Putrajaya Monorail

Article snapshot taken from Wikipedia with creative commons attribution-sharealike license. Give it a read and then ask your questions in the chat. We can research this topic together.

Incomplete monorail system in Putrajaya, Malaysia
Putrajaya Monorail Line
14
Putrajaya Monorail Suspended BridgeThe Monorail Suspension Bridge in Putrajaya since 2004
Overview
Native nameLaluan Monorel Putrajaya
StatusShelved in 2004; 20 years ago (2004) due to federal budget constraints.
(Under feasibility study)
Line number14
Termini
Stations25 stations
Service
TypeStraddle-beam single rail track monorail
Rolling stockTBD
Daily ridershipNot Available
RidershipNot Available
History
Planned openingTBD
OpenedTBD
Last extensionTBD
Technical
Line length18 km (11 mi)
Line 1: 13.2 km (8.2 mi)
Line 2: 6.8 km (4.2 mi)
Electrification750 V DC Third rail
Conduction systemTBD
Operating speed100 km/h (62mph)
Route map

Legend
S16D Kajang Parking 1 9
S16C Reko Sentral
S16B Bandar Baru Bangi
possibile extension
to HSR and MRT
S16A
Kampung Dato' Abu
Abu Bakar Baginda
 HSR 
S16 Presint Diplomatik
S15 Alamanda Putrajaya
S14 Lebuh Perdana Timur
S13 Taman Putra Perdana
S12 Laman Perdana
S11 Dataran Putra Putra Bridge
Depot S01 S10 Dataran Wawasan
Presint 11 S02 S09 Lebuh Bestari
Presint 9 S03 S08 Dtrn Putrajaya
Parking Putrajaya Sentral S04 Line 2 stabling
7 12 S21 Presint 17 Parking
Presint 7 S05
Presint 8 S06 S20 Presint 18
Dataran Rakyat S07
Monorail Suspension Bridge S19 Dataran Gemilang
Seri Gemilang Bridge
S18 PICC
S17 Presint 6 Parking
This diagram:

The Putrajaya Monorail is an incomplete monorail system in Putrajaya, Malaysia. Construction has been stalled since 2004, and while revivals have been proposed periodically, as of 2024 there are no plans to revive the project.

Putrajaya was originally planned to include a light rail system, but plans were changed, and a monorail plan was selected instead, after the construction of tunnels for aforementioned system began. It called for two sublines; Line 1, which is a 12 km (7.5 mi) monorail route with 17 stations and Line 2, which is a 6 km (3.7 mi) monorail route with 6 stations. In 2019, the government proposed a new light rapid transit (LRT) system may be built to revive the incomplete monorail project.

The monorail will include the Monorail Suspension Bridge, currently incomplete, and the Putra Bridge.

The monorail line would allow transfers to the existing KLIA Transit, connecting to Kuala Lumpur and Kuala Lumpur International Airport, and the now opened MRT Putrajaya line at  KT3   PY41  Putrajaya Sentral station. The project originally cost RM400 million.

Project Status

Monorail tracks with newly build MRT elevated track

Construction was halted in 2004; 20 years ago (2004), and will probably resume as the city becomes more populated.

In 2016, the MMC Corporation Berhad (MMC) submitted a proposal to the Economic Council (EC) to revive the stalled monorail project. The Land Public Transport Commission (SPAD) was due to conduct a feasibility study for monorail and tram services for both Putrajaya and Cyberjaya.

In October 2020, the government announced it had opened a request for proposals process to complete the project, within three months. As of 2021, the RFP has not yet opened.

In June 2023, the Ministry of Transport confirmed that the government is not planning to revive the project.

Putrajaya Tram Proposal

Federal Territories Minister, Datuk Seri Tengku Adnan Tengku Mansor, had hoped to get tram infrastructure construction going within three years. Now under the jurisdiction of the Economic Council, the minister saw the development of the tram system as an alternative solution to the abandoned monorail projects and recommended it be built due to cost considerations.

SPAD had hoped to open up tenders for the tram system between Putrajaya and Bangi in 2018 after getting the green light from EC. This move was announced by SPAD during their annual review of public transportation for 2017. The tram system was selected due to its relatively cheaper price of construction and operation compared to conventional rail systems.

The tram system is expected to be integrated with the existing and future rail lines between Putrajaya and Bangi and will also cover the distance between Cyberjaya and Kajang. The MRT Kajang Line only reaches Kajang but MRT Putrajaya Line will reach  KT3   PY41  Putrajaya Sentral station which is currently in operation. The future HSR station located at Kampung Abu Bakar Baginda will be one of the expected stops along the planned tram route.

The stretch between Putrajaya and Bangi has been selected as the first phase to be constructed due to their wide roads, allowing the tram system to share the traffic.

Putrajaya Tram
Legend
Proposed route
Kajang Parking  ETS  1 9
Kajang 2 1
Bandar Baru Bangi
Kampung Dato' Abu Bakar Baginda  HSR 
Alamanda Putrajaya
Putrajaya Sentral Parking 7 12
Cyberjaya City Centre 12
Bandar Cyberjaya Parking
Proposed route for the Putrajaya monorail as of 2022.

See also

References

  1. "Putrajaya Monorail back on track?". Retrieved 23 September 2016.
  2. "Long-abandoned Putrajaya monorail set for completion by 2025". 10 January 2020.
  3. ^ Sallehuddin, Qistina (27 June 2023). "No plans to revive the suspended monorail project". New Straits Times. Retrieved 27 June 2023.
  4. "Transportation Study for the Putrajaya Monorail Project - Perunding Trafik Klasik". ptk.my.
  5. "Putrajaya". Archived from the original on 18 April 2007. Retrieved 30 April 2007.
  6. "Kajang-Putrajaya rail link may be revived".
  7. "Putrajaya Monorail Construction - August 13, 2005 Page Two of Two". Retrieved 30 April 2007.
  8. "Development Databank". Archived from the original on 27 September 2007. Retrieved 30 April 2007.
  9. "Utusan Malaysia Online - Home News". Archived from the original (asp) on 30 September 2007. Retrieved 30 April 2007.
  10. "Fresh bid to get Putrajaya monorail project back on track". Archived from the original on 2 April 2007. Retrieved 30 April 2007.
  11. "MMC proposes Putrajaya monorail" (asp). Retrieved 23 September 2016.
  12. "Putrajaya: Monorail RFP opens in three months". The Malaysian Reserve. 1 October 2020. Retrieved 4 July 2021.
  13. "Tram service for Putrajaya within three years" (asp). 21 February 2016. Retrieved 21 February 2016.
  14. "Putrajaya and Cyberjaya to have tram service in three years" (asp). Retrieved 21 February 2016.
  15. "Trams for Putrajaya, Cyberjaya in three years?" (asp). Retrieved 21 February 2016.
  16. "Tram service for Putrajaya in the works" (asp). Retrieved 6 March 2018.

External links

Malaysia Rail transport in Malaysia
Overview
Fares and ticketing
Statutory authority
Major Operators
Inter-city rail
Main Lines
Current
Future
Planning
Shelved
Services
Commuter rail
Suburban
Current
Airport Link
Current
Metro rail
LRT
Current
Future
Planning
MRT
Current
Planning
ART
Future
Monorail
Current
Planning
Border link
Current
Future
Other rail
People mover
Funicular
Gondola lift
Rolling stock
& manufacturers
Inter-city
Commuter
Airport link
LRT
MRT
Monorail
Others
Depots
Current
Future
Related articles
Greater KL/Klang Valley Area rail transit stations
1 Batu Caves-Pulau Sebang Line
2 Tanjung Malim-Port Klang Line
3 Ampang Line
4 Sri Petaling Line
5 Kelana Jaya Line
6 KLIA Ekspres
7 KLIA Transit
8 KL Monorail
9 Kajang Line
10 KL Sentral-Terminal Skypark Line
11 Shah Alam Line
Phase 1
Opening 2025
Phase 2
12 Putrajaya Line
13 Circle Line
Opening 2028-2030
B1 BRT Sunway Line
Stations and services in italics are planned or under construction
Public transport in the Klang Valley
Rail
Klang Valley Integrated
Transit System
Commuter rail
LRT
MRT
Monorail
Airport rail link
High speed rail
Inter-city rail
Operators
Bus
BRT
OthersTaxi
Transit Hubs
Services in italics are planned or under construction
Urban rail transit in Southeast Asia
Indonesia Indonesia
Java
Sumatra
Lesser Sunda Islands
Laos Laos
Malaysia Malaysia
Peninsular Malaysia
East Malaysia
Myanmar Myanmar
Philippines Philippines
Luzon
Visayas
Mindanao
Singapore Singapore
Thailand Thailand
Bangkok Metropolitan
Provincial
Vietnam Vietnam
Note: Under construction & planned lines are in Italics
Categories: