Urban Extension Road-II (UER II) or NH-344M is an upcoming 75.7 km long, 6 lanes (main expressway) & 6 lanes (service roads) wide grade separated expressway in Delhi NCR, India. It would start from National Highway 44 at Alipur then passes from Rohini, Mundka, Najafgarh, Dwarka and end at Delhi–Gurgaon Expressway on National Highway 48 near Mahipalpur. Its main route forms a semicircle on the western side of Delhi, additionally it has two side spurs - one from Bawana in Northwest Delhi to Sonipat in Bawana's North and second in west Delhi from between Tikri border & Najafgarh to NH9 Bahadurgarh south bypass. Delhi NCT has 4 concentric ring roads around it - namely Inner Ring Road; Outer Ring Road; third ring outside it formed by the combination of UER-II & Chilla-Okhla Expressway, and fourth ring formed by the combination of part of Dwarka Expressway (from Tikampur) & Gurugaon-Ghata Expressway, Gurgaon-Sohna Elevated Corridor Expressway, Sohna-Faridabad section of Delhi–Mumbai Expressway, Faridabad–Noida–Ghaziabad Expressway (FNG), Ghaziabad-Narela Expressway (planned) and Rai-Narela-Bahadurgarh-Gurgaon Expressway (meet Dwarka Expressway at Tikampur in Gurugaon). Outside these ring roads, NCR region will have 3 Regional Circular Expressways (first of which is the existing combination of WPE and EPE) and 3 Zonal Circular Expressways (ZCE).
The project also features two 4 lane spurs
- NH-344P to Bahadurgarh Bypass
- NH-344P to Barwasni Bypass
History
In the year 2000, DDA's NCR Transport Plan 2021 conceived the UER-II project, which did not materialize due to financial viability and land procurement problems. In 2018, NHAI took over the implementation of UER-II phase-1 on payment of INR4000 crore financial viability gap funding by DDA, while DDA itself simultaneously undertook the construction of phase-2.
Route
The access-controlled UER-II expressway project phase 1 & 2 have a main 74.98 km long 6-lane semi-circular route on western side of Delhi NCT, with two additional spurs - the 29.6 km long 4-lane Bawana-Sonipat spur in northwest and second 7.3 km long 6-lane Najafgarh-Bahadurgarh spur in west. UER-II is an at grade expressway with elevated flyovers at intersections.
- Main route:
- Phase-1: 75.7 km - covers northwest quadrant from NH44 Alipur to NH48 IGI Airport Shiv Murti:
- Spurs: both are part of phase-1.
- Najafgarh-Bahadurgarh spur: from UER north of Najafgarh to its northwest to 9 Bahadurgarh south bypass.
- Phase-2 - covers southwest quadrant:
- Rangpuri Bypass Expressway: 6-lane expressway from Shiv Murti to Nelson Mandela Marg in Vasant Kunj with interchanges at Andheria Mor and NH148A Anuvrat Marg-Mehraul intersection, then Mehrauli to Badarpur at NH19.
- Rangpuri-Mahrauli-Badarpur Expressway: 6-lane expressway from Rangpuri Bypass, via Saket-Mehrauli-Tughlakabad, to Badarpur interchange, with elevated corridor over the Vasant Vihar T-section, Khanpur, Hamdard Nagar and Maa Anandmayi Marg intersections.
- Kalindi Bypass: connects at Badarpur interchange.
- Phase-3 - covers eastern semicircle:
- Badarpur-Noida Expressway (BNE): from Badarpur interchange, over the yamuna river via new bridge, to Noida-Greater Noida Bundh Expressway (NGNBE) at Asgarpur Jagir & Noida-Greater Noida Expressway (NGNE) at Noida Sector-98 interchange - both of which converge at Okhla Bird Sanctuary.
- Chilla-Okhla Sanctuary Expressway (i.e. Chilla-Shahadra Drain Elevated Road): from Noida end of DND Flyway at Chilla, then over and along the Shahdara Drain to Okhla Bird Sanctuary (beginning of Noida-Greater Noida Expressway and Noida-Greater Noida Bundh Expressway).
- Chilla-Akshardham-Agraula section of Delhi–Saharanpur–Dehradun Expressway: from Chilla-Okhla Expressway (Chilla-Shahadra Drain Elevated Road), via Akshardham temple & Loni to Agraula.
- Spurs:
- Burari-Loni-Ghaziabad-Okhla - North Delhi-Ghaziabad inner loop: will pass through Khanpur Japti, Loni, south of Hindon Airport, Chaudhary Charan Singh Marg (Bhopura, Saheed Nagar, Kaushambhi & Ghazipur), and via Ghazipur Road to DND Flyway.
- Agraula-Jawli-Ghaziabad Expressway - North Delhi-Ghaziabad outer loop: Alipur-Burari-Agraula will continue to Jawli and then to NH9 Morti interchange in Ghaziabad where it will meet Faridabad-Noida-Ghaziabad Expressway (FNG).
Construction
Phase 1
The NHAI has divided the construction work of UER II project into 5 packages and its construction cost is around ₹7,716 crores.
Sr No | Package | Length in km | Value in crores | State |
---|---|---|---|---|
1. | NH1 to Karala-kanjhawala Road | 15 | ₹1,552 | Delhi |
2. | Karala-kanjhawala Road to Nangloi Najafgarh Road | 13.450 | ₹1,121 | Delhi |
3. | Nangloi Najafgarh Road to Dwarka Sector 24 Road | 9.661 | ₹685.31 | Delhi |
4. | Starting From Bawana Industrial Area, Delhi to Village Barwasani, Sonipat In Haryana | 29.6 | ₹694 | Delhi and Haryana |
5. | UER-II near Bakkarwala to Bahadurgarh bypass of NH-10 near Bahadurgarh in Haryana | 7.269 | ₹324 | Delhi and Haryana |
Current status
- 2021 Mar: Expected completion date for UER II set to August 2023. Delhi Govt granted permission to transplant 6600 trees.
- 2021 Nov: H.G. Infra Engineering awarded the tender by NHAI for the Phase-I Package-1.
- 2024 Oct: Entire UER-II Phase-I 75.7 km will become operational by December 2024, Alipur-Kanjhawala section will be ready by December 2024, Najafgarh-Dwarka section is already operational, Kanjhawala-Najafgarh section will be ready by December 2024.
As per the ground reports, the project is not expected to be completed before March 2024. The company completing phase 2 is very bad at work completion
See also
References
- ^ "Delhi: Work on second phase of UER-II to start by September-end". Times of India. Retrieved 28 August 2021.
- "Delhi Urban Extension Road 2 – Information & Status". The Metro Rail Guy. Retrieved 24 November 2022.
- ^ Delhi Urban Extension Road 2 – Information & Status, The Metro Guy, accessed 7 dec 2022.
- ^ Factories to flyovers, what 2021 has in store for Noida and greater Noida., Times of India, 31 December 2021
- शामली से होकर गुजरेगा सर्कुलर एक्सप्रेस-वे, Amar Ujala, 22 sept 2021.
- Draft NCR Regional plan 2041, NCR planning board accessed, 6 dec 2022.
- "Finish Delhi's 3rd ring road by 2023, make delayed projects list: PM Modi". Times of India. 26 August 2021.
- "Permission to cut, transplant 6,000 trees for third Ring Road in Delhi". Hindustan Times. 20 August 2021.
- "H G Infra Engineering receives appointed date from NHAI for Delhi project". IIFL Securities. 2 November 2021.
- UER-II to be ready by year end: Delhi LG office, Hindustan Times, 18 Oct 2024.