Venezuela has experienced a marked deficit in the generation of electrical energy. The immediate cause of the energy crisis was a prolonged drought that caused the water in the reservoir of the Simón Bolívar Hydroelectric Plant to reach very low levels. Although various measures were taken to overcome the crisis, one of the most controversial was the implementation of a program of electrical rationing throughout the country, except in the capital Caracas, which was ultimately officially suspended in June 2010, due to the recovery of reservoirs due to the rains, and not to interrupt the transmission of the 2010 FIFA World Cup. Power cuts have continued to occur in the interior of the country, although with less frequency and duration, this time driven by failures in other parts of the system. The situation of "electrical emergency" decreed by the government on 21 December 2009 was suspended on 30 November 2010; however, on 14 May 2011, after the country experienced two national blackouts, the government of Hugo Chávez announced a temporary rationing plan and acknowledged that the electricity system continued to face "generation weaknesses" that they did not expect to surpass until end the year.

The energy problem was widely politicized in Venezuela: in addition to the drought, the Chávez government also blamed wealthy sectors of the population of the crisis, assuring that they wasted electricity. The Venezuelan opposition responded by holding the government itself responsible, accusing it of not having made the necessary investments to keep pace with the country's electricity consumption growth, as well as having neglected the electricity infrastructure, which was completely nationalized a few years before.

According to United Nations Economic Commission for Latin America and the Caribbean (ECLAC), the electricity crisis was one of the factors that contributed to the economic crisis that Venezuela experienced since 2009, which in turn is credited with giving way to the ongoing crisis in Venezuela. Furthermore, this crisis also influenced the notable increase in votes that the Venezuelan opposition experienced in the 2010 parliamentary elections.

Causes and characteristics

Crisis in Venezuela
Causes
Effects
Events
Elections
Protests
Timeline
Armed violence
flag Venezuela portal

Venezuela, the main oil exporter in South America, suffered from a long drought that significantly reduced the volume of water in the dams of hydroelectric plants. For 2009, 73% of the electric energy consumed by Venezuelans depended on these plants. Additionally, the country's electricity consumption has been increasing by 6% per year, a percentage that exceeds the growth rate in the electrical supply that has been installed.

Most of Venezuela's power comes from one of the largest hydroelectric dams in the world, Guri Dam in Bolívar State, Venezuela on the Caroni River; as of 2019, 70–80% of Venezuela's power comes from Guri. Venezuela has a history of electrical blackouts dating at least to 2010; Juan Nagel wrote in Foreign Policy in 2016 that the problems resulted from "massive government corruption and the country’s disastrous energy policies". Univision also reported that the problems in the energy sector resulted from corruption and "lack of maintenance and investment". A report from Transparency Venezuela said that maintenance was abandoned for twenty years beginning in 1998. The aging infrastructure made the problems worse, and critics were silenced; a union leader for state power workers was arrested in 2018 by the Bolivarian Intelligence Service for warning that a blackout was likely.

The private company, Electricidad de Caracas was owned by the United States' AES Corporation until 2007; according to The Wall Street Journal, "Venezuela's power grid was once the envy of Latin America". Then-President Hugo Chávez created the state-run Corpoelec by nationalizing the electric sector and expelling private industry in 2007; hence, the state has been solely responsible for energy supply for over ten years. Univision says Chávez "admitted failures (...) such as the 'insufficient' availability of the thermoelectric generation plant and the limitations of the national electric power transmission network and distribution systems"; he signed a decree in 2010 declaring a "State of Emergency of the National Electric Service". Chávez had Corpoelec speed up projects, and bypassing the process of public bidding for projects, he "authorized 'contracting by direct award'," which facilitated corruption.

Low level of the Guri reservoir

Simón Bolívar Hydroelectric Plant, on the Guri Dam

The main power plant of the hydroelectric system is the Simón Bolívar Hydroelectric Plant, with a generation capacity of 10,000 MW, but which generated only 5,000 MWh after being affected by the drought, and by the beginning of February 2010, the level of the dam had dropped nine meters below its optimum level. If the level of the Guri reservoir falls below 240 masl, some turbines in the plant could not work, and the country's electricity supply would decrease. The government foresaw that if nothing were done, this level would be reached in May 2010, so it began to execute a series of measures that seek to reduce electricity demand and minimize Venezuela's dependence on hydroelectric power plants. By the end of March 2010, this date had been postponed to June 2010.

The possibility that the Guri reservoir reached the critical level was first seen by President Hugo Chávez on 31 January 2010, by ensuring that if the companies did not reduce their electricity consumption "70% of the country would be left without electric service". On 9 March, Chávez was more emphatic about it, declaring:

The Guri is 13 meters away from what they call the collapse level. If these parameters were reached, the Guri plants would have to be turned off, which generate electricity for half of Venezuela. That is the reality.

— Hugo Chávez, 9 March 2010

Subsequently, on 18 March, the Minister of Electric Power, Alí Rodríguez Araque, accused the Venezuelan opposition of causing fear in the population by talking about a "collapse." Operating below this level is dangerous because steam could enter the turbines, a phenomenon known as cavitation, that can cause mechanical damage to them.

By April 15, 2010, the Guri reservoir reached 8.79 meters above the collapse level; however, the next day its level increased by one centimeter, the first increase reported in months. On 23 April, the Minister of the Environment, Alejandro Hitcher, assured that the Guri would reach a normal growth rate within fifteen or twenty days. However, according to Miguel Lara, former general manager of the Interconnected Systems Operation Office, the crisis continued due to problems in the thermal generation park and transmission lines, although he recognized that it is unlikely that the Guri will collapse.

Thermal park deficiency

The National Electric Corporation, the public body that manages all electricity generating companies, acknowledged that by the end of 2008, 79% of thermoelectric plants were more than 20 years old, and that 30% were unavailable due to technical problems. In addition, of the plants that were working, many did not do so at full capacity: 3,800 MW were generated, when the installed capacity was 9,051 MW.

Planta Centro, Carabobo

One of the main thermoelectric plants in the country, Planta Centro, has an installed capacity of 2,000 MW, divided into five units of 400 MW each. In the last few months only two units were operational, generating about 450 MW. Although the funds to reactivate an additional unit were delivered months before, for the start of the crisis the work was 21 months behind. Subsequently, on 27 March, a unit was stopped for maintenance. By the beginning of April 2010, Planta Centro operates only with a unit of 400 MW, which is only generating 250 MW. Electrical specialists believe that Planta Centro is unlikely to recover in the short term, claiming lack of maintenance in recent years as the main cause.

Other plants presented similar situations: the Pedro Camejo plant produced 50% of its capacity "for reasons of fuel and associated transmission"; and the Josefa Camejo plant operated at 33% of its capacity. Additionally, operating plants have reduced their generation since the beginning of the crisis: Plant Tacoa in Vargas had to shut down a unit of 377 MW in April, and plant Ramon Laguna stopped two machines that generated 253 MW in Zulia.

Disparity in the increase in demand and electric supply

Even before the 2009-2010 drought, there was already a disparity between the increase in supply and demand for electricity in Venezuela; the latter had been increasing at a rate of 7% per year since 2005. This deficit has been criticized by the opposition, alleging that in previous years the Venezuelan government did not make the necessary investments to increase power generation capacity at the same rate as the increase in demand. On the other hand, the government has accused sectors of the population of "wasting" electricity, and has highlighted the fact that Venezuela is the country with the highest electricity consumption per capita in Latin America.

According to figures from the Office of Operation of Interconnected Systems, the Chávez government completed less than half of the investments in thermoelectric energy generation planned in 2005. Alí Rodríguez has denied that the government has not made the necessary investments, although he acknowledged that there are delays in the execution of projects.

Saturation of distribution and transmission lines

On 21 April 2010, a power cut was reported from the east to the west of the country, affecting 15 of the 24 states of Venezuela. Due to the distribution of the fault, Ciro Portillo, former vice president of Enelven, has assured that it is due to overload in one of the three transmission lines that start from the Guri. Before the crisis, the transmission lines were transmitting 1,000 MW over their capacity during the peak hours. The high temperatures Venezuela experiences between April and May also influence the saturation of these lines. The company Enelven, responsible for the affected areas, has not reported on the causes of this energy slump. For its part, the National Management Center has reported that Cadafe-Occidente overloads transmission lines daily.

Responses

Investments

 In 2009, the Chávez administration declared a national electric emergency and invested $100 billion US dollars towards solving it. The Chávez administration "distributed million-dollar contracts without bidding that enriched high officials of his government and the works were never built", according to Univision. The Wall Street Journal stated that the government awarded electrical contracts to companies with little experience in the energy sector. Billions of dollars were awarded in contracts for projects that were never completed, leading to international investigations of "high officials of the Chavez regime today persecuted for plundering the coffers of the Bolivarian Republic". Critics say that one company, Derwick Associates, was given projects although they had no previous experience; Derwick denies any bribes were involved. Of 40 energy projects approved between 2010 and 2014 analyzed by Transparency Venezuela, 17 are not completed as of March 2019, none are operating at capacity, and overcharging by billions of dollars was identified. In 2017, the National Assembly investigated the $100 billion dollars invested in the electrical system and determined that over $80 billion was embezzled, that more than 14 thermoelectric stations were not functioning, and that neither the electrical transmission nor the distribution system had adequate maintenance.

Installation of thermoelectric plants

This section needs expansion. You can help by adding to it. (January 2022)

President Chávez set a goal of installing 6,000 MW in 2010 through thermoelectric plants, an increase in the electricity supply greater than what has been installed during his then-eleven years in office. In addition, the estimated cost of the plan was of more than US$5,000 million.

Rationing in Caracas

Initially, an electric rationing plan was implemented in Caracas, the Venezuelan capital, but it was suspended days later amid protests, which also led to the departure of then-Minister of Electric Energy Ángel Rodríguez, who was replaced by Rodríguez Araque. A new electricity service charge scheme was implemented for users who consume more than 500 kWh per month, who have been identified as "high consumers" by the government. In addition, industries were ordered to reduce by 20% its electricity consumption, with a penalty of temporary interruption of the service in case they did not reach the goal. According to the director of the Chamber of Commerce of Caracas, this last measure was an attempt by the government to "blame the companies for the crisis".

Rationing in the rest of the country

In the rest of Venezuela, an electric rationing system was implemented by zones. Before Holy Week in 2010, the power supply was cut by about 3 hours at a frequency of 3 or 4 days. On average, outside of Caracas, Venezuela experienced an interruption in electrical service of between 9 and 12 hours a week.

However, the results were not as expected; between January and February, a reduction in demand of 3% was experienced, while the goal set by President Chávez was 20%. After Easter, the frequency and duration of electricity supply cuts would increase in all of Venezuela except in Caracas: The Venezuelan inside the country experienced daily cuts of four hours, that is, more than 20 hours per week.

The Venezuelan government ruled out interrupting the electricity supply in Caracas, even if the Guri reservoir reaches the emergency level. In this case, rationing would be accentuated in the Venezuelan territory corresponding the Guiana Shield, eastern Venezuela, and the Central-Falcón zone. The Venezuelan opposition criticized the idea of applying rationing to the rest of Venezuela except the capital as "discriminatory".

At the end of April, Corpoelec ordered greater rationing, this time without prior notice and at night. Blackouts due to this cause have been reported in the states of Aragua, Anzoátegui, Mérida, Sucre, Táchira and Zulia.

Reduction of activities in basic industries

SIDOR's basic industries in Venezuela's side of the Guiana Shield have been hit hard by the crisis, whose production had already fallen by 40% in December 2009, after the Electricity Ministry set a 300 MW consumption limit; before the crisis, SIDOR consumed 800 MW. By February 2010, SIDOR operated at only 45% of its capacity, and 30,000 tons of metal billets were imported to Brazil to meet national demand.

The government did not rule out paralyzing the activities of these industries completely, due to the high energy consumption that their processes require. In addition, three power plants were acquired to allow SIDOR to generate its own energy. It was expected that by the end of May 2010, the first of these plants would start generating the first 175 MW out of a total of 425 MW.

Import of electric power from Colombia

In 2011, due to the crisis and electricity deficit, electrical energy began to be imported from Colombia. The transfer is made through Cuestecitas-Cuatricentenario, through the exclusive commercial representative Isagen. Electric exports to Venezuela are also made from Norte de Santander through the San Mateo-Corozo circuit, with which Isagen has a connection contract through which 27.52 GWh have been exported.

Official suspension of rationing and new blackouts

On 22 May, the Venezuelan government announced the suspension of rationing on weekends and holidays, and off peak hours throughout the country. Rationing would then be maintained only on weekdays during peak hours, due to the partial recovery of the reservoirs thanks to the arrival of rains and the inauguration of some electrical works.

On 10 June, President Chávez ordered the suspension of rationing, although he acknowledged that if peak hours were to exceed the limit of the transmission lines, rationing could be applied in that period. In addition, the state of electrical emergency would be maintained, as well as the rationing schedule in the public offices, at least until 30 July 2010. Chávez also acknowledged that the production of the basic companies of Guayana "went to the ground, but the worst is over". On 17 June, the Minister for Electric Power, Alí Rodríguez, declared that the electricity crisis had not ended, but that "the worst has happened." The suspension of rationing was carried out due to the recovery of the reservoirs for the rains and not to interrupt the transmission of the 2010 FIFA World Cup.

However, despite the fact that the Guri reservoir reached its maximum level at the end of August 2010, power cuts have continued to happen. According to the newspaper El Tiempo, Barcelona and Puerto la Cruz, two cities of Anzoátegui state, went almost 62 hours without electricity in a period of six days, due to faults in circuits and substations. In other parts of the country, the blackouts would be driven by faults in the transmission lines, and because several units of the Simón Bolívar Hydroelectric Plant is under maintenance. Chavismo spokespeople also hinted that there was "sabotage", claiming that they believed it was "very suspicious" that the blackouts intensified when the Guri reservoir reached its peak, others have accused the Venezuelan opposition directly, and even the United States of sabotage. However, there has also been recognition of inefficiency on the part of the government:

There is inefficiency too, many of us are learning to govern ... It takes at least 20 years for us to learn to govern.

— Perfecto Abreu, spokesman of the Communist Party of Venezuela

Consequences

Venezuela presented a GDP contraction of 3.3% in 2009, leading the energy crisis to prolong the recession in 2010. Additionally, the transfer of power generation from hydroelectric to thermoelectric increased domestic consumption of petroleum products and natural gas, causing a drop in Venezuelan exports, that had already experienced a 17% drop in 2009. The Minister of Energy and Mines, Rafael Ramírez, calculated that Venezuela would need 100,000 barrels of diesel fuel a day to maintain the thermoelectric plants working, once they are all operational.

Although the government has blamed the El Niño phenomenon exclusively for the crisis, several polls indicate that the majority of Venezuelans blamed the Chávez government, accusing him of not having invested enough to offset the demand. For his part, Chávez accused the opposition of seeking political gains from the energy crisis.

There were two major blackouts in 2013. In 2016, Venezuela had a severe electricity crisis that caused blackouts, industry shutdowns, and the decision by then-President Nicolás Maduro to cut back on government employee's work hours. Maduro's administration has put rationing in place several times, and changed the country's clocks to accommodate a daytime commute. Nagel wrote in 2016, "... there are two main reasons for the crisis: excessive electricity consumption and insufficient production. And the root of both of these problems is bad governance: populism, poor planning, inflexible ideology, and overwhelming corruption." In 2017, there were more than 18,000 power outages nationwide.

See also

References

  1. "El Niño conditions return to affect weather". NBC News. 9 July 2009. Retrieved 28 March 2010.
  2. ^ "Chávez ordenó suspender medidas de racionamiento eléctrico en Venezuela" [Chávez ordered the suspension of electricity rationing measures in Venezuela] (in Spanish). Terra. Agence France-Presse. 10 June 2010. Archived from the original on 24 November 2011.
  3. ^ García, Daniela (27 August 2010). "Ejecutivo se ve obligado a drenar agua en el Guri" [Executive is forced to drain water in the Guri]. La Verdad (in Spanish). Archived from the original on 30 November 2011. Retrieved 6 September 2010.
  4. ^ "Mayor embalse de Venezuela se recupera, aunque persiste el racionamiento" [Largest reservoir in Venezuela recovers, although rationing persists]. AméricaEconomía (in Spanish). 30 August 2010. Retrieved 6 September 2010.
  5. ^ Vargas, Andreína (31 August 2010). "Gobierno admite saturación de redes eléctricas en Oriente" [Government admits power grid saturation in Oriente]. El Tiempo (in Spanish). Retrieved 6 September 2010.
  6. "El fantasma del racionamiento eléctrico sobrevuela Venezuela" [The ghost of electric rationing overflies Venezuela]. Infobae (in Spanish). Associated Press. 14 May 2011. Retrieved 14 May 2011.
  7. "Ministro Alí Rodríguez Araque alertó sobre un posible racionamiento eléctrico" [Minister Alí Rodríguez Araque warned of possible electric rationing]. Ciber Protesta Venezuela (in Spanish). 13 March 2011. Retrieved 19 March 2011.
  8. ^ "Chávez desea terminar con "derroche" de energía eléctrica en el país" [Chávez wants to end with "waste" of electricity in the country]. El Economista (in Spanish). 16 October 2009. Retrieved 28 March 2010.
  9. "Chávez combate 'derroche' de agua y luz en Venezuela" [Chavez fights 'waste' of water and electricity in Venezuela]. Diario Expreso (in Spanish). 1 November 2009. Archived from the original on 11 January 2012. Retrieved 28 March 2010.
  10. "Crisis energética acosa a gobierno venezolano" [Energy crisis harasses the Venezuelan government]. El Universo (in Spanish). Reuters. 24 October 2009. Retrieved 28 March 2010.
  11. "Venezuela anuncia inversión en energía" [Venezuela announces investment in energy] (in Spanish). BBC. 1 February 2010. Retrieved 28 March 2010.
  12. "2010, un mal año para la economía venezolana" [2010, a bad year for the Venezuelan economy]. Terra (in Spanish). 28 December 2010. Archived from the original on 13 December 2013. Retrieved 30 December 2010.
  13. "Hugo Chávez sufre un revés doloroso a dos años de las presidenciales" [Hugo Chávez suffers a painful setback two years before the presidential elections] (in Spanish). MSN. Agence France-Presse. 27 September 2010. Archived from the original on 30 September 2010. Retrieved 19 March 2011.
  14. "Chávez sufre revés en elección legislativa de Venezuela" [Chávez suffers setback in Venezuela's legislative election]. Terra (in Spanish). Reuters. 27 September 2010. Archived from the original on 24 July 2014. Retrieved 19 March 2011.
  15. ^ Molinski, Dan (8 January 2010). "Energy-Rich Venezuela Faces Power Crisis". The Wall Street Journal. Retrieved 2 April 2010.
  16. ^ "Facts about Venezuela's energy crisis". Reuters. 9 March 2010. Archived from the original on 12 March 2010. Retrieved 2 April 2010.
  17. ^ Dube, Ryan and Maolis Castro (8 March 2019). "Venezuela Blackout Plunges Millions Into Darkness; Maduro, without evidence, blames sabotage by local opponents and the U.S. for power outage". Wall Street Journal. Retrieved 10 March 2019. One company, Derwick Associates, formed by a number of well connected young businessmen with scant experience in the power business, received about $1.8 billion in contracts from Venezuelan state companies to buy and install turbines, paying a U.S. company about $1 billion to do the work. Derwick officials said they paid no bribes to any Venezuelan officials and the prices charged by the company reflected the high costs of doing business in Venezuela.
  18. ^ Newman, Lily Hay (12 March 2019). "Why it's so hard to restart Venezuela's power grid". Wired. Retrieved 13 March 2019.
  19. ^ Peñaloza, Pedro Pablo (10 March 2019). "Más de una década de corrupción e improvisación dejan a Venezuela a oscuras" [More than a decade of corruption and improvisation leave Venezuela in the dark]. Univision (in Spanish). Retrieved 14 March 2019.
  20. ^ Nagel, Juan Cristóbal (1 April 2016). "In Venezuela, the Lights Are Going Out". Foreign Policy. Retrieved 10 March 2019. U.S. and Swiss authorities launched probes into Derwick Associates, a Venezuelan firm that builds power plants for the government. No criminal charges have yet been filed, but the firm is being investigated for laundering money and paying bribes to the state-owned oil giant, PDVSA, using international financial institutions. Venezuelan investigative journalists and bloggers have been on Dewick's (sic) case, finding more examples of bad behavior. They claim that its contracts were overpriced and awarded without public tender, and that the firm passed off used power plants as brand new. Derwick denies all these allegations, claiming that it is being subjected to a "witch hunt." Derwick is just one firm, but the saga appears to confirm that much of what ails Venezuela's electricity sector has to do with massive government corruption. It would be simplistic to say that corruption is the only problem, however. In addition to tackling corruption, sorting out this mess for good would involve undoing the country's disastrous energy policies – privatizing electricity generation and raising prices.
  21. Jones, Sam (13 March 2019). "Venezuela blackout: what caused it and what happens next?". The Guardian. ISSN 0261-3077. Retrieved 13 March 2019.
  22. "Central Hidroeléctrica Simón Bolívar en Guri" [Simón Bolívar Hydroelectric Plant in Guri] (in Spanish). EDELCA. Archived from the original on 23 March 2010. Retrieved 2 April 2010.
  23. Fernández, Yaneth (19 March 2010). "Operating Guri Dam below the critical level is a "suicide"". El Universal. Archived from the original on 25 March 2010. Retrieved 2 April 2010.
  24. ^ "Chavez puts Venezuela under 'electricity emergency'". BBC News. 9 February 2010. Retrieved 2 April 2010.
  25. ^ "Cota del Guri en 240 metros implica ahorrar hasta 2.000 Mw" [Guri elevation in 240 meters means saving up to 2,000 Mw]. El Universal (in Spanish). 22 March 2010. Archived from the original on 9 April 2013. Retrieved 2 April 2010.
  26. ^ Prat C., Damian (22 March 2010). "El falso colapso del Guri" [The false collapse of the Guri]. Tal Cual (in Spanish). Archived from the original on 27 March 2010. Retrieved 2 April 2010.
  27. León, Mariela (16 April 2010). "Guri dam level rises for the first time in months". El Universal. Archived from the original on 9 April 2013. Retrieved 23 April 2010.
  28. ^ León, Mariela (24 April 2010). "Hitcher advierte que en 20 días el nivel de Guri se normalizará" [Hitcher gives notice that in 20 days the level of Guri will be normalized]. El Universal (in Spanish). Archived from the original on 27 April 2010. Retrieved 29 April 2010.
  29. León, Mariela (21 April 2010). "Embalse de Guri se recupera y gana 24 centímetros en 5 días" [Embalse de Guri recovers and gains 24 centimeters in 5 days]. El Universal (in Spanish). Archived from the original on 7 March 2016. Retrieved 29 April 2010.
  30. ^ Hernández, Moisés G. (29 March 2010). "Noticias" [News]. El Carabobeño (in Spanish). Archived from the original on 19 April 2015. Retrieved 2 April 2010.
  31. Díaz, Ana (9 March 2010). "Guri está a 13,64 metros de su nivel crítico" [Guri is 13.64 meters from its critical level]. El Nacional (in Spanish). Archived from the original on 11 March 2010. Retrieved 2 April 2010.
  32. "Trabajadores cuestionan atraso en las obras de Planta Centro" [Workers question delays in the works of Plant Center]. El Universal (in Spanish). 1 March 2010. Retrieved 2 April 2010.
  33. ^ García, Daniela (24 April 2010). "Aplicarán más racionamiento eléctrico sin previo aviso" [More electric rationing will be applied without notice]. La Verdad (in Spanish). Archived from the original on 30 November 2011. Retrieved 29 April 2010.
  34. ^ Zerpa, Fabiola; Romero, Tibisay (30 March 2010). "Deterioro de Planta Centro hace inviable su recuperación" [Deterioration of Planta Centro makes recovery unfeasible]. El Nacional (in Spanish). Retrieved 2 April 2010.
  35. ^ "Consumo per cápita de electricidad en Venezuela es el más alto de la región" [Per capita electricity consumption in Venezuela is the highest in the region]. Informe21 (in Spanish). 11 February 2010. Retrieved 2 April 2010.
  36. ^ García, Daniela (21 April 2010). "Bajón eléctrico en 15 estados por fallas en línea de transmisión" [Electric downturn in 15 states due to transmission line failures]. La Verdad (in Spanish). Archived from the original on 30 November 2011. Retrieved 29 April 2010.
  37. ^ León, Mariela (28 April 2010). "Fallas de luz demuestran saturación del sistema" [Light failures show system saturation]. El Universal (in Spanish). Archived from the original on 9 April 2013. Retrieved 23 April 2010.
  38. Vinogradoff, Ludmila (8 March 2019). "Un largo apagón de 20 horas deja en la oscuridad a toda Venezuela". ABC (in Spanish). Retrieved 18 March 2019.
  39. Grant, Will (14 March 2019). "Entrevista de Juan Guaidó con la BBC: "Ninguno de los organismos de seguridad que el gobierno controla se ha atrevido a apresarme"". BBC. Retrieved 18 March 2019.
  40. "Venezuela invertirá 600 millones de dólares en dos plantas generadoras" [Venezuela will invest 600 million dollars in two power plants] (in Spanish). EFE. 31 March 2010. Archived from the original on 11 April 2013. Retrieved 2 April 2010.
  41. ^ "Venezuela corta la luz a los comercios que no redujeron consumo eléctrico" [Venezuela cuts the light to businesses that did not reduce electricity consumption]. BioBioChile (in Spanish). 20 March 2010. Retrieved 2 April 2010.
  42. ^ Zerpa, Fabiola (28 March 2010). "Extenderán cortes de electricidad en el interior después del asueto" [Power cuts will be extended in the interior after the break]. El Nacional (in Spanish). Retrieved 2 April 2010.
  43. ^ "Caracas estará protegida ante colapso del Guri" [Caracas will be protected from the collapse of the Guri]. Reporte360 (in Spanish). 17 March 2010. Retrieved 2 April 2010.
  44. "Oposición exige cese de racionamiento discriminatorio de electricidad" [Opposition demands cessation of discriminatory electricity rationing]. El Espectador (in Spanish). EFE. 16 January 2010. Retrieved 2 April 2010.
  45. ^ "30 mil toneladas de acero comprará Sidor a Brasil" [Sidor will buy 30,000 tons of steel from Brazil]. La Clase (in Spanish). 26 February 2010. Retrieved 2 April 2010.
  46. "Isagen exporta energía desde la Guajira a Venezuela" [Isagen exports energy from Guajira to Venezuela]. El Universal. 14 June 2011.
  47. Hernández F., Alejandra M. (22 May 2010). "Chávez suspende parcialmente "dieta eléctrica" nacional" [Chávez partially suspends national "electric diet"]. El Universal (in Spanish). Retrieved 13 June 2010.
  48. ^ "Chávez levanta racionamientos eléctricos de fines de semana y festivos" [Chávez lifts electric rationing for weekends and holidays] (in Spanish). Europa Press. 22 May 2010. Retrieved 13 June 2010.
  49. ^ "Gobierno suspende racionamiento eléctrico durante fines de semana" [Government suspends power rationing during weekends]. Analítica (in Spanish). 22 May 2010. Retrieved 13 June 2010.
  50. ^ "Suspenden racionamiento eléctrico en todo el país" [Suspended electricity rationing throughout the country]. El Nacional (in Spanish). 10 June 2010. Archived from the original on 15 June 2010. Retrieved 17 June 2010.
  51. "Rodríguez Araque dice que "lo peor ha pasado" en la crisis eléctrica" [Rodríguez Araque says that "the worst has happened" in the electricity crisis]. Últimas Noticias (in Spanish). 17 June 2010. Retrieved 17 June 2010.
  52. "Autoridades investigarán presunto sabotaje eléctrico" [Authorities will investigate alleged electrical sabotage]. El Universal (in Spanish). 6 September 2010. Archived from the original on 7 November 2017. Retrieved 6 September 2010.
  53. ^ "PCV culpa al "imperio" de los apagones" [PCV blames the "empire" of the blackouts]. El Universal (in Spanish). 6 September 2010. Archived from the original on 7 November 2017. Retrieved 6 September 2010.
  54. "Prevén prolongada recesión por crisis eléctrica en Venezuela" [Long-term recession foreseen due to electric crisis in Venezuela]. El Informador (in Spanish). 6 January 2010. Retrieved 2 April 2010.
  55. García, Daniela (9 March 2010). "Consumo de combustible de Venezuela subirá 31 por ciento por crisis eléctrica" [Venezuela's fuel consumption will rise 31 percent due to electric crisis]. La Verdad (in Spanish). Archived from the original on 30 November 2011. Retrieved 2 April 2010.
  56. ^ "Crisis eléctrica que padece Venezuela golpea la exportación de petróleo" [Electric crisis that Venezuela suffers hits the export of oil]. Portafolio (in Spanish). 18 February 2010. Retrieved 2 April 2010.
  57. ^ Parraga, Marianna (25 March 2010). "Venezuela misses energy target, dams keep falling". Reuters. Archived from the original on 11 April 2013. Retrieved 2 April 2010.
  58. Rendon, Moises (14 March 2019). "Venezuela's man-made power outage". Center for Strategic and International Studies. Retrieved 14 March 2019.
Financial crises
Pre-1000
Commercial revolution
(1000–1760)
1st Industrial Revolution
(1760–1840)
1840–1870
2nd Industrial Revolution
(1870–1914)
Interwar period
(1918–1939)
Wartime period
(1939–1945)
Post–WWII expansion
(1945–1973)
Great Inflation
(1973–1982)
Great Moderation/
Great Regression
(1982–2007)
Great Recession
(2007–2009)
Information Age
(2009–present)
Crisis in Venezuela
Events
Ongoing
2010
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
Deaths during protests
2014
2015
2017
People
Pro-Maduro
Anti-Maduro
Organizations
Pro-Maduro
Anti-Maduro
Related
In popular culture
Categories: