Length | 63 km (39 mi)47.0 km (29.2 mi) built 16.16 km (10.04 mi) under construction |
Major junctions | |
From | Sofia |
To | Kalotina ; |
Location | |
Country | Bulgaria |
Major cities | Sofia, Slivnitsa |
Highway system | |
The Europe Motorway (Bulgarian: Автомагистрала "Европа", Avtomagistrala "Evropa"), designated A6, is a motorway that will link the Bulgarian capital Sofia with Serbia at the Kalotina border crossing. Spanning approximately 64.15 kilometers (39.86 mi), the motorway is planned to be connected with the Serbian A4 motorway.
In 2018 the government changed its name from Kalotina motorway to Europe motorway, as well as merging the Northern Sofia Bypass in it and designating it A6.
Tenders
The first 31.5 km of the motorway (Kalotina–Herakovo) were tendered in 2012, and the construction works were expected to begin in 2013. The route in the tendered section follows the existing major road 8/European route E80 road and also is part of Pan-European Corridor X, branch C. In October 2013 the tender procedure was cancelled due to lacking financing under the allocated for Bulgaria EU funds.
In May 2014, the section between Kalotina and Herakovo was retendered. This time it has been divided into 2 sublots, Kalotina-Dragoman and Dragoman-Herakovo. The costs are estimated at 200 million levs (102.26 million euro). Later, this tender also was cancelled.
On September 13, 2017, the sections Kalotina-Dragoman and Dragoman-Slivnitsa were put to tender; Strabag is to build the first section, GBS-Infrastructure the latter.
Construction
Construction of the 17 km long Dragoman - Slivnitsa section was launched in the second half of May 2019 and was opened in November 2020 Construction of Dragoman - Kalotina section is currently ongoing. There is presently a 4-lane undivided highway between Slivnitsa and the Sofia Ring Road.
Exits
This article contains a bulleted list or table of intersections which should be presented in a properly formatted junction table. Please consult this guideline for information on how to create one. Please improve this article if you can. (November 2021) |
Exit | km | Destinations | Lanes | Notes |
---|---|---|---|---|
0 | Kalotina; Serbia, | In service | ||
1+644 | Kalotina | In service | ||
13+046 | Dragoman-west | In service | ||
14+389 | Dragoman-east | In service | ||
25+850 | Slivnitsa-west | In service | ||
29+206.86 | Slivnitsa-east | In service | ||
45+540 | Kostinbrod | Under Construction | ||
48+460 | Volujak | Under Construction | ||
48+611 | Sofia Ring Road | In service | ||
51+695 | Rozhen blvd. | In service | ||
53+462 | Iliyantsi blvd. | Not yet in service | ||
57+750 | Chepinsko shose str. | In service | ||
59+282 | East tangent, Sofia Airport | Not yet in service | ||
63+611 | Sofia Ring Road | In service |
Northern Bypass Highway
The Northern Bypass Highway or Sofia Northern Speed Tangent (Bulgarian: Северна скоростна тангента, Severna Skorostna Tangenta) is a dual carriageway, grade separated road with controlled-access, designed for high speeds. The Northern Bypass has three traffic lanes and an emergency lane in each carriageway. The motorway gets around the Bulgarian capital Sofia from north to carry the transit traffic, which otherwise would pass through the city or via the Sofia Ring Road.
The Bypass is an important thoroughfare, as it connects four motorways - A1 Trakia motorway (via the Sofia ring road), A2 Hemus motorway and the A3 Struma motorway. Also, it connects 3 Pan-European corridors - IV, VIII and X.
Construction
In 2012, a tender for construction was announced. Construction works were expected to begin in 2013, but due to litigation the contract for design and build was signed in February 2014. The term for implementation of the contract is 18 months. Due to land expropriation issues, the construction works started in February 2015.
The first 13 kilometers of the motorway were opened in the end of 2015 and the remaining segment was inaugurated on 28 April 2016.
Gallery
- Europe motorway near Slivnitsa
- Europe motorway
Notes
References
- "Construction of Sofia-Kalotina Motorway". Operational programme on Transport and Transport Infrastructure 2014 – 2020. Retrieved 9 September 2018.
- "Правителството създаде нова магистрала – "Европа"" (in Bulgarian). dnevnik. Retrieved 28 December 2018.
- "Tender for construction of Kalotina motorway". napi via aop.bg.
- "400 M leva needed for two roads near Sofia". monitor (in Bulgarian). 2013-06-03. Archived from the original on 2013-09-28.
- "10 applicants for 32 km of Sofia-Kalotina motorway". infrastructure.bg (in Bulgarian). 2013-03-15. Archived from the original on 2016-03-04. Retrieved 2013-03-15.
- "РЕШЕНИЕ Номер: 169 от 17.10.2013 г. за прекратяване на процедура за възлагане на обществена поръчка". aop.bg.
- ""Определяне на изпълнител за проектиране и строителството на обект: " Модернизация на съществуващото трасе на път І-8 "Калотина-СОП" с две обособени позиции, както следва: Обособена позиция 1: Участък 1 от км 1 + 000 до км 15+500 Обособена позиция 2: Участък 2 от км 15+500 до км 32+447" (in Bulgarian). aop.bg. 21 May 2014.
- "Bulgaria's Sofia-Kalotina Highway Section Procurement Announced". novinite.com. 21 May 2014.
- "Austrian and Bulgarian Companies will Build the Sofia-Kalotina Highway". Sofia, Bulgaria: Novinite.com. 2018-07-30. Retrieved 2022-09-04.
- "Ноември пускат първата част от АМ "Европа"". 5 October 2020.
- "Участък от автомагистрала "Европа" ще бъде открит в четвъртък". www.bta.bg (in Bulgarian). Retrieved 28 April 2023.
- "Участък от автомагистрала "Европа" ще бъде открит в четвъртък". www.bta.bg (in Bulgarian). Retrieved 28 April 2023.
- "Участък от автомагистрала "Европа" ще бъде открит в четвъртък". www.bta.bg (in Bulgarian). Retrieved 28 April 2023.
- "Eleven Tenders Were Opened for the Design and Construction of the North-Speed Tangent". api.government.bg. Archived from the original on 8 April 2013. Retrieved 17 January 2013.
- "400 M leva needed for two roads near Sofia". monitor (in Bulgarian). 6 March 2013. Archived from the original on 28 September 2013.
- "Only 4 price bids opened in the tender for Northern tangent". infrastructure.bg (in Bulgarian). 12 March 2013.
- "Започва проектирането и строителството на Северната скоростна тангента". vestnikstroitel.bg. 17 February 2014.
- "АПИ преговаря за отчуждаването на имоти за Северната скоростна тангента" (in Bulgarian). infrastructure.bg. 6 January 2015.
- "The Construction of North Speed Tangent Starts up". RIA. 18 February 2015.
- "Пуснаха движението по 13-километров участък от Северната скоростна тангента" (in Bulgarian). infrastructure.bg. 30 December 2015. Archived from the original on 26 January 2016. Retrieved 28 December 2018.
- "Изцяло е пусната за движение Северната скоростна тангента" (in Bulgarian). API. 28 April 2016.
Roads in Bulgaria | |
---|---|
Motorways | |
Expressways | |
1st class roads | |
2nd class roads |
Categories: