Misplaced Pages

Quemahoning Tunnel

Article snapshot taken from Wikipedia with creative commons attribution-sharealike license. Give it a read and then ask your questions in the chat. We can research this topic together.
This article needs additional citations for verification. Please help improve this article by adding citations to reliable sources. Unsourced material may be challenged and removed.
Find sources: "Quemahoning Tunnel" – news · newspapers · books · scholar · JSTOR (June 2020) (Learn how and when to remove this message)
Quemahoning Tunnel
Overview
LocationSomerset County, Pennsylvania
Coordinates40°03′18″N 79°07′48″W / 40.055°N 79.130°W / 40.055; -79.130
StatusDestroyed
SystemPittsburgh, Westmoreland and Somerset Railroad
Operation
Opened1906
Closed1916
Technical
Track gauge1,435 mm (4 ft 8+1⁄2 in) standard gauge

The Quemahoning Tunnel was a tunnel that was constructed for use on the stillborn South Pennsylvania Railroad. The tunnel was located in Somerset County, Pennsylvania near the 106.3 milemarker of the Pennsylvania Turnpike.

While the South Pennsylvania Railroad never came to fruition and is known in history as "Vanderbilt's Folly", the Quemahoning Tunnel has the distinction of being the only tunnel of the nine tunnels constructed on the South Pennsylvania alignment that was actually used by railroads, as it was used by the Pittsburgh, Westmoreland and Somerset Railroad from 1909 to 1916.

When the newly formed Pennsylvania Turnpike Commission purchased the South Pennsylvania Railroad alignment in 1937, the Turnpike considered using the Quemahoning Tunnel, but instead bypassed it. The Laurel Hill Tunnel, which was also constructed by the railroad but used by the Pennsylvania Turnpike until its own bypassing in 1964, is located six miles to the west. The Negro Mountain Tunnel, also bypassed by the Turnpike during the original construction, is located ten miles to the east.

As of 2019, it was planned to be daylighted as part of the expansion of the turnpike to six lanes. In 2022 the destruction of the tunnel was reported to have been completed in preparation of the widening of the Turnpike.

References

  1. https://www.facebook.com/stuff.thatsgone/videos/1145045275669403/
  2. https://www.facebook.com/photo/?fbid=10217209062738199&set=gm.10159857209205073&idorvanity=38777495072

External links

Pennsylvania Turnpike Commission
Completed highways
Partially completed highways
Tunnels and bridges
Aborted expansion plans
Historical structures
Tolling systems
Categories: