Main Southern railway line, New South Wales

Article snapshot taken from Wikipedia with creative commons attribution-sharealike license. Give it a read and then ask your questions in the chat. We can research this topic together.
(Redirected from Old Main South railway line) Railway line in New South Wales, Australia

Main Southern Line
1916 Binalong station (now closed), 2013
Overview
StatusOpen
Termini
Continues fromMain Suburban railway line
Continues asNorth East railway line
Stations46 open
History
Commenced1855
Completed1881
Technical
Line length650 km (400 mi)
Number of tracks2 (Lidcombe-Junee) 1 (Junee-Albury)
Track gauge1,435 mm (4 ft 8+1⁄2 in)
Electrification1500 V DC Overhead catenary as far as Macarthur
Route map

Legend
km km from Central
Main Northern line
 
Olympic Park line
 
Main Suburban line
to Central
Lidcombe 16.61 Port Botany line
Main Suburban
line
18.36 Berala
19.86 Regents Park
Granville 21.22
Southern Sydney
Freight Line
Main Western line Bankstown line
Merrylands 23.47 21.19 Sefton
Guildford 25.72 22.31 Chester Hill
Yennora 27.44 23.67 Leightonfield
Fairfield 29.00 24.50 Villawood
Canley Vale 30.98 25.89 Carramar
Old Main South line
Cabramatta 28.43
to
Warwick Farm
Racecourse
Warwick Farm 34.16
Holsworthy line
Liverpool 35.68
Casula 38.80
to
Moorebank
Intermodal Terminal
East Hills line
41.93 Glenfield
South West
Rail Link
43.80 Macquarie Fields
44.14 Bumberry Junction
45.65 Ingleburn
49.67 Minto
52.63 Leumeah
54.71 Campbelltown
56.58 Macarthur
Southern Sydney
Freight Line
limit of electrification &
suburban passenger
Glenlee colliery line
services
 
60.71 Glenlee
to
Menangle
Racecourse
62.85 Menangle Park
63.95 North Menangle
Nepean River Bridge
65.33 Menangle
73.32 Douglas Park
Maldon –
Dombarton line
82.50 Maldon
85.25 Picton
Stonequarry Creek
viaduct
Picton Junction
Picton – Mittagong
loop line
94.49 Tahmoor
Bargo railway viaduct
102.87 Bargo
109.10 Yanderra
116.31 Yerrinbool
125.60 Aylmerton
Picton – Mittagong
loop line
Mittagong Junction
131.57 Mittagong
Joadja line
Box Vale colliery
136.34 Bowral
138.84 Burradoo
143.00 Bong Bong
Berrima
cement works
Unanderra –
Moss Vale line
145.71 Moss Vale
151.30 Werai
155.88 Exeter
162.26 Bundanoon
169.79 Kareela
171.40 Penrose
177.14 Wingello
185.38 Tallong
Medway Quarry line
192.91 Marulan
205.02 Carrick
208.52 Towrang
216.43 Murrays Flats
222.46 North Goulburn
Crookwell line
224.90 Goulburn
Bombala line
234.90 Yarra
247.90 Breadalbane
256.30 Cullerin
271.02 Fish River
278.60 Gunning
287.90 Oolong
297.70 Jerrawa
309.90 Coolalie
318.01 Yass Junction
Yass Town line
329.30 Bowning
339.90 Goondah
Burrinjuck tramway
Illalong Creek
354.10 Binalong
365.20 Galong
Boorowa line
371.70 Rocky Ponds
380.90 Cunningar
385.40 Harden
388.70 Murrumburrah
391.60 Demondrille
Blayney line
401.64 Nubba
407.20 Wallendbeen
413.10 Morrisons Hill
420.20 Jindalee
Lake Cargelligo
line
429.65 Cootamundra
Tumut line
Mullaly's Siding
services
 
445.13 Frampton
Bethungra Spiral
456.01 Bethungra
468.47 Illabo
477.89 Marinna
Hay line
485.67 Junee
487.91 Junee Racecourse
497.61 Harefield
504.64 Shepherds
513.69 Bomen
Murrumbidgee River
Tumbarumba line
521.40 Wagga Wagga
529.41 Kapooka
535.72 Uranquinty
Kywong line
541.37 Bon Accord
Westby line
550.29 The Rock
Oaklands line
557.58 Kubura
565.09 Yerong Creek
Rand line
580.29 Henty
596.82 Culcairn
Holbrook line
Billabong Creek
Corowa line
616.37 Gerogery
631.10 Table Top
637.26 Ettamogah
642.35 Albury Racecourse
646.24 Albury
Murray River bridge
& Victorian border
North East line
to North Melbourne
This diagram:

The Main Southern Railway is a major railway in New South Wales, Australia. It runs from Sydney to Albury, near the Victorian border. The line passes through the Southern Highlands, Southern Tablelands, South West Slopes and Riverina regions.

Description of route

View map

The Main Southern Railway commences as an electrified pair of tracks in the Sydney metropolitan area. Since 1924, the line branches from the Main Suburban railway line at Lidcombe and runs via Regents Park to Cabramatta, where it rejoins the original route from Granville. The line then heads towards Campbelltown and Macarthur, the current limit of electrification and suburban passenger services. The electrification previously extended to Glenlee Colliery, but this was removed following the cessation of electric haulage of freight trains in the 1990s.

The line continues as a double non-electrified track south through the Southern Highlands towns of Mittagong and Goulburn to Junee on the Southern Plains. Here the line becomes single track for the remainder of its journey south to the state border with Victoria at Albury. The North East railway line then continues through northern Victoria to Melbourne.

There are six tunnels on the line: the Picton tunnel, the Yerrinbool tunnel, the Aylmerton tunnel, the Gib (Mt Gibraltar) tunnel, and the two "up" track tunnels in the Bethungra Spiral.

The line north of Macarthur is maintained by Transport Asset Holding Entity. South of Macarthur the line is leased to the Australian Rail Track Corporation until 2064.

Though the bulk of the line has a maximum gradient of 1.5%, the ruling grade of the line is 2.5% due to short, steep sections of track between Binalong and Harden.

Development of the line

On 26 September 1855, the first railway in New South Wales, the Sydney to Granville railway opened. Exactly a year later, a branch was opened from what was known as Parramatta Junction (the present day Granville) to Liverpool.

Parramatta Junction (Granville) to Liverpool

The Liverpool line extension commenced from Parramatta Junction (now Granville) and was constructed by Mr. W Randle. The turning of the first sod occurring 20 November 1855.

The line was constructed as a single track of 8.5 miles (13.7 km) in length laid with double-headed rails of 75 lb (34 kg) per yard and with fish joints. The total construction cost was placed at £120,040 4s. 11d.

The railway was officially opened 18 August 1856 as a result of the inspection of the line by the Governor General. The press attending the inspection also noted, "the country traverses offers great facilities for railway continuation, being for the most part level and even."

The building of the railway wasn't without incident as on 16 August 1856, a man died as a result of a derailment. The guard on the front of the train noted, "a plank lying across the rails near where was working."

The Parramatta Junction (Granville) – Liverpool line was opened to the public 1 September 1856.

Liverpool to Campbelltown

The Cumberland County was a large producer of agricultural products such as wheat, maize, beef, and wool. This, combined with an approximate 10,000 passengers travelling between Sydney and Campbelltown in 1846, and community support, provided impetus for the construction of a railway line from Sydney to Campbelltown at the earliest possible opportunity.

On 29 October 1856, it was announced that the Great Southern Railway was to be extended from Liverpool to Campbelltown with the stations between Liverpool and Campbelltown yet to be determined although, "every landholder on the line is quite prepared to prove to the satisfaction of the Commissioners that the proper place for a station is on his property."

Owing to financial difficulties, turnover of skilled specialist, and several gold rushes depriving the company of labour, preparations for the construction of a railway reaching Campbelltown didn't commence until 1857 via the issue of a notice from the Commissioner of Railways. In the meantime, the plans and estimates (at approximately £11,500 per mile) for the line were completed and sent to the Colonial Secretary in August 1856. These plans and estimates were considered to be, "in such a state of forwardness, that they may be contracted for at once".

As per the notice, the line was to commence from the south end of Liverpool Railway Station, "and extend thence for twelve miles eight chains, or thereabouts, in a south-westerly direction, through the parishes of Saint Luke, Minto, and Saint Peter, to the Town of Campbelltown, and ending at the south fence of a lane on the property of Charles Morris..." The line was to not exceed a gradient of 1 in 100 and the smallest radius of a curve being 30 chains. The railway is to be, "a single line throughout, laid with the double-headed rail, 75lbs to the yard, on cross sleepers, with chairs, and fish jointed."

On 25 April 1857, the tender for the first four miles of the extension was won by a Mr. W. Randle with the fencing and timber for the extension being awarded to Messrs. Scott and Jolly on 27 April 1857. Scott and Jolly had constructed a large sawmill at Cabramatta and sourced wood (primarily Ironbark) from the nearby forest. This wood was used for the sleepers on the extension.

On 7 May 1857, construction began with, "the first turf of the railway in extension of the great Southern Railway from Liverpool to Campbelltown, was turned (. . .) without any particular ceremony."

Randle, having been able to keep to the scheduled completion date of 1 September, offered to continue the construction of the line through to Campbelltown at the same cost per mile. However, the commissioners, "declined to accept it, having determined to advertise for tenders for each portion separately".

Initially, a Mr. Hall had won the tender for the remaining distance to Campbelltown, but through some arrangement (nefarious or otherwise), Randle had been announced as the winner of the tender. It was also revealed that Randle had won the tender at a higher price than that which Randle had initially offered.

Progress continued to be made for the extension to Campbelltown (plus an extension beyond to Goulburn) and by August 1857, construction of the line had progressed significantly; telegraph poles had been delivered alongside the proposed railway line through Campbelltown in preparation for its construction. These telegraph poles would later form part of the Sydney-Albury telegraph line.

On 29 August 1857, it was reported that the construction of the railway was advancing rapidly and that, "...there are a great many men already at work clearing the most woody portion of the line, about four miles from here, the real track is now easily to be traced by the formidable looking posts erected for the electric telegraph."

Even prior to the opening of the extension, land values surrounding the railway corridor was noted to have increased by 250 percent, and the anticipation of the opening was growing.

On 17 April 1858, a navvy (by the name of "Romilly") working on the construction of the extension was killed when, "a truck of sleepers passing along the rail by mischance overturned upon the unfortunate man. He was picked up senseless, and at once conveyed to the Liverpool Hospital, where it was found that life was quite extinct."

Finally, 29 April 1858 saw the first train arrived within one hundred yards of Campbelltown Railway Station. This train carried the Commissioner of Railways (Captain Ben Martindale), Chief Engineer John Whitton, and staff of the railway office. They then inspected the buildings and subsequently boarded the train to return to Sydney.

The Liverpool – Campbelltown railway line was opened 4 May 1858.

Campbelltown to Menangle

The construction of the railway to Goulburn was always going to extend beyond Campbelltown. But the path for the extensions considered multiple options (including Menangle) while also explicitly excluding a path aligning with the dreaded Razorback road. The survey of multiple options at the time were considered prudent as, "The expense and trouble of such survey of (...) lines would be trifling, as compared with the survey of the Eastern line."

As early as 29 April 1846, the path of the Great Southern Railway was to cross through the parish of Menangle. In January 1852, surveyors were dispatched to commence the first of multiple surveys of a line towards Goulburn with the first section being, "the line running by Menangle, between Campbell Town and Myrtle Creek." Myrtle Creek was the former name of Tahmoor. Another survey was conducted at the direction of Gother K. Mann, Chief Commissioner of Sydney, and Hunter River Railways. Moving traffic from the Southern Road and onto rail was a primary motivator for making the line profitable.

Delays in the survey were causing some frustration within the Legislative Assembly. The Commissioner stated that the extension to Campbelltown and then onto Menangle would, "have intercepted the traffic of the Southern Road, and made the present lines remunerative. The Government would thus have been placed in possession of information that would have fully determined the question of railway extension as applicable to the present wants of the colony."

Despite delays, and even before the government had announced the exact path of the line, anticipation for it could be seen in advertising of property and housing near Menangle. However, there were some rumblings within the community about the priority of the line over other lines such as the one to Windsor, Penrith, and Singleton.

On 16 November 1857, the government projected the cost and constraints for the line to, "not exceed £10,000 per mile; the worst gradient being 1 in 80, and the smallest radius of a curve 40 chains."

Proclamation of the line was made 4 November 1858 and published the following day as, "to make and complete that portion of the Great Southern Railway, commencing near to the Campbelltown Station, in the parish of St Peter, and county of Cumberland, at a point marked A on the proclaimed Plan, and terminating near to the Nepean River, at a point marked B on the proclaimed Plan, in the parish of Menangle, and county of Cumberland, being a distance of five miles and sixty chains."

In April 1859, Peto, Brassey & Betts, represented by their agent, Alexander Rhodes, signed a contract with the government for the extension of a number of lines in the colony, including the line from Campbelltown to Menangle. Rhodes had arrived from England as an agent of Peto, Brassey & Betts for the execution of the contract. This contract was exempt from the rules of public competition as the government felt there was no suitable contractor available to complete the work. The existing contractors were either unreliable, not going to submit a proposal, or unable to complete the contract.

By July 1859, construction "begins to exhibit considerable progress in the cuttings and embankments". And by August 1859, Rhodes had made significant progress on the extensions. Two thirds of the works had been finished with a third of this ready for the laying of the ballast and rails. The progress was characterised as being constructed, "with the energy and admirable system; which have characterised the operations of these eminent contractors in various parts of the world".

On 12 November 1859, the progress of construction was reported to be well advanced with considerable earthworks, wooden bridges, several culverts and under bridges having been completed. The work was described as being, "in a very forward state, and will, if it receives the same amount of labour that has hitherto been bestowed upon it, soon be ready for the permanent way".

However, Rhodes was feeling the pressure of delivery on time. Rhodes criticised the Engineer-in-Chief of withholding rails and expressed, "remonstrances that the timber bridges proposed for the lines would not be sufficiently strong for the traffic they would have to carry." It did not help Rhodes' cause that a number of men working on the project had left to assist with the harvest of nearby farms. But, at the same time, it was noted that brickmaking and other works were continuing in their absence.

By 13 March 1860, the progress of the extension was characterised as, "generally a forward aspect, and, with the exception of the bridge over the Nepean, that portion of the line might be completed within four months."

It was reported in the same month that the earthworks for the laying of the line had been completed for some time. A description of the line was published as, "Starting from Campbelltown, the country being for some distance tolerably level, the line is carried along a low embankment, and for nearly two miles keeps within sight of the road. About three-quarters of a mile beyond Campbelltown, the old Southern Road through Camden and the new one through Menangle unite; the line crosses the former road a few yards beyond its junction with the latter; being slightly above the level of the road, the road has been raised for a level crossing. The formation of the line as far as the Camden road has for a long time been finished, and is ready for the ballasting and permanent way; and temporary rails have been laid down for the convenience of the contractors."

It is at this time, with the line ready for laying, the viaduct crossing the formidable Nepean River was the main obstacle to the completion of the line into Menangle. Flooding from the river had recently destroyed some embankments and carried off some sleepers but no injuries were reports.

South of the Nepean River, the line resumes along a high embankment and passes by, "a cluster of houses known as Riversford, the residents in which are chiefly cultivators of the rich agricultural land through which the line runs for some distance, and which is the property of Messrs. Macarthur."

The government and Rhodes were often arguing over the cost and delays in completing the contract. In March 1860, in a review of the contract for the construction of the line, Rhodes submitted their version to the Legislative Assembly of events leading up to the signing, and execution, of the contract . Rhodes explained the history of the engagement of Peto, Brassey & Betts and of Rhodes' arrival to the colony to execute on the contract. Rhodes then proceeds to list the issues encountered and the concerns expressed to the government in great detail.

By this time, the government had lost faith in Rhodes and had written to Peto, Brassey & Betts to have Rhodes recalled to England. The government also informed Rhodes that Peto, Brassey & Betts would not be considered for any future contracts. It is possible there may have been a personal and/or professional conflict between the Chief Commissioner, Captain Martindale and the Executive Government, and Rhodes. On 20 June 1860, Rhodes subsequently acknowledged this loss of faith by the government.

On 23 October 1861, it was reported that the line is being ballasted in a number of places between Campbelltown and Picton with the permanent way being laid between Campbelltown and Menangle. The work was predicted to be completed well before the contracted time of 1 January 1863.

The completion of the line, except for the viaduct, was nearing, with ongoing ballasting and the laying of the permanent way to be completed. The extension from Campbelltown to within a few metres of the bridge was to be completed within a few days, "but no arrangements are being made for opening the line".

At the northern end of the river, a platform was constructed at a terminus of the line to allow passengers to board and alight from the train. This terminus was only temporary as, "the permanent Menangle Station is to be ready a mile further on the south side of the Nepean."

The extension from Campbelltown to the temporary terminus was opened for traffic on 1 September 1862.

The opening of the line attracted dignitaries from the colony. His Excellency the Governor and Lady Young, plus others accompanied the Minister for Works to the site. The viceregal party arrived at the temporary terminus and Mr Willcox then "showed and explained the works".

The complete opening of the line to Menangle was unexpectedly delayed due to the loss of the ship containing the iron girders for the northern span of the bridge.

Menangle to Douglas Park

On 26 July 1859, the proclamation for the section of the line from Menangle to Douglas park (sometimes referred to as "Douglass Park") was made. This was to be part of the extension of the Great Southern Railway from Campbelltown through to Picton and was to extend the line 6 miles and 42 links (9.5 km) from Menangle.

A small ceremony was held where the first sod for the extensions was at Douglas Park 2 August 1859. It was attended by Peto, Brassey, and Betts, several contractors, and Miss Douglass, the daughter of the Hon G Douglass, M.L.C.

Upon the turning of the sod, "three cheers were then given for the Queen, three for success to railways, and three for the contractors, which, being suitably acknowledged, the company partook of a well-served collation, and left highly pleased with their visit."

By 12 November 1859, progress was reported on as being, "not so forward as on this side " but steadily progressing. Progress continued to be slow through the first half of 1860 due to the need for heavy works at Douglas Park and Spaniards Hill. This slow progress and ongoing disputes between Rhodes and the government was to be the overarching theme of the construction for the year. The nature of the dispute was what was considered shale (included as "earthworks" in the contract), and rock (not included in the contract).

On 1 July 1863, the railway to Douglas Park was opened as part of the opening of the line to Picton.

Douglas Park to Picton

The proclamation for the extension of the railway to Picton was made 9 August 1859.

The completion of the Menangle viaduct, on 1 July 1863, allowed for the opening of the entire line between Campbelltown and Picton. Prior to its opening, on 29 June 1863, his Excellency Sir John Young and Lady Young were accompanied by other colonial dignitaries to visit Picton prior to the opening of the line. The party crossed the viaduct to Picton, had lunch, and returned again across the viaduct to Sydney.

On the day of the opening, a "sumptuous banquet" was put on by Samuel Wilcox Esq. for the men who had been employed on the works. The banquet was situated to the right of the station near the road with a, "marquee, with long tables, and capable of seating three hundred persons, and in an adjacent paddock were congregated the German band and numerous groups of navvies and their friends and spectators."

Picton to Nattai (Mittagong)

On 5 April 1855, a letter to the editor was published in the Sydney Morning Herald that proposed building a railway to the Fitzroy Ironworks and Coal Company in Nattai. It wasn't until 26 July 1862 that tenders to supply for the extension were first invited.

In September 1862, work commenced on the extension. The 30 mile (48 km) extension from Picton to Nattai extension included the need for heavy earthworks, crossing several Nattai River tributaries and requiring, "four or five large viaducts, the longest of which will be about three hundred feet in length."

Many issues relating to the contractors resulted in multiple delays to construction. However, upon resolution, work progressed steadily. It was noted that, "it is felt, however, that any more than ordinary energy of action would tend to raise labour rates, and this, the process at which contracts have been taken, will not admit of."

By 24 February 1864, positive progress was being reported with the bridge piers and abutments at Stonequarry Creek completed. Progress was expected to be, "pushed on more rapidly upon the completion of four steam cranes, two locomotives, and other machinery, which are being made for the contractors and the use of which will greatly facilitate the execution of the works." Subsequently, steady progress was reported for the remainder of 1864 and 1865 and by November 1865, rails were being delivered to Picton for laying on the freshly ballasted permanent way. However, the final section to the Fitzroy Ironworks required heavy earthworks, "the execution of which will delay for many months the opening of the railway to Mittagong."

With construction nearing completion, a journalist, Mr. Waverley, from the Sydney Morning Herald visited the extension describing the journey from Picton to Nattai as passing through several cuttings, embankments, and crossing the Great Southern Road near the Industrial School. At this time, the proposed station at Mittagong had not yet been built.

On 22 February 1867, the official opening of the extension was announced by the Commissioner for Railways. It was to take place on 28 February 1867 and then, "be opened for public traffic on the first (1st) proximo ."

The opening of the extension was reported as, "so important to the welfare of the district could not be permitted to transpire without attracting to the scene the inhabitants of Mittagong, Bong Bong, Wingecarribee, and Sutton Forest."

A special train, arranged for the occasion, left the Redfern Terminus at 10am and arrived at Mittagong at 1:30pm. Upon arrival, guests and dignitaries were served lunch in marquees plus a separate, grander marquee, "In which two hundred navvies with many of their wives and families, were being treated to a sumptuous and substantial dinner of roast beef plum pudding, and English ale."

The Picton – Mittagong railway line was opened for public traffic 1 March 1867.

Continued extensions

This line was extended to Goulburn in 1869, Yass Junction in 1876, Galong, Harden-Murrumburrah and Cootamundra in 1877 and Junee and Bomen (on the north bank of the Murrumbidgee River) in 1878. The Murrumbidgee River Railway Bridge was completed in 1881 and the line was extended to Wagga Wagga, Uranquinty, The Rock, Henty and Albury in 1881. Victorian Railways' North East 1,600 mm (5 ft 3 in) gauge line was extended from Wodonga to Albury in 1883. To accommodate the break of gauge, a very long railway platform was built, the covered platform being one of the longest in Australia.

The original alignment was built under the supervision of John Whitton, Engineer-in-Charge of the New South Wales Government Railways from 1856 to 1898.

The two main sections of the line that were deviated; the Old Main South line (in blue) and the Picton - Mittagong Loop line (in purple)

The original single track was duplicated from Granville to Liverpool in 1857, to Campbelltown in 1891, to Picton in 1892. Between 1913 and 1922 the 343 km (213 mi) section from Picton to Cootamundra was duplicated. At the same time, the section between Picton and Mittagong was deviated by a less direct route in 1919 to ease the steep grades of the original alignment, and the old line became known as the Picton – Mittagong loop railway line which is now largely closed. (The Main Southern Railway Deviation, was estimated in the 1914 Act of Parliament to have construction costs of £630,353). Other sections of the original Whitton alignment between Goulburn and Wagga Wagga were also replaced by more curvy sections with lower grades. The section between Granville and Cabramatta via Fairfield was bypassed with a more direct route from Lidcombe via Regents Park in 1924. The former route through Fairfield became known as the Old Main South. The section from Cootamundra to Junee, including a rail spiral at Bethungra, was duplicated between 1941 and 1945.

Construction of a standard gauge track parallel with the broad gauge track from Albury to Melbourne commenced in 1959, completing the Sydney-Melbourne railway. The first freight train operated on the line on 3 January 1962, followed by the first passenger train on 16 April 1962.

The original wrought iron Murrumbidgee River Railway Bridge at Wagga Wagga was replaced in 2007 by a new concrete and steel bridge.

The main line south of Junee was substantially upgraded in 2007 and 2008, including the construction of passing loops up to 7 km (4.3 mi).

Redbank Tunnel near Tahmoor closed on 30 November 2012 when replaced by a deviation funded by Xstrata to allow expansion of its Tahmoor Colliery under the tunnel which was sealed.

In January 2013, the Australian Rail Track Corporation opened the Southern Sydney Freight Line between Sefton and Macarthur as a dedicated line for freight services.

Branches

The Rock station
Cootamundra station

Several lines branched from the Main South, some of which are closed either fully or in part:

Passenger services

Commuter services

Sydney Trains operates electric commuter passenger trains between Sydney and Macarthur. The section between Macarthur and Glenfield is operated as part of the T8 Airport & South Line, the section between Glenfield and Granville along the Old Main South line is operated as part of the T2 Leppington & Inner West Line, and the section between Liverpool and Lidcombe via Regents Park is operated as part of the T3 Liverpool & Inner West Line.

NSW TrainLink diesel railcars operate south from Campbelltown to Goulburn on an irregular frequency as part of the Southern Highlands Line.

Country services

Prior to 1962, travelling south of Albury into Victoria required a change of trains (due to gauge differences between NSW and Victoria) and often an overnight stay. From March 1956, a daylight connection was introduced between Sydney and Melbourne whereby a train from Sydney connected at Albury with a train to Melbourne and vice versa. In 1962, an additional Standard Gauge track was built from Albury to Melbourne alongside the existing Broad Gauge line, allowing through operation of trains between Sydney and Melbourne. Between April 1962 and August 1991, the Main South was served by the Intercapital Daylight, a locomotive hauled limited stop passenger train. It was operated jointly by the New South Wales Government Railways and the Victorian Railways with the former's air-conditioned rolling stock. Two overnight services also ran, the limited stops Southern Aurora and the Spirit of Progress. Until 1982, locomotives were exchanged at Albury for a locomotive of the respective state that the train was entering.

The South Mail operated overnight between Sydney and Albury until it ceased in June 1985. In August 1986, the Southern Aurora and the Spirit of Progress were merged into the Sydney/Melbourne Express. In August 1991, airline deregulation and falling patronage saw the Intercapital Daylight replaced by a coach service between Melbourne and Albury, connecting with the Riverina XPT at Albury. In November 1993 the delivery of additional XPT rollingstock saw the introduction of a through overnight XPT service between Sydney and Melbourne, replacing the Sydney/Melbourne Express, and the Riverina XPT extended to Melbourne from December 1994.

In 2013, with the upgrading of the East Hills line, regional trains heading southwest to Canberra, Griffith and Melbourne from Sydney Central began to use that line to travel through metropolitan Sydney, instead of the Main Southern line through Strathfield railway station.

As at October 2019, NSW TrainLink services operated on the Main South line were:

  • Sydney to Canberra – 3 in each direction per day
  • Sydney to Griffith – 2 in each direction per week
  • Sydney to Melbourne – 2 in each direction per day

References

  1. "Picton Tunnel". www.nswrail.net. Retrieved 9 February 2021.
  2. "Yerrinbool Tunnel". www.nswrail.net. Retrieved 9 February 2021.
  3. "Aylmerton Tunnel". www.nswrail.net. Retrieved 9 February 2021.
  4. "The Gib Tunnel". www.nswrail.net. Retrieved 9 February 2021.
  5. Memorandum between The Commonwealth of Australia & The State of New South Wales & Australian Rail Track Corporation Limited Archived 11 April 2013 at the Wayback Machine Australian Rail Track Corporation
  6. The Agreement in Summary Australian Rail Track Corporation
  7. NSW Curve and Gradient Diagram Main South Australian Rail Track Corporation
  8. "Sydney Correspondence". Illawarra Mercury. 25 August 1856. Retrieved 23 February 2023.
  9. "OPENING OF THE RAILWAY TO LIVERPOOL". Empire. 2 September 1856. Retrieved 23 February 2023.
  10. "PARLIAMENTARY PAPER". Empire. 16 November 1857. Retrieved 23 February 2023.
  11. "OPENING OF THE LIVERPOOL RAILWAY". Sydney Morning Herald. 2 September 1856. Retrieved 23 February 2023.
  12. "Colonial Intelligence". Goulburn Herald and County of Argyle Advertiser. 23 August 1856. Retrieved 23 February 2023.
  13. "FRIDAY". Maitland Mercury and Hunter River General Advertiser. 21 August 1856. Retrieved 23 February 2023.
  14. "OPENING OF THE LIVERPOOL RAILWAY LINE". People's Advocate and New South Wales Vindicator. 6 September 1856. Retrieved 23 February 2023.
  15. "Advertising". Sydney Morning Herald. 31 October 1848. Retrieved 1 January 2023.
  16. "To the Editors of Bell's Life". Bell's Life in Sydney and Sporting Reviewer. 25 November 1848. Retrieved 1 January 2023.
  17. "THE INTENDED RAILWAY". Sydney Morning Herald. 21 March 1849. Retrieved 1 January 2023.
  18. "Railway from Liverpool to Campbelltown. Notice". New South Wales Government Gazette. 1 May 1857. p. 1016. Retrieved 26 December 2021.
  19. "Campbelltown Railway". The Goulburn Herald. 8 May 1858. p. 2. Retrieved 26 December 2021.
  20. "Campbelltown Railway". The Sydney Morning Herald. 5 May 1858. p. 5. Retrieved 26 December 2021.
  21. ^ "RAILWAY DEPARTMENT". New South Wales Government Gazette. 1 May 1857. Retrieved 1 January 2023.
  22. "LEGISLATIVE ASSEMBLY". Sydney Morning Herald. 7 March 1857. Retrieved 1 January 2023.
  23. "OUR RAILWAY". Shipping Gazette and Sydney General Trade List. 9 March 1857. Retrieved 1 January 2023.
  24. ^ "PARLIAMENTARY PAPER". Empire. 16 November 1857. Retrieved 1 January 2023.
  25. "PUBLIC WORKS AND CITY IMPROVEMENTS". Sydney Morning Herald. 15 May 1857. Retrieved 1 January 2023.
  26. "No title". Sydney Morning Herald. 25 April 1857. Retrieved 1 January 2023.
  27. "No title". Sydney Morning Herald. 27 April 1857. Retrieved 1 January 2023.
  28. "COLONIAL INDUSTRY". Sydney Morning Herald. 10 October 1857. Retrieved 1 January 2023.
  29. "SYDNEY NEWS". Maitland Mercury and Hunter River General Advertiser. 12 May 1857. Retrieved 1 January 2023.
  30. "STOCK, SALE YARDS, AT LIVERPOOL". Empire. 1 July 1857. Retrieved 1 January 2023.
  31. "PARLIAMENT OF NEW SOUTH WALES. LEGISLATIVE ASSEMBLY. FRIDAY, AUGUST 14. THE SPEAKER took the chair at a quarter-past three o'clock. MESSAGE FROM THE GOVERNOR". Sydney Morning Herald. 15 August 1857. Retrieved 1 January 2023.
  32. "THE PAST YEAR". Illawarra Mercury. 5 January 1857. Retrieved 1 January 2023.
  33. "PARLIAMENTARY PAPER". Empire. 16 April 1857. Retrieved 1 January 2023.
  34. "CAMPBELLTOWN". Sydney Morning Herald. 18 August 1857. Retrieved 1 January 2023.
  35. "ELECTRIC TELEGRAPH". Empire. 5 December 1859. Retrieved 1 January 2023.
  36. "No title". Sydney Morning Herald. 1 September 1857. Retrieved 1 January 2023.
  37. "WAYS AND MEANS". Empire. 8 April 1858. Retrieved 1 January 2023.
  38. "CAMPBELLTOWN". Empire. 13 March 1858. Retrieved 1 January 2023.
  39. "CAMPBELLTOWN". Sydney Morning Herald. 18 March 1858. Retrieved 1 January 2023.
  40. "COMMERCIAL RECORD". Empire. 19 April 1858. Retrieved 1 January 2023.
  41. Abbott, G.J. (1974). "Ben Hay Martindale (1824–1904)". Australian Dictionary of Biography. Vol. 5. Canberra: National Centre of Biography, Australian National University. ISBN 978-0-522-84459-7. ISSN 1833-7538. OCLC 70677943. Retrieved 22 October 2024.
  42. "CAMPBELLTOWN". Sydney Morning Herald. 1 May 1858. Retrieved 1 January 2023.
  43. "CAMPBELLTOWN RAILWAY". Sydney Morning Herald. 5 May 1858. Retrieved 1 January 2023.
  44. "Advertising". Sydney Morning Herald. 29 April 1846. Retrieved 10 April 2023.
  45. "THE GREAT SOUTHERN AND WESTERN RAILWAY". Sydney Morning Herald. 7 May 1846. Retrieved 10 April 2023.
  46. "ORIGINAL CORRESPONDENCE". Sydney Morning Herald. 31 January 1851. Retrieved 10 April 2023.
  47. "Sydney Railway Company—Half-Yearly Meeting". Empire. 7 January 1852. Retrieved 10 April 2023.
  48. "Railways". Sydney Morning Herald. 20 June 1856. Retrieved 10 April 2023.
  49. "The Sydney Morning Herald". 23 April 1857. Retrieved 10 April 2023.
  50. "LEGISLATIVE ASSEMBLY". Sydney Morning Herald. 7 March 1857. Retrieved 10 April 2023.
  51. "Advertising". Sydney Morning Herald. 25 July 1857. Retrieved 10 April 2023.
  52. "WINDSOR". Sydney Morning Herald. 1 September 1857. Retrieved 10 April 2023.
  53. "Mr Darvall and the Windsor Railway". Empire. 8 September 1857. Retrieved 10 April 2023.
  54. "PARLIAMENTARY PAPER". Empire. 16 November 1857. Retrieved 10 April 2023.
  55. "GREAT SOUTHERN RAILWAY". New South Wales Government Gazette. 5 November 1858. Retrieved 10 April 2023.
  56. ^ "PARLIAMENTARY PAPER". Sydney Morning Herald. 25 April 1860. Retrieved 10 April 2023.
  57. "RAILWAYS". Sydney Morning Herald. 13 July 1859. Retrieved 10 April 2023.
  58. "RAILWAYS AND COUNTRY WORKS". Sydney Morning Herald. 13 August 1859. Retrieved 10 April 2023.
  59. "RAILWAYS AND COUNTRY WORKS". Maitland Mercury and Hunter River General Advertiser. 20 August 1859. Retrieved 10 April 2023.
  60. "RAILWAYS". Sydney Morning Herald. 12 November 1859. Retrieved 10 April 2023.
  61. ^ "RAILWAYS". Sydney Morning Herald. 13 December 1859. Retrieved 10 April 2023.
  62. "RAILWAYS". Sydney Morning Herald. 13 March 1860. Retrieved 10 April 2023.
  63. ^ "THE SOUTHERN RAILWAY EXTENSION". Goulburn Herald. 17 March 1860. Retrieved 10 April 2023.
  64. "Parliamentary Intelligence". Empire. 2 May 1860. Retrieved 10 April 2023.
  65. "CAPTAIN MARTINDALE AND THE EXECUTIVE GOVERNMENT VERSUS MR. RHODES". Empire. 26 June 1860. Retrieved 10 April 2023.
  66. "LEGISLATIVE ASSEMBLY". Sydney Morning Herald. 4 July 1860. Retrieved 10 April 2023.
  67. "To the Editor of the Herald". Sydney Morning Herald. 23 June 1860. Retrieved 10 April 2023.
  68. "LOCAL AND PROVINCIAL". Goulburn Herald. 23 October 1861. Retrieved 10 April 2023.
  69. "RAILWAYS". Sydney Morning Herald. 21 July 1862. Retrieved 10 April 2023.
  70. "Local and General Intelligence". Yass Courier. 30 August 1862. Retrieved 10 April 2023.
  71. "Local and General Intelligence". Yass Courier. 30 August 1862. Retrieved 10 April 2023.
  72. "TOWN AND COUNTRY NEWS". Sydney Mail. 13 September 1862. Retrieved 10 April 2023.
  73. "PROGRESS OF RAILWAYS IN THE COLONY". Maitland Mercury and Hunter River General Advertiser. 25 October 1862. Retrieved 10 April 2023.
  74. "GREAT SOUTHERN RAILWAY". New South Wales Government Gazette. 26 July 1859. Retrieved 13 August 2023.
  75. "PARLIAMENTARY PAPER". Sydney Morning Herald. 5 December 1859. Retrieved 13 August 2023.
  76. "STATISTICS OF CUSTOMS". Sydney Morning Herald. 4 August 1859. Retrieved 13 August 2023.
  77. "RAILWAYS". Sydney Morning Herald. 12 November 1859. Retrieved 13 August 2023.
  78. "Parliamentary Intelligence". Empire. 12 May 1860. Retrieved 13 August 2023.
  79. "PUBLIC WORKS". Empire. 13 June 1860. Retrieved 13 August 2023.
  80. "COLONIAL PARLIAMENT". Sydney Morning Herald. 17 October 1860. Retrieved 8 February 2024.
  81. "Parliamentary Intelligence". Empire. 2 May 1860. Retrieved 13 August 2023.
  82. "OPENING OF THE RAILWAY TO PICTON". Sydney Morning Herald. 21 July 1863. Retrieved 13 August 2023.
  83. "GREAT SOUTHERN RAILWAY". New South Wales Government Gazette. 9 August 1859. Retrieved 8 February 2024.
  84. "PICTON". Empire. 3 July 1863. Retrieved 10 April 2023.
  85. "RAILWAY PAPERS". Sydney Morning Herald. 5 April 1855. Retrieved 11 February 2024.
  86. "Advertising". Sydney Morning Herald. 26 July 1862. Retrieved 11 February 2024.
  87. "RAILWAYS". Sydney Morning Herald. 21 October 1862. Retrieved 11 February 2024.
  88. "PROGRESS OF RAILWAYS IN THE COLONY". Maitland Mercury and Hunter River General Advertiser. 25 October 1862. Retrieved 11 February 2024.
  89. "ADELAIDE". Sydney Morning Herald. 26 February 1863. Retrieved 11 February 2024.
  90. "RAILWAYS". Sydney Morning Herald. 21 March 1863. Retrieved 11 February 2024.
  91. "RAILWAYS". Sydney Morning Herald. 21 April 1863. Retrieved 11 February 2024.
  92. "No title". Sydney Morning Herald. 6 November 1863. Retrieved 11 February 2024.
  93. "PUBLIC AND PRIVATE WORKS, AND IMPROVEMENTS". Empire. 23 June 1863. Retrieved 11 February 2024.
  94. ^ "LOCAL AND PROVINCIAL". Goulburn Herald. 24 February 1864. Retrieved 11 February 2024.
  95. "RAILWAYS". Sydney Mail. 22 April 1865. Retrieved 12 February 2024.
  96. "RAILWAYS". Sydney Morning Herald. 21 October 1865. Retrieved 12 February 2024.
  97. "RAILWAYS". Sydney Morning Herald. 21 November 1865. Retrieved 12 February 2024.
  98. "RAILWAYS". Sydney Mail. 25 February 1865. Retrieved 12 February 2024.
  99. "A TRIP TO THE HIGHLANDS". Sydney Morning Herald. 13 June 1866. Retrieved 12 February 2024.
  100. "Advertising". Sydney Morning Herald. 23 February 1867. Retrieved 12 February 2024.
  101. "THE OFFICIAL OPENING OF THE GREAT SOUTHERN RAILWAY FROM PICTON TO NATTAI". Empire. 1 March 1867. Retrieved 12 February 2024.
  102. "The Sydney Morning Herald". 1 March 1867. Retrieved 12 February 2024.
  103. "GREAT SOUTHERN RAILWAY—OPENING OF EXTENSION TO NATTAI". Sydney Mail. 2 March 1867. Retrieved 12 February 2024.
  104. "GREAT SOUTHERN RAILWAY". Maitland Mercury and Hunter River General Advertiser. 5 March 1867. Retrieved 12 February 2024.
  105. "Murrumbidgee River Rail Bridge, Wagga Wagga, NSW (Place ID 15910)". Australian Heritage Database. Australian Government. Retrieved 30 January 2007.
  106. "Albury Railway Precinct". Department of Environment and Heritage.
  107. "Main South Line". www.nswrail.net. Retrieved 16 April 2008.
  108. T. Richards (1883). The Union of the railway systems of New South Wales and Victoria : celebration at Albury on the 14th June, 1883. New South Wales Government.
  109. Singleton, C.C (1976). "John Whitton (1820–1898)". Australian Dictionary of Biography. Vol. 6. Canberra: National Centre of Biography, Australian National University. ISBN 978-0-522-84459-7. ISSN 1833-7538. OCLC 70677943. Retrieved 22 October 2024.
  110. "Liverpool Railway Precinct". Department of Environment and Heritage.
  111. "Campbelltown Railway Precinct". Department of Environment and Heritage.
  112. "Picton Railway Precinct". Department of Environment and Heritage.
  113. "Goulburn Viaduct (Mulwaree Ponds)". Heritage Council of New South Wales.
  114. Main Southern Railway Deviation – Picton to Mittagong Act 1899 (NSW)
  115. "Picton Railway Precinct". Department of Environment and Heritage.
  116. "Bethungra Spiral". Heritage Council of New South Wales.
  117. ^ "VR timeline". Victorian Railways. Mark Bau. Archived from the original on 30 May 2008. Retrieved 8 April 2008.
  118. "Wagga Wagga" (PDF). Railway Lattice Bridge and Viaducts. Institution of Engineers. Archived from the original (PDF) on 15 June 2005. Retrieved 30 January 2007.
  119. "Iron Lattice Girder Railway Bridges" (PDF). Endangered Places. National Trust of Australia. Archived from the original (PDF) on 8 October 2006. Retrieved 30 January 2007.
  120. "Main rail line to get better passing loops". Border Mail. 10 June 2007.
  121. "Rail tunnel will soon be history". Wollondilly Advertiser. 15 January 2013.
  122. "Signaling & Infrastructure" Railway Digest February 2013 page 51
  123. "Bombala Line". www.nswrail.net. Retrieved 11 December 2006.
  124. "Canberra Branch". www.nswrail.net. Retrieved 11 December 2006.
  125. "Captains Flat Branch". www.nswrail.net. Retrieved 11 December 2006.
  126. "Crookwell Branch". www.nswrail.net. Retrieved 11 December 2006.
  127. "Taralga Branch". www.nswrail.net. Retrieved 11 December 2006.
  128. "Yass Branch". www.nswrail.net. Retrieved 12 December 2006.
  129. "Goondah–Burrinjuck Line". www.nswrail.net. Retrieved 12 December 2006.
  130. "Boorowa Branch". www.nswrail.net. Retrieved 11 December 2006.
  131. "Vale Boorowa" Railway Digest December 1987 page 392
  132. Date, Ken; Dominik Giemza (December 2006). "Southern Semaphore Swansong". Railway Digest. 44 (12). Australian Railway Historical Society NSW Div.
  133. "Blayney – Demondrille Line". www.nswrail.net. Retrieved 11 December 2006.
  134. "Grenfell Branch". www.nswrail.net. Retrieved 11 December 2006.
  135. "Eugowra Branch". www.nswrail.net. Retrieved 11 December 2006.
  136. "Lake Cargelligo Branch". www.nswrail.net. Retrieved 11 December 2006.
  137. "Lost Railways: Potts Hill Branch Line". www.visitsydneyaustralia.com.au. Retrieved 16 April 2020.
  138. "Stockinbingal – Parkes Line". www.nswrail.net. Retrieved 11 December 2006.
  139. "Temora – Roto Line". www.nswrail.net. Retrieved 11 December 2006.
  140. "Rankins Springs Branch". www.nswrail.net. Retrieved 11 December 2006.
  141. "Tumut Branch". www.nswrail.net. Retrieved 11 December 2006.
  142. "Kunama Branch". www.nswrail.net. Retrieved 11 December 2006.
  143. "Hay Branch". www.nswrail.net. Retrieved 11 December 2006.
  144. "Tocumwal Branch". www.nswrail.net. Retrieved 11 December 2006.
  145. "Yanco – Griffith Line". www.nswrail.net. Retrieved 11 December 2006.
  146. "Tumbarumba Branch". www.nswrail.net. Retrieved 11 December 2006.
  147. "Kywong Branch". www.nswrail.net. Retrieved 11 December 2006.
  148. "Oaklands Branch". www.nswrail.net. Retrieved 11 December 2006.
  149. "Westby Branch". www.nswrail.net. Retrieved 11 December 2006.
  150. "Rand Branch". www.nswrail.net. Retrieved 11 December 2006.
  151. "Holbrook Branch". www.nswrail.net. Retrieved 11 December 2006.
  152. "Corowa Branch". www.nswrail.net. Retrieved 11 December 2006.
  153. Banger, C. The Intercapital Daylight, 1956–1991 Australian Railway Historical Society Bulletin June 2001
  154. Goulburn Post, "Times are a changing", 24 May 2013
  155. "Southern timetable". NSW TrainLink. 7 September 2019.
New South Wales Railway lines in New South Wales
Main lines
Country branch lines
Operational
Closed
Sydney lines
Commuter rail
Goods lines
Rapid transit
Converted lines
Closed
Proposed or under construction
Tourist & heritage railways
Categories: