Rajasthan Atomic Power Station | |
---|---|
Country | India |
Coordinates | 24°52′20″N 75°36′50″E / 24.87222°N 75.61389°E / 24.87222; 75.61389 |
Status | Operational |
Construction began | 1963 |
Commission date | 16 December 1973 |
Operator | Nuclear Power Corporation of India Ltd (NPCIL) |
Nuclear power station | |
Reactors | 8 |
Reactor type | Units 1 & 2: CANDU Units 3 to 6: IPHWR-220 Units 7 & 8: IPHWR-700 |
Reactor supplier | Units 1 & 2: AECL Units 3 to 8: NPCIL |
Cooling source | Rana Pratap Sagar Dam, Chambal River |
Power generation | |
Units operational | 1 x 200 MW 4 x 220 MW |
Units under const. | 2 x 700 MW |
Units decommissioned | 1 x 100 MW |
Nameplate capacity | 1080 MW |
Capacity factor | 78.07% (2020-21) |
Annual net output | 7386 GW.h (2020-21) |
External links | |
Website | Nuclear power Corporation of India Ltd |
Commons | Related media on Commons |
[edit on Wikidata] |
The Rajasthan Atomic Power Station (RAPS; also Rajasthan Atomic Power Project - RAPP) is a nuclear power plant located at Rawatbhata in the state of Rajasthan, India. It is the fourth largest nuclear power plant in the country after the Kudankulam Nuclear Power Plant, Kakrapar Atomic Power Station, and Tarapur Atomic Power Station interms of installed capacity.
History
The construction of the Douglas Point Nuclear Generating Station Canada began in 1961 with a CANDU (Canada Deuterium Uranium) pressurised heavy water reactor (PHWR) capable of producing 220 MW of electricity. Two years after the construction of the Rajasthan Atomic Power Project (RAPP) commenced, two similar reactors were built in the state of Rajasthan. Ten years later, in 1973 RAPS-1 was put into service. In 1974 after India conducted Smiling Buddha, its first nuclear weapons test Canada stopped its support of the project, delaying the commissioning of RAPS-2 until 1981.
In the context of the Indian atomic program, two more PHWR with an output of 220 MW each were built. They cost around 570 million dollars. RAPS-3 became critical on 24 December 1999, RAPS-4 became critical on 3 November 2000. Commercial operations began on 1 June 2000 for unit 3, and on 23 December 2000 for unit 4.
Two more reactors (RAPS-5 and RAPS-6) with 220 MWe have also been built, with unit 5 beginning commercial operation on 4 February 2010, and unit 6 on 31 March 2010.
Two of the new Indian-designed 700 MWe series of the reactor (RAPP-7 and RAPP-8) are under construction in Rajasthan.
In November 2012, the International Atomic Energy Agency (IAEA) intensively audited over several weeks two reactors at the Rajasthan Atomic Power Station for safety. It has been concluded that the reactors are among the best in the world, the indigenously made 220 MW atomic plants can withstand a Fukushima type of accident, even suggesting that the "safety culture is strong in India" and that India emerged a winner with a high global safety rank.
First concrete for unit 7 was poured on 18 July 2011, with commercial operation expected by 2016. Unit 7 and unit 8 will cost together an estimated Rs 123.2 billion (US$2.6 billion).
In 2024 the AERB granted permission for unit 7 fuel loading and addition of moderator. The 19 September 2024, unit 7 started a controlled fission chain reaction.
Incidents
By 2003 RAPS-1 had experienced numerous problems due to leaks, cracks in the end-shield and turbine blade failures, had undergone repairs and appeared to be generating 100 MW of electricity, with RAPS-2 reportedly generating 200 MW.
On 29 August 2006, a 90% iron meteorite weighing 6.8 kilograms (15 lb) fell in Kanvarpura village, near the power station. The Deputy Director-General (western region) of the Geological Survey of India, R.S. Goyal, said that devastation on an "unimaginable scale" would have ensued had the object struck the station. However, the kinetic energy of a meteorite of this size is smaller than that of jet aircraft frequently used as a basis for impact resistance of containment structures.
In June 2012, 38 workers were exposed to tritium when a welding operation went wrong inside the protected environment of the reactor.
Units
Phase | Unit No. |
Reactor | Status | Capacity in MWe | Construction start | First criticality | Grid Connection | Commercial operation | Closure | Notes | ||
---|---|---|---|---|---|---|---|---|---|---|---|---|
Type | Model | Net | Gross | |||||||||
I | 1 | PHWR | CANDU | Shut Down-pending decommissioning | 90 | 100 | 1 August 1965 | 11 August 1972 | 30 November 1972 | 16 December 1973 | 9 October 2004 | |
2 | PHWR | CANDU | Operational | 187 | 200 | 1 April 1968 | 8 October 1980 | 1 November 1980 | 1 April 1981 | — | ||
II | 3 | PHWR | IPHWR-220 | Operational | 202 | 220 | 1 February 1990 | 24 December 1999 | 10 March 2000 | 1 June 2000 | — | |
4 | PHWR | IPHWR-220 | Operational | 202 | 220 | 1 October 1990 | 3 November 2000 | 17 November 2000 | 23 December 2000 | — | ||
III | 5 | PHWR | IPHWR-220 | Operational | 202 | 220 | 18 September 2002 | 24 November 2009 | 22 December 2009 | 4 February 2010 | — | |
6 | PHWR | IPHWR-220 | Operational | 202 | 220 | 20 January 2003 | 23 January 2010 | 28 March 2010 | 31 March 2010 | — | ||
IV | 7 | PHWR | IPHWR-700 | Critical | 630 | 700 | 18 July 2011 | 19 September 2024 | — | — | — | |
8 | PHWR | IPHWR-700 | Under Construction | 630 | 700 | 30 September 2011 | — | — | — | — |
Current status
Unit 1 was placed under permanent shutdown and is to be decommissioned. Unit 2 to 6 are currently operational. The AERB has give permission to add moderator, fuel and start chain reaction in unit 7 recently. It is expected to come online by the year end. Unit 8 is expected to come online next year. These two are IPHWR-700 reactor. Unit 7 achieved criticality on 19 September 2024. It is expected to come online for commercial operation by the end of the year.
See also
References
- ^ "Monthly Genration Reports Actual for Apr-2021 : Central Sector Nuclear" (PDF). National Power Portal. Central Electricity Authority. Retrieved 10 October 2021.
- ^ "Rajasthan Atomic Power Station (RAPS)". Nuclear Threat Initiative. 1 September 2003. Retrieved 18 February 2017.
- "Rajasthan Atomic Power Station (RAPS)". Plants Under Operation. Nuclear Power Corporation of India Limited (NPCIL). Archived from the original on 16 July 2011. Retrieved 18 July 2011.
- Bagla, Pallava (15 November 2012). "UN's nuclear watchdog: Rajasthan reactors are among world's safest". NDTV.com.
- "India begins construction of 25th nuclear plant". The Hindu. 18 July 2011. Retrieved 18 July 2011.
- "Construction starts on new Rajasthan units". World Nuclear News. World Nuclear Association (WNA). 18 July 2011. Retrieved 18 July 2011.
- "Rajasthan Atomic Power Project-7 goes critical, to start power generation this year". ETEnergyworld.com. 20 September 2024. Archived from the original on 21 September 2024. Retrieved 21 September 2024.
- Meteorite fall in Rajasthan village The Hindu, 6 September 2006.
- Jiang, Hua; Chorzepa, Mi G. (1 November 2014). "Aircraft impact analysis of nuclear safety-related concrete structures: A review". Engineering Failure Analysis. 46: 118–133. doi:10.1016/j.engfailanal.2014.08.008.
- Allain, Rhett (1 March 2013). "How Fast Would a Small Meteor Travel?". Wired.
- Bagla, Pallava (30 June 2012). Bhatt, Abhinav (ed.). "Radiation scare in Rajasthan, workers exposed". NDTV.com.
- "Rajasthan Atomic Power Station". NPCIL. Retrieved 13 February 2020.
- "RAPS-2". PRIS. Retrieved 13 February 2020.
- "RAPS-3". PRIS. Retrieved 13 February 2020.
- "RAPS-4". PRIS. Retrieved 13 February 2020.
- "RAPS-5". PRIS. Retrieved 13 February 2020.
- "RAPS-6". PRIS. Retrieved 13 February 2020.
- ^ "Kakrapar 3 achieves first criticality : New Nuclear - World Nuclear News".
- "Indian government takes steps to get nuclear back on track - World Nuclear News". world-nuclear-news.org. Retrieved 28 March 2019.
- "RAPS-7". PRIS. Retrieved 13 February 2020.
- "RAPS-8". PRIS. Retrieved 13 February 2020.
External links
- Juggernaut, a 1968 Canadian documentary on the delivery of the plant's calandria.