The following page lists power stations in Bolivia. Most of them are managed by ENDE.
Installed generating capacity and production
Bolivia had an estimated installed generating capacity of 1,365 MW in 2012 and produced an estimated 7.375 billion kWh in 2013.
BuloCarrascoChoCoraniEl AltoEntre RiosGuaracachiMisicuniSantaValleYanacachiHydroelectric
Hydroelectric power plants with a nameplate capacity > 20 MW.
Name | Capacity (MW) | River (basin) | Status |
---|---|---|---|
Chojlla HPP | 38,4 | Río Taquesi | Operational |
Corani HPP | 45 | Corani Lake | Operational |
Misicuni Dam | 80 | Río Misicuni | Under construction |
Santa Isabel HPP | 93,4 | Corani Lake | Operational |
Yanacachi HPP | 51,1 | Río Taquesi | Operational |
Thermal
Thermal power plants with a nameplate capacity > 80 MW.
Name | Capacity (MW) | Type of fuel | Status |
---|---|---|---|
Bulo Bulo Power Plant | 90 | Natural gas | Operational |
Carrasco Power Plant | 152,6 | Natural gas | Operational |
El Alto Power Plant | 80 | Natural gas | Operational |
Entre Rios Power Plant | 120 | Natural gas | Operational |
Guaracachi Power Plant | 350 | Natural gas | Operational |
Valle Hermoso Power Plant | 167 | Natural gas | Operational |
Additional information
- Bulo Bulo, Cochabamba, 2 X 45 MW LM6000 gas turbines, natural gas
Bulo Bulo was built by a joint venture of NRG Energy, Vattenfall, and Pan American Energy LLC. It went commercial on 30 June 2000 with a 30-year generation license. In May 2003, Petrolera Chaco purchased the plant.
- Entre Rios, Cochabamba, 4 X 30 MW SGT-700 gas turbines, natural gas
This project is a 60:40 joint venture of Ende and PDVSA and was the result of an August 2007 agreement between Presidents Evo Morales and Hugo Chávez. It cost about $80mn and connects to the 230kV grid. Commercial operation began on 22 July 2010.
- Guaracachi, Santa Cruz, 210-MW, 2+1 CCGT plant with 6001FA gas turbines, natural gas
In Oct 2010, two 6FA gas turbines at Guaracachi in Santa Cruz were converted to combined-cycle operation. In addition to the HRSGs and steam set, the installation included a new five-cell mechanical draft tower and a demineralized water treatment plant. The plant was 50% owned by Rurelec PLC when nationalized by Bolivian President Evo Morales in February 2010.
See also
External links
- NRG Energy acquires South American generation capacity from Vattenfall
- Industry Picture Cards for Bolivia
References
- "The World Factbook". CIA. Retrieved 2015-10-03.
- "Chojlla Hydroelectric Power Plant Bolivia". Global Energy Observatory. Retrieved 2015-10-03.
- "Corani Hydroelectric Power Plant Bolivia". Global Energy Observatory. Retrieved 2015-10-03.
- "Santa Isabel Hydroelectric Power Plant Bolivia". Global Energy Observatory. Retrieved 2015-10-03.
- "Yanacachi Norte Hydroelectric Power Plant Bolivia". Global Energy Observatory. Retrieved 2015-10-03.
- "Bulo Bulo OCGT Power Plant Bolivia". Global Energy Observatory. Retrieved 2015-10-04.
- "Carrasco OCGT Power Plant Bolivia". Global Energy Observatory. Retrieved 2015-10-04.
- "El Alto (El Kenko) Power Plant Bolivia". Global Energy Observatory. Retrieved 2015-10-04.
- "Entre Rios Power Plant Bolivia". Global Energy Observatory. Retrieved 2015-10-04.
- "Guaracachi CCGT Power Plant Bolivia". Global Energy Observatory. Retrieved 2015-10-03.
- "Valle Hermoso Power Plant Bolivia". Global Energy Observatory. Retrieved 2015-10-04.