Misplaced Pages

Wyaralong Dam

Article snapshot taken from Wikipedia with creative commons attribution-sharealike license. Give it a read and then ask your questions in the chat. We can research this topic together.
(Redirected from Lake Wyaralong)

Dam in South East Queensland
Wyaralong Dam
The dam wall, from the viewing platform.
Wyaralong Dam is located in QueenslandWyaralong DamLocation of the Wyaralong Dam
in Queensland
CountryAustralia
LocationSouth East Queensland
Coordinates27°54′33″S 152°52′52″E / 27.90917°S 152.88111°E / -27.90917; 152.88111
PurposePotable water supply
StatusOperational
Construction began2010 (2010)
Opening date2011 (2011)
Construction costA$380 million
Operator(s)SEQ Water
Dam and spillways
Type of damGravity dam
ImpoundsTeviot Brook
Height48 m (157 ft)
Length490 m (1,610 ft)
Dam volume218,300×10^ m (7,710×10^ cu ft)
Spillway typeUncontrolled
Reservoir
Total capacity102,883 ML (22,631×10^ imp gal; 27,179×10^ US gal)
Catchment area546 km (211 sq mi)
Surface area1,230 ha (3,000 acres)
Website
www.seqwater.com.au

The Wyaralong Dam is a mass concrete gravity dam with an un-gated spillway across the Teviot Brook that is located in the South East region of Queensland, Australia. The main purpose of the dam is for supply of potable water for the Scenic Rim region. The dam was initiated by the Queensland Government in 2006 as a result of the prolonged Millennium drought which saw the catchment areas of South East Queensland's dams receive record low rain. It was completed in 2011.

Location and features

The dam is located approximately 14 kilometres (8.7 mi) north-west of Beaudesert. The dam wall itself is split between the localities of Wyaralong and Allenview, but the bulk of impounded water is within Wyaralong.

The Wyaralong Dam was completed prior to the 2010–2011 Queensland floods. On January 11, during the flood period, the Mayors of both Logan City and Scenic Rim said they believed that Logan had been spared a great deal of flood damage because of the dam.

The concrete dam structure is 48 metres (157 ft) high and 463.60 metres (1,521.0 ft) long. The dam wall is constructed from a medium cementitious mix roller compacted concrete, which is a zero-slump concrete that is placed in 300mm thick lifts and compacted with vibratory compactors. The foundation is a sub horizontal dipping blocky sandstone. The dam is built with a 130-metre (430 ft) wide uncontrolled central primary spillway and an uncontrolled left bank secondary spillway which commences discharging at the 1:100 year flood level. The dam cross section is rather squat in order to provide sufficient resistance against potential sliding along foundation bedding planes. The 218,300-thousand-cubic-metre (7,710×10^ cu ft) dam wall holds back the 103,000-megalitre (23×10^ imp gal; 27×10^ US gal) reservoir when at full capacity. From a catchment area of 546 square kilometres (211 sq mi) that includes much of the western portion of the McPherson Range, the dam creates a reservoir with a surface area of 1,230 hectares (3,000 acres). Teviot Brook and the surrounding land is a recognised Aboriginal Pathway with significant cultural heritage values.

The dam is managed by SEQ Water as part of a water security project in the South East Queensland region, known as the South East Queensland Water Grid. The outlet is on the right bank and is capable of abstracting water from any level of the reservoir by the use of baulks. The outlet includes an innovative and operationally complex bidirectional fish lift, which uses a single hopper to transport fish in both upstream and downstream directions.

Conception

The site was identified in a 1990 study, Water Supply Sources in South-East Queensland, as a future source of water supply for the South East Queensland region. In this report, the site of Wyaralong Dam was ranked 13th out of 15 studied possible dam locations in the region. A location on the Albert River at Glendower, also near Beaudesert, was the preferred location and the government subsequently bought back all the land required for the Glendower Dam. A new dam was not expected to be required until 2060 or later and Glendower Dam remained the preferred dam site, the land already fully government owned. Properties previously acquired by the government are progressively being sold to private buyers.

In October 2005, in advance of the state election, the Queensland government announced Wyaralong Dam as the new preferred option, even after recent studies into possible dam locations found a location upstream on the Logan River to be a more reliable option. After a series of studies, a Senate Inquiry and much contested information, Federal Environment Minister Peter Garrett granted approval for the Wyaralong Dam in November 2008.

The dam is a storage and regulation facility. It does not discharge directly into the piped reticulation network, but rather discharges back into the natural drainage network of creeks and brooks. Water released from the dam flows downstream along Teviot Brook to Cedar Grove Weir, where it is diverted for treatment and use in the piped network.

Construction

Picnic area and boat ramp

The construction was tendered under an alliance contract. In this type of contract risks and rewards are shared by all the proponents including designers constructors and the owner. Queensland Dam Consortium won the tender for the dam's construction, and the Alliance was formed from their members which included Macmahon Construction as the lead contractor, Hydro Tasmania, Snowy Mountains Engineering Corporation, Paul Rizzo and Associates (USA), ASI Contractors (USA) and Queensland Water Infrastructure the special purpose vehicle created by the Queensland Government owner to deliver the project. The Alliance contract for dam construction was for a little over A$100 million. However it was widely reported that the building costs for the dam would total A$333 million. The latter figure includes the cost of the Bromelton Offpeak Storage Project, Cedar Grove Weir and the reconstruction of a length of the Boonah to Beaudesert Road.

Work on access roads began in early 2009 and construction of the dam wall began in early 2010. The diversion channel was plugged on 17 December 2010, allowing the dam to begin to fill. The dam site was opened to the public on 3 June 2011. The 12 kilometres (7.5 mi) of new road between Boonah and Beaudesert were constructed under a separate contract by Fulton Hogan.

The dam cost A$380 million to construct, including purchasing farmland flooded by the dam reservoir.

Treatment

By late 2012 the dam still had not been connected to the SEQ Water Grid because it contains water so mineralised it is cheaper to produce desalinated water than to treat it. The Wyaralong water treatment plant is expected to cost A$235 million to construct. Funding for the plant was planned for the 2014/15 financial year. In 2017 SEQ Water external relations manager Mike Foster stated the Wyaralong Water Treatment Plant wouldn't be necessary until "2030 or beyond".

January 2011 floods

Main article: 2010–2011 Queensland floods

As a result of rainfall during the 2010–2011 Queensland floods the dam filled to 100% capacity, just 25 days after the wall was plugged to hold water, but before its completion. By 10 January during the flood period, the dam held 83,133 megalitres (18,287×10^ imp gal; 21,961×10^ US gal), 80.7 per cent of its 103,000 megalitres (23×10^ imp gal; 27×10^ US gal) capacity. Parts of the dam were still under construction, but its wall was plugged to hold water on 17 December 2010. On 11 January the dam filled and began to overtop at 9:27am, Following the overtopping, in the first 24 hours over 17,300 megalitres (3,800×10^ imp gal; 4,600×10^ US gal) of water flowed over the primary spillway and entered the Logan River at Cedar Grove.

See also

References

  1. ^ "Register of Large Dams in Australia" (Excel (requires download)). Dams information. Australian National Committee on Large Dams. 2010. Archived from the original on 12 December 2013. Retrieved 5 July 2014.
  2. ^ "Wyaralong Dam". Water supply: Dams and weirs. Seqwater. 2014. Archived from the original on 14 April 2014. Retrieved 5 July 2014.
  3. ^ "Wyaralong". Seqwater. Archived from the original on 9 March 2022. Retrieved 19 March 2022.
  4. "Queensland Globe". State of Queensland. Retrieved 7 June 2020.
  5. "On the road in Logan today". Logan West Leader. 11 January 2011. Archived from the original on 15 January 2011. Retrieved 13 January 2011.
  6. ^ "Wyaralong Dam contractors announced". Queensland Water Infrastructure Pty Ltd. Archived from the original on 2 October 2009. Retrieved 22 October 2009.
  7. Hurst, Daniel (7 July 2009). "Water funds slash debt". The Bayside Bulletin. Retrieved 21 April 2008.
  8. "Glendower trio makes stunning $15.8m". Queensland Country Life. 24 November 2018. Archived from the original on 6 January 2020. Retrieved 19 March 2022.
  9. "A country lifestyle". Jimboomba Times. 23 October 2018. Archived from the original on 22 March 2019. Retrieved 19 March 2022.
  10. "Glendower properties pull in $8m". North Queensland Register. 7 August 2018. Archived from the original on 7 August 2018. Retrieved 19 March 2022.
  11. "Wyaralong dam decision 'devastating' for residents". ABC News. Australia. 26 November 2008. Archived from the original on 10 November 2012. Retrieved 22 October 2009.
  12. ^ "Wyaralong Dam to boost jobs, economy: Lucas". ABC News. Australia. 21 January 2009. Archived from the original on 8 July 2012. Retrieved 22 October 2009.
  13. ^ "Wyaralong Dam". Seqwater. Archived from the original on 15 July 2012. Retrieved 27 November 2012.
  14. Maeseele, Melanie (4 June 2011). "Summer rains fill up dam". The Queensland Times. Archived from the original on 22 March 2014. Retrieved 27 November 2012.
  15. ^ Thomson, Tuck (16 October 2012). "Bligh government-built Wyaralong Dam an expensive 'mistake'". The Courier-Mail. Queensland. Archived from the original on 6 May 2016. Retrieved 16 October 2012.
  16. Lion, Patrick (19 June 2011). "Water wasted as State Government decides against tapping into $350m dam". The Sunday Mail. Queensland. Retrieved 27 November 2012.
  17. Cunningham, Susie (9 October 2015). "Dam won't join water grid until at least 2030". Beaudesert Times. Retrieved 19 October 2022.
  18. "Wivenhoe Dam hits record high". The Queensland Times. 11 January 2011. Archived from the original on 13 January 2011. Retrieved 13 January 2011.

External links

Water supply in Queensland, Australia
Dams and reservoirs by region
South East Queensland
Darling Downs
South West Queensland
Wide Bay–Burnett
Central Queensland
North Queensland
Far North Queensland
North West Queensland
Historical
Water resource management by function
Companies and government agencies
Other sources / facilities
Regulators
Historical
Categories: