(Redirected from Loss of load expectation) Term for when the available generation capacity in an electrical grid is less than the system load Not to be confused with Load loss.

Loss of load in an electrical grid is a term used to describe the situation when the available generation capacity is less than the system load. Multiple probabilistic reliability indices for the generation systems are using loss of load in their definitions, with the more popular being Loss of Load Probability (LOLP) that characterizes a probability of a loss of load occurring within a year. Loss of load events are calculated before the mitigating actions (purchasing electricity from other systems, load shedding) are taken, so a loss of load does not necessarily cause a blackout.

Loss-of-load-based reliability indices

Multiple reliability indices for the electrical generation are based on the loss of load being observed/calculated over a long interval (one or multiple years) in relatively small increments (an hour or a day). The total number of increments inside the long interval is designated as N {\displaystyle N} (e.g., for a yearlong interval N = 365 {\displaystyle N=365} if the increment is a day, N = 8760 {\displaystyle N=8760} if the increment is an hour):

  • Loss of load probability (LOLP) is a probability of an occurrence of an increment with a loss of load condition. LOLP can also be considered as a probability of involuntary load shedding;
  • Loss of load expectation (LOLE) is the total duration of increments when the loss of load is expected to occur, L O L E = L O L P N {\displaystyle {LOLE}={LOLP}\cdot N} . Frequently LOLE is specified in days, if the increment is an hour, not a day, a term loss of load hours (LOLH) is sometimes used. Since LOLE uses the daily peak value for the whole day, LOLH (that uses different peak values for each hour) cannot be obtained by simply multiplying LOLE by 24; although in practice the relationship is close to linear, the coefficients vary from network to network;
  • Loss of load events (LOLEV) a.k.a. loss of load frequency (LOLF) is the number of loss of load events within the interval (an event can occupy several contiguous increments);
  • Loss of load duration (LOLD) characterizes the average duration of a loss of load event: L O L D = L O L E L O L F {\displaystyle {LOLD}={\frac {LOLE}{LOLF}}}

One-day-in-ten-years criterion

A typically accepted design goal for L O L E {\displaystyle LOLE} is 0.1 day per year ("one-day-in-ten-years criterion" a.k.a. "1 in 10"), corresponding to L O L P = 1 10 365 0.000274 {\displaystyle {LOLP}={\frac {1}{10\cdot 365}}\approx 0.000274} . In the US, the threshold is set by the regional entities, like Northeast Power Coordinating Council:

resources will be planned in such a manner that ... the probability of disconnecting non-interruptible customers will be no more than once in ten years

— NPCC criteria on generation adequacy

See also

References

  1. ^ Ascend Analytics 2019.
  2. Elmakias 2008, p. 174.
  3. Duarte & Serpa 2016, p. 157.
  4. Wang, Song & Irving 2010, p. 151.
  5. Ela et al. 2018, p. 134.
  6. Billinton & Huang 2006, p. 1.
  7. Ibanez & Milligan 2014, p. 4.
  8. NERC 2018, p. 13.
  9. Arteconi & Bruninx 2018, p. 140.
  10. ^ Meier 2006, p. 230.
  11. ^ Tezak 2005, p. 2.

Sources

Reliability indices
Generic
Electricity distribution
Electricity generation
Stub icon

This electricity-related article is a stub. You can help Misplaced Pages by expanding it.

Categories: