensland and surplus capacities in New South Wales. It was developed as an Independent Transmission Project. It was commissioned in December 1999 and it started operations in April 2000. It was the first time that transmission systems of New South Wales and Queensland were linked. The construction cost US$70 million.
In December 2006, it was announced that Directlink would be purchased by Australian Pipeline Trust (APT, a part of APA Group) for US$133 million. The transaction was completed in February 2007.
Originally, the interconnector operated as a non-regulated market network service. However, on 6 May 2004 an application to convert it to a regulated network service was submitted. The application was approved by the Australian Energy Regulator on 10 March 2006.
In December 2008, ownership of Directlink (as well as Murraylink) was transferred to the Energy Infrastructure Investments Group, while the APA Group continued as the operator. The ownership of EII is allocated as APA with 19.9%, Japan-based Marubeni Corporation with 49.9%, and Osaka Gas with 30.2%.
Technical description
Directlink (Terranora) interconnector is a 59-kilometre (37 mi) HVDC land cable route. The system has three 65 MVA Voltage Source Converters at each station connected by three pairs of transmission cables. Each pair of cables operates at +/-80 kV and transmits 60 MW. In New South Wales it is connected to a 132 kV alternating current transmission grid and in Queensland to 110 kV alternating current transmission grid.
The total rating of the interconnector is 180 MW. The maximum net transfer minus losses is around 170 MW. If one pair of cables malfunctions, the available capacity is around 115 MW. If two pairs of cables are out of service, the capacity is around 57 MW. However, in some cases for a limited time period the interconnector has operated in an overloading mode for up to 250 MW. The limiting factor for flow in the New South Wales direction is the thermal ratings of the Terranora–Mudgeeraba 110 kV lines and Mullumbimby–Dunoon 132 kV lines, and for flow in the Queensland direction is the thermal ratings of the Lismore–Dunoon 132 kV lines.
HVDC VSC was chosen for this project for reasons of low environmental impact of the transmission route and the ability of the IGBT converter stations at each end to accurately control both real and reactive power. Individual water-cooled IGBT modules are rated at 2.5 kV and 500 A, with multiple units connected in series to achieve the required voltage rating.
References
- ^ "Development of Electricity Supply to the NSW Far North Coast. Supplementary Report" (PDF). TransGrid. May 2010. p. 7. Archived from the original (PDF) on 24 July 2011. Retrieved 12 June 2011.
- ^ "Directlink Project Queensland – New South Wales in Australia" (PDF). ABB. Archived from the original (PDF) on 20 August 2011. Retrieved 9 June 2011.
- ^ Grant-Taylor, Tony (20 December 2016). "APT buys DirectLink line". The Courier-Mail. News Limited. Retrieved 12 June 2011.
- "Network Interconnection: Murraylink: the underground connection". Power-Gen Worldwide. PennWell Corporation. 1 May 2001. Retrieved 8 June 2011.
- ^ Sood, Vijay K. (2004). HVDC and FACTS controllers: applications of static converters in power systems. Springer. pp. 172, 174. ISBN 978-1-4020-7890-3.
- "Electric/Gas Utilities Could Threaten Telecoms". Transmission & Distribution World. Penton Media. 1 February 1999. Archived from the original on 28 September 2011. Retrieved 12 June 2011.
- Wong, Fayen (25 February 2008). "APA Group H1 profit rises, upgrades outlook". Reuters. Retrieved 12 June 2011.
- "AER final decision approves Directlink conversion" (Press release). AER. 10 March 2006. Archived from the original on 25 March 2012. Retrieved 12 June 2011.
- "Electricity Transmission Network Service Providers Directlink & Murraylink Amended Cost Allocation Methodologies" (PDF). AER. March 2010. Retrieved 12 June 2011.
- Electricity Transmission Network Service Providers - Directlink and Murraylink amended Cost Allocation Methodologies - March 2010
- "electricity transmission interconnectors - APA Group". www.apa.com.au. Retrieved 30 December 2018.
- ^ "Terranora interconnector (Directlink)". ABB. Retrieved 9 June 2011.
- Arrillaga, J.; Liu, Y. H.; Watson, N. R. (2007). Flexible power transmission: the HVDC options. John Wiley & Sons. p. 310. ISBN 978-0-470-05688-2.
- "Review of Last Resort Planning Powers" (PDF). Sinclair Knight Merz. AEMC. 17 September 2010. p. 5. Archived from the original (PDF) on 6 March 2016. Retrieved 12 June 2011.