Karachi-Hyderabad (M-9) section 136 km (Re-carpeting of existing Super Highway)
Hyderabad-Sukkur (M-6) section 296 km
Sukkur-Multan (M-5) section 387 km
Multan-Abdul Hakeem (M-4) section 103
Abdul Hakeem-Lahore (M-3) section 230 km
Lahore-Islamabad (M2) section 376 km
Islamabad-Peshawar (M1) section 166 km
The 296-km stretch of M-6 from Hyderabad to Sukkur is the last missing link on the Karachi-Lahore motorway on which construction work has yet to be started.
Sections
Section
Length (km)
Length (mi)
Starting Date
Completion date
Karachi-Hyderabad
136
85
March 2015
December 2017
Hyderabad-Sukkur
296
184
March 2017
February 2020
Sukkur-Multan
387
240
May 2016
August 2019
Multan-Abdul Hakeem
103
64
January 2016
August 2019
Abdul Hakeem-Lahore
230
140
January 2016
31 March 2019
Lahore Abdul Hakeem Motorway